September 2013
- Report Date
- September 2013
Section One: Programme Commentary, RAG and Resources Update
Section Two: Projects Not Started
Section Three: Projects In Progress
Section Four: Closed or Withdrawn Projects
Section One: Programme Commentary, RAG and Resources Update
The Development Tools was withdrawn to balance the programme budget, allowing the completion of the carry over projects. We will review the estimates and the requirements for the withdrawn Development Tools Upgrade in October to see if there is a possibility for bringing back this proposal into 13/14.
The main risk to the programme is the increased estimate for ITS103 (from 50 to almost 150 days), which cannot complete even with the withdrawal of AP34-041 Business Data Recovery project, which itself now is at severe risk.
Programme Owner will work with Programme Manager to resolve budget issues and clarify the situation of started, pending and withddrawn projects by end of October.


Section Two: Projects Not Started
| Project Info | Programme Manager's Commentary |
| AP34-041 Business Data Recovery and Storage Implementation |
https://www.projects.ed.ac.uk/planning/project/140 This proposal will implement the findings of the review of data recovery and storage requirements for IS Applications as part of a wider review by ITI. The review will have outlined the requirements for storage of business data for disaster recovery/backup, archival and replication purposes. The necessary technical infrastructure will have been provisioned during 12/13 period as a result of the review and this proposal will bring the Applications service under the revised process and facilities. Tony Weir will be developing the brief for the end of October. Small project.
Status isRED as the budget required to complete ITS103 would mean we have no budget for further work this year.
|
Section Three: Projects in Progress
| Project Info | Project Managers Commentary | ||||||||||||||
ITS095 (AP12-031) Upgrade of Oracle SOA Suite
Category:Discretionary Milestones
RAG Status AMBER | Report completed by Stevie Conlon for September 2013 Achievements This Period
Issues No issues Next steps
The project is marked as Amber as DR solution to be documented and signed off by Tech Man.
| ||||||||||||||
ITS101 (AP23-009) SAN Migration Category: Compliance Milestones
RAG Status GREEN | Report completed by Karen Stirling for September 2013 Achievements in Last Period
Issues
Next Steps
| ||||||||||||||
ITS103 (AP34-038) Core Technology Updates. Category : C
Milestones
RAG Status RED
| Report completed by Stevie Conlon for September 2013 Achievements This Period
Issues
Next steps
| ||||||||||||||
INF104 Application Infrastructure Upgrade Project Category: Complience Milestones
RAG Status GREEN | Report completed by Adam Wadee for September 2013
Achievements in Last Period
Issues
Next Steps
|
Section Four: Closed or Withdrawn Projects
| Project Info | Project Managers Commentary |
AP34-039 Development Tool Upgrades | Withdrawn on 30/8/13. https://www.projects.ed.ac.uk/planning/project/141 This was due to impact on programme budget from carry over 12/13 projects. However, we hope to be able to bring the project pack into the 13/14 programme if budget, priority and new estimates allow.
The Division has built up reliance on a number of key products over the years to assist in project and service delivery. This project would apply relevant upgrades to the following products: JIRA Greenhopper Bamboo
|
Implement New Database Tier | Report by David Watters This project was closed on 13th September 2013 Please see the Completion Report for further information.
|