Report for March 2013
- Report Date
- March 2013
Nikki Stuart (IS Apps Programme Manager) for Lindsey Miller, Eilidh Fraser, Gordon Forbes (Programme Owners)
Section One: Programme Commentary, RAG and Resources Update
Section Two: Projects Not Started
Section Three: Projects In Progress
Section Four: Closed or Withdrawn Projects
Section One: Programme Commentary, RAG and Resources Update
Commentary
UPDATE on 8th April - HRS073 eRecruitment Phase 1b has been updated to a RED status. The supplier has failed to meet the early April delivery of Priority 1 and Bug Fix work and all remaining supplier milestones are currently at Risk. Matter has been escalated to Project Board and discussions are underway with Core's Senior Supplier to ascertain the current situation and confirm whether remaining milestones are achievable.
HRS068 - eRecruitment Lessons learned exercise had to be postponed to allow key people to attend an urgent Autoenrolment/Tax Year End Meeting. Due to leave and other commitements this exercise cannot be held until April
HRS070 - Closure delayed so as not to impact resourcing of HRS072 during critical phase. Closure reschdeuled for end April.
HRS071 - Project reviewed and no change to milestones or budget required for loss of lead developer. Build now complete.
HRS072 - Tax Year End, Auto Enrolment and all release Real Time Information patches applied to LIVE by the start of year. Patching now underway for JRE and milestones for the final security and RTI patches agreed.
HRS073 - Project green for March, however, Supplier has indicated that not all Priority 1 and Bug Fix deployments will be made available at the start of April as expected. Discussions underway with Supplier as it is not clear what the impact will be.
HRS074/AP23-053 - Project initiated with planning to formally start in April.
Section Two: Projects Not Started
Project Info | Programme Manager's Commentary |
AP23-053 Staff Development- Implementation Funded Planning tbc Delivery tbc RAG Status GREEN
| Plan tbc - will depend on outcome of procurement project
Dependencies Implementation requirements will depend on the outcome of the procurement project. |
Section Three: Projects in Progress
Project Info | Project Managers Commentary | ||||||||||||||
HRS068 (AP01-011) HR Sytsem R12 Upgrade
Category: Compliance Milestones
RAG Status BLUE
| Report by Nikki Stuart for March 2013
Achievements in Last Period
Issues
Project Status is blue as delivery is complete.
| ||||||||||||||
HRS070 (AP90-049 ) Procure and Implement New Recruitment System
Category: Discretionary
Milestones
RAG Status BLUE
| Report by Nikki Stuart for February 2013
Achievements in Last Period
Next Steps
Project Status is blue as delivery is complete.
| ||||||||||||||
HRS071 (AP23-006 ) HR HESA Staff Return 12/13
Category: Compliance
Milestones
RAG Status GREEN | Report by Jill Nicoll for March 2013 Achievements in last period: System Build work (excluding APEX forms) completed. Issues: Oracle canceled its course offering for the APEX software, which the project's second developer was scheduled to attend in late March. Oracle offered a place on the June course offering in London, but this would not have allowed the subsequent HESA forms development to meet the hard HESA milestones. The only other option offered by Oracle was that the University secure an additional course offering in April in Edinburgh, by booking four places on that course. IS Applications have secured this new course offering. However, its delay will mean that the APEX forms will not be completed in time for the planned release of the Build for UAT testing. It has been agreed with the Business Area Manager that the rest of the Build will be released on the agreed schedule, and that the APEX forms will follow when they become available. The project team has still not received the complete business requirement for deriving the LEVELS field. Since this phase of the Build is now complete, any subsequent changes to the preliminary business logic provided for this field will be raised through a Jira and applied during the UAT stage. The PPIP requirements, although completed as part of the project's Build stage, were subsequently removed from the project's scope by the Business Area Manager. The PPIP database and code changes that were applied by the second developer have therefore been removed. Next Steps: Business Area Manager to provide the full business logic required to derive LEVELS. Developers to attend Oracle APEX training. Second developer to build APEX forms. Build (excluding APEX forms) to be reviewed and signed off by ISA project team and managers. Build (excluding APEX forms) to be deployed to Test and Integration tested. Build (excluding APEX forms) to be released for UAT testing.
| ||||||||||||||
Oracle HR & Payroll Annual Patching
Category: Compliance Milestones
RAG Status Green | Report by Anne Mathison for March 2013Achievements in Last Period -
Issues
Next Steps
| ||||||||||||||
HRS073 eRecruitment Phase 1b
Category: Funded Milestones
RAG Status GREEN | Report by NIkki Stuart for March 13 Achievements in Last Period
Issues
Next Steps
| ||||||||||||||
RS074 (AP23-053) Staff Development System- Procurement Funded
Milestones To be planned in April
RAG Status GREEN | Report by NIkki Stuart for March 13
Achievements in Last Period
Milestones still to be planned
|
Section Four: Closed or Withdrawn Projects
Project Info | Project Managers Commentary |
Project Code AP23-007 Project Title HR Real Time Tax Year End 12/13
Compliance | Report by Nikki Stuart This project was withdrawn on 19th October 2012
The deliverables and revised estimated effort for these have been merged with teh Tax Year End Project for the newly named HR & Payroll Annual Maintenance project. Please see the PRICCL log for further details https://www.projects.ed.ac.uk/programme/hr/issues/3
|