Report for August 2019

Report Date
August 2019

Section One: Programme Commentary, RAG and Resources Update

Commentary

The overall status of the HRS Programme is RED , with the GDPR project reporting RED and the HESA project reporting GREEN this month.

During August:

  • The GDPR project re-estimated a mirroring solution to align to an emerging requirement from REF
  • The HESA project ran the final HESA extract in the LIVE environment and started work on data fixes

Please note that the project RAG status is following the guidelines available on the Project RAG status guidance page.

Forward Look - August 2019

 

Resources to end August 2019

 

Section Two: Projects Not Started and Start of Year

Project Info Programme Manager's Commentary and Start of Year Position
AP90-033 HESA Staff Return 19/20 to be started later this academic year - approx March 2020

The budget for the HRS programme for 2019/20 is set at 242 days from core allocation; this breaks down as 16 days for programme/portfolio management, 220 days for the HESA projects and 6 days for the contingency.

  • HRS096 is a continuing project from session 18/19; budget is to be allocated from this session's allocation once the estimated remaining effort has been confirmed.
AP Number / Project Code Title Funding Start of Year Programme Allocation Current Programme Allocation Unplanned (No Budget) Start Planning Delivery Closure
HRSP01 HRSP01 19/20 Human Resources (excluding Payroll) Programme Mgmt Core 16 16          
HRS096 HR GDPR Updates Core 0 0 TBC 07/11/17 24/08/18 TBC TBC
HRS097 HR HESA Staff Return 18/19 Core 20 20   08/03/19 07/05/19 30/09/19 06/12/19
AP90-033 HESA Staff Return 19/20 Core 200 200   TBC TBC TBC TBC
HRSCFC1 19/20 Human Resources (excluding Payroll) Programme Contingency - Core Funded Core 6 6          
HRSSFC2 19/20 Human Resources (excluding Payroll) Programme Contingency - Sponsor Funded Core 0 0          
  Total   242 242          

 

Section Three: Projects in Progress

Project Info

Project Managers Commentary

 

HRS096 GDPR Updates for eRecruitment

 
Milestones

TBC

RAG Status: Red

 

Report by Ken Miller for August 2019

Achievements this Period

  • Further analysis regarding REF requirements highlighted their need of unanonymised data from 01/01/2007.  This was 7 years earlier than had been expected.
  • Initial estimate of effort to mirror PPIPMI universe significantly greater than expected.  This was due to the evolution of the PPIPMI being such that the mirroring process entailed significant manual effort.
  • Further investigation has indicated a more manageable estimate of effort.  This has to be finalised and raised with HR. 

Issues

  • Budget for effort in 2019/20 has yet to be approved.

Next Steps

  • Agree revised project tasks and timescales to be confirmed and raised with HR.
  • Raise revised schedule at WIS.
HRS097 HR/HESA Staff Return 2018/19

 

Milestones :

Milestone Date
Submit HESA Return (Major) 30-Sep-2019
Commit 03-Oct-2019
Final Submission 29-Oct-2019
Closure (Major) 06-Dec-2019

 

RAG Status : Green

 

 

Report by Anne Mathison for August 2019

Achievements

  • Received the final 2 files from GaSP before the 9-August (8-Aug)
  • Received and ran the final cost centre files
  • Supported running of the HESA return in LIVE
  • Ran the final HESA extract
  • HR have made good progress on the required data fixes
  • HR have completed resolving the majority of errors

Issues

  • None

Next Steps

  • Support running of the HESA return in LIVE, if required
  • About 200 data fixes left and 450 will be covered by the HESA switch
  • HR hope to complete the remaining required data fixes, potentially by 6-Sep
  • Then the 'Submit HESA Return'  milestone can be completed, likely to be prior to 20-Sep

 