Report for October 2019
- Report Date
- October 2019
Report for September 2019
Report compiled by Andy Stewart (IS Apps Programme Manager) for Candice Schmid (Programme Owner)
Section One: Programme Commentary, RAG and Resources Update
During October
- Both active projects are progressing into the Build phase after successfully completing their respective planning phases this month
Forward Look
Resource Position
Section Two: Projects Not Started
Project Info | Programme Manager's Commentary |
|
|
Section Three: Projects in Progress
Project Info | Project Managers Commentary | ||||||||||||||
Cardinus Upgrade Category: Discretionary Milestone
RAG Status: Green
|
Report by Andy Stewart for October 2019 Achievements this Period
Issues
Next Steps
|
||||||||||||||
eOPAS Upgrade Category: Discretionary Milestone
RAG Status: GREEN |
Report by Andy Stewart for October 2019 Achievements this Period
Issues
|
Section Four: Closed or Withdrawn Projects
Project Info | Project Managers Commentary |
The project was closed in August 2019. |
|
HAS005 Fire Management System Procurement |
The project was closed on 27/09/19 |