Report for December 2018
- Report Date
- December 2018
Report compiled by Muriel Mewissen (IS Apps Programme Manager) for Susan McLaren (HRS Programme Owner).
Section One: Programme Commentary, RAG and Resources Update
Commentary
During December, there was little activity in the programme following as HRS096 GDPR Updates for eRecruitment deployment to LIVE is scheduled for March 2019 to allow GaSP enough time in UAT to review the data after anonymisation.
The overall USG Other Programme status is GREEN.
Please note that the project RAG status is following the guidelines available on the Project RAG status guidance page.
Forward Look - December 2018
Resources to end December 2018
Section Two: Projects Not Started
Project Info | Programme Manager's Commentary |
---|---|
HESA Staff Return 18/19 | To be started in February 2019. |
Section Three: Projects in Progress
Project Info |
Project Managers Commentary | ||||||||||||
HRS096 GDPR Updates for eRecruitment Milestones
RAG StatusAMBER |
Report by Ken Miller for December 2018Achievements this Period
Issues
Next Steps
|
Section Four: Closed or Withdrawn Projects
Project Info | Project Managers Commentary |
---|---|
HRS094 HESA Staff Return 17/18 | This project started on 22 November 2017 and was closed on 23 November 2018. The Closure Report is available to view. |