Report for November 2018
- Report Date
- November 2018
Report compiled by Muriel Mewissen (IS Apps Programme Manager) for Susan McLaren (HRS Programme Owner).
Section One: Programme Commentary, RAG and Resources Update
Commentary
During November,
- HRS094 HESA Staff Return 17/18 was successfully completed slightly ahead of schedule and under budget. The Closure Report is available to view.
- The anonymisation work has started in DEV & TEST for HRS096 GDPR Updates for eRecruitment. Deployment to LIVE has been moved from January to March 2019 to allow GaSP additional time in UAT to review the data after anonymisation.
A change in budget spread was recorded in PRICCL 93. There is no change in the overall budget, but an increase in the contingency from 20 to 58 days as days were released following planning of HRS096 and closure of HRS094. These are curren;ty earmarked to support the phase 2 follow on project to be identified in HRS096.
The overall USG Other Programme status is GREEN.
Please note that the project RAG status is following the guidelines available on the Project RAG status guidance page.
Forward Look - November 2018

Resources to end November 2018

Section Two: Projects Not Started
| Project Info | Programme Manager's Commentary |
|---|---|
| HESA Staff Return 18/19 | To be started in February 2019. |
Section Three: Projects in Progress
|
Project Info |
Project Managers Commentary | ||||||||||||
|
HRS094 HESA Staff Return 17/18 RAG StatusCLOSED |
Report by Anne Mathison for November 2018Achievements
Issues
Next Steps
|
||||||||||||
|
HRS096 GDPR Updates for eRecruitment Milestones
RAG StatusAMBER |
Report by Ken Miller for November 2018Achievements this Period
Issues
Next Steps
|
Section Four: Closed or Withdrawn Projects
| Project Info | Project Managers Commentary |
|---|---|
| HRS094 HESA Staff Return 17/18 | This project started on 22 November 2017 and was closed on 23 November 2018. The Closure Report is available to view. |