December 2013
- Report Date
- December 2013
Infrastructure Programme Report for Programme Owner David Smyth
Section One: Programme Commentary, RAG and Resources Update
Section Two: Projects Not Started
Section Three: Projects In Progress
Section Four: Closed or Withdrawn Projects
Section One: Programme Commentary, RAG and Resources Update
Additional budget has been found to allow the programme to fnd the Business Data Recovery proposal.
The projected total for the year has the programme running over by 13 days, but 10 of these are held in the balance row as contingency so we are still able to work towards a balanced budget.


Section Two: Projects Not Started
| Project Info | Programme Manager's Commentary |
| AP34-041 Business Data Recovery and Storage Implementation |
https://www.projects.ed.ac.uk/planning/project/140 This proposal will implement the findings of the review of data recovery and storage requirements for IS Applications as part of a wider review by ITI. The review will have outlined the requirements for storage of business data for disaster recovery/backup, archival and replication purposes. The necessary technical infrastructure will have been provisioned during 12/13 period as a result of the review and this proposal will bring the Applications service under the revised process and facilities. Tony Weir will be developing the brief. The work is temporarily on hold due to conflicts with other priority work, but Tony has confirmed that it will happen in first half of 2014, and that it will be a procurement followed by an installation. The IS Apps effort involved for each project needs re-estimated. Currently this is a Small budget proposal.
|
Section Three: Projects in Progress
| Project Info | Project Managers Commentary | ||||||||||||||
ITS103 (AP34-038) Core Technology Updates. Category : C
Milestones
RAG Status GREEN
| Report completed by Stevie Conlon for December 2013 Achievements This Period
Issues
Next Steps
| ||||||||||||||
INF104 Application Infrastructure Upgrade Project Category: Complience Milestones
RAG Status AMBER | Report completed by Adam Wadee for December 2013 Achievements in Last Period
Issues
Next Steps
RAG status Amber as additional effort required to complete the project.
|
Section Four: Closed or Withdrawn Projects
| Project Info | Project Managers Commentary |
AP34-039 Development Tool Upgrades | Withdrawn on 30/8/13. https://www.projects.ed.ac.uk/planning/project/141 This was due to impact on programme budget from carry over 12/13 projects. However, we hope to be able to bring the project back into the 13/14 programme if budget, priority and new estimates allow.
The Division has built up reliance on a number of key products over the years to assist in project and service delivery. This project would apply relevant upgrades to the following products: JIRA JIRA has fallen a few version behind latest version, so it may be this upgrade is required. Whether a proejct is required remain to be re-assessed.
Greenhopper This is a small task to be done under APP004
Bamboo This is a small task that should be covered by current Support arrangements.
|
Implement New Database Tier | Report by David Watters This project was closed on 13th September 2013 Please see the Completion Report for further information.
|
ITS101 SAN Migration | Report by Karen Stirling This project was closed on 29th November 2013 Please see the Completion Report for further information. |
ITS095 Upgrade of Oracle SOA Suite | Report by Stevie Conlon The project was closed on the 7th November Please see the Completion Report for further information. |
