Report for October 2019
- Report Date
- October 2019
Report for September 2019
Report compiled by Andy Stewart (IS Apps Programme Manager) for Candice Schmid (Programme Owner)
Section One: Programme Commentary, RAG and Resources Update
During October
- Both active projects are progressing into the Build phase after successfully completing their respective planning phases this month
Forward Look

Resource Position

Section Two: Projects Not Started
| Project Info | Programme Manager's Commentary |
|
|
|
Section Three: Projects in Progress
| Project Info | Project Managers Commentary | ||||||||||||||
|
Cardinus Upgrade Category: Discretionary Milestone
RAG Status: Green
|
Report by Andy Stewart for October 2019 Achievements this Period
Issues
Next Steps
|
||||||||||||||
|
eOPAS Upgrade Category: Discretionary Milestone
RAG Status: GREEN |
Report by Andy Stewart for October 2019 Achievements this Period
Issues
|
Section Four: Closed or Withdrawn Projects
| Project Info | Project Managers Commentary |
|
The project was closed in August 2019. |
|
| HAS005 Fire Management System Procurement |
The project was closed on 27/09/19 |