Section One: Programme Commentary, RAG and Resources Update

The Development Tools was withdrawn to balance the programme budget, allowing the completion of the carry over projects. However, due to the increased estimate for ITS103 (from 50 to 114 days), the programme has used up all its contingency.

The main challenge is to keep within the current budget so that started projects can all complete without the need for descoping or withdrawal.

The small AP34-041 Business Data Recovery and Storage Implementation project cannot now start without additional funding being found for the project.

The withdrawn Development Tools Upgrade in October could possibly be brought back into the prgoramme if funds and priority were established, but the effort needed may be small enough to allow it to be done under support.

 

 

 

 

 

 

 

 

 

 Section Two: Projects Not Started

Project InfoProgramme Manager's Commentary
AP34-041 Business Data Recovery and Storage Implementation

 

https://www.projects.ed.ac.uk/planning/project/140

This proposal will implement the findings of the review of data recovery and storage requirements for IS Applications as part of a wider review by ITI. The review will have outlined the requirements for storage of business data for disaster recovery/backup, archival and replication purposes. The necessary technical infrastructure will have been provisioned during 12/13 period as a result of the review and this proposal will bring the Applications service under the revised process and facilities.

Tony Weir will be developing the brief. The work is temporarily on hold due to conflicts with other priority work, but Tony has confirmed that it will happen in first half of 2014, and that it will be a procurement followed by an installation. The IS Apps effort involved for each project needs re-estimated. Currently this is a Small budget proposal.

Status is RED as there is in sufficient programme budget to fund this proejct.

 

 

  
  

Section Three: Projects in Progress

 

Project InfoProject Managers Commentary

ITS095  (AP12-031)

Upgrade of Oracle SOA Suite

 

Category:Discretionary

Milestones

 

07-Nov-2013Project Closure

RAG Status

GREEN

Report completed by Stevie Conlon for October 2013
 
 
 
 
Achievements This Period
  • DR test was completed using the Veeam tool. This has been agreed as the recovery option for SOA with ITI management ( Tony Weir and Gary Scobie).
  • DSOR milestone was completed and signed off as Operational Documentation was handed over and agreed with Tech Man and App Man

Issues

No issues

Next steps

  • Complete Closure Report and closure at WIS.

 

 

 

ITS101  (AP23-009)

SAN Migration

Category: Compliance

Milestones

06-Nov-2013Accommodation Services Migration Completed
15-Nov-2013DSOR & Closure

                                     

RAG Status

GREEN

Report completed by Karen Stirling for October 2013

Achievements in Last Period

  • SQL Maintenance Plan modified for Accommodation Services ACCM-DB-AT1 / ACCM-DB-KB1, backups successfully completed on Transaction Logs and Differentials. Weekly backups to be confirmed
  • Live migrations for Hosting Server KB-IIS-1 completed on 30th October
  • Copy over remaining data files on ACCM-DB- AT1 and ACCM-DB- KB1, a small number of files remaining
  • Completion Report issued for comments from Project Sponsor

 

Issues

  • PICCL raised detailing revised milestones dates for Accommodation Services, DSOR and Closure, and submitted to WIS for approval.
  • Due to permission issues on a number of folders within Hosting LIVE Server resulted in migration being rescheduled, PICCL raised to move date 8th Oct to 29th Oct

 

Next Steps

  • DSOR  and Closure sign offs
  • Completion Report submit to WIS for approval

 

ITS103 (AP34-038)

Core Technology Updates.

Category : C

 

Milestones

 

12-Nov-2013End of MISLIVE investigations
02-Dec-2013Development Environments complete
21-Jan-2014ASOR APPSLIVE, NEWSLIVE
28-Jan-2014Deploy APPS LIVE
04-Feb-2014Deploy NEWSLIVE
13-Feb-2014DSOR
17-Feb-2014Closure

 

 

RAG Status

GREEN

 

Report completed by Stevie Conlon for October2013
 
Achievements This Period
  • Scope and final budget agreed.
  • Brief and Planning Milestone completed and signed off

Issues

  • Stefan unable to complete the MISLIVE investigatios but this will not impact the main milestones

Next steps

  • Confirm all user groups happy with the dates communicated.
  • Ensure MISLIVE investigations complete.

INF104 Application Infrastructure Upgrade Project

Category: Complience  

Milestones

Target dateTitle
22-Nov-2013Assessment Complete
29-Nov-2013Strategy Document Review
06-Dec-2013Delivery (Strategy Document Complete)
20-Dec-2013Closure

 

 

 

RAG Status

GREEN

Report completed by Adam Wadee for October 2013

Achievements in Last Period

  • The objective of the project is to produce a strategy document detailing the options for migrating applications from the current infrastructure.  The outcomes of the document will be used to inform the relevant business areas about the need to migrate their applications to the new infrastructure.
  • The project brief has been aproved.
  • Development Technology are currently writing the strategy document with input from Production Management and ITI.

Issues

  • None

Next Steps

  • Complete the strategy document and review with key stakeholder groups.

 

 

 

 

 

 

 

Section Four: Closed or Withdrawn Projects

 

 

Project InfoProject Managers Commentary

AP34-039

Development Tool Upgrades

Withdrawn on 30/8/13.

https://www.projects.ed.ac.uk/planning/project/141

This was due to impact on programme budget from carry over 12/13 projects.

However, we hope to be able to bring the project back into the 13/14 programme if budget, priority and new estimates allow.

 

The Division has built up reliance on a number of key products over the years to assist in project and service delivery.

This project would apply relevant upgrades to the following products:

JIRA

JIRA has fallen a few version behind latest version, so it may be this upgrade is required. Whether a proejct is required remain to be re-assessed.

 

Greenhopper

This is a small task to be done under APP004

 

Bamboo

This is a small task that should be covered by current Support arrangements.

 

 

ITS100

Implement New Database Tier

Report by David Watters

This project was closed on 13th September 2013