Report for April 2019
- Report Date
- April 2019
Report compiled by Ben Armstrong (IS Apps Programme Manager) for Susan McLaren (HRS Programme Owner).
Section One: Programme Commentary, RAG and Resources Update
Commentary
The overall status of the HRS Programme is AMBER, with the GDPR project reporting AMBER and the HESA project, GREEN.
During April:
- A fix was implemented for the Phase 1 anonymisation requirement under the GDPR project and is awaiting user acceptance testing; and further discussions were held regarding Phase 2 (EDW) but remain unresolved. A request has been made for additional budget to complete Phase 1.
- Planning continued for the HESA project, with the project brief being revised and signed off; and initial estimates put forward to implement the requirements in scope
Please note that the project RAG status is following the guidelines available on the Project RAG status guidance page.
Forward Look - April 2019
Resources to end April 2019
Section Two: Projects Not Started
Project Info | Programme Manager's Commentary |
---|---|
None noted | N/A |
Section Three: Projects in Progress
Project Info |
Project Managers Commentary | ||||||||||||||||||||||||||||||||||||||||
HRS096 GDPR Updates for eRecruitment Milestones
RAG Status: AMBER
|
Report by Ken Miller for April 2019Achievements this Period
Issues
Next Steps
|
||||||||||||||||||||||||||||||||||||||||
HRS097 HR/HESA Staff Return 2018/19
Milestones
RAG Status : GREEN |
Report by Anne Mathison for April 2019Achievements
Issues
Next Steps
|
Section Four: Closed or Withdrawn Projects
Project Info | Project Managers Commentary |
---|---|
HRS094 HESA Staff Return 17/18 | This project started on 22 November 2017 and was closed on 23 November 2018. The Closure Report is available to view. |