Report for August 2019

Report Date
August 2019

Report for August 2019

Report Date
August 2019

Report compiled by Andy Stewart  (IS Apps Programme Manager) for Candice Schmid (Programme Owner)

Section One: Programme Commentary, RAG and Resources Update

During August

  • Fire Safety Management System Procurement - project is now moving to closure 
  • COSHH Health Passport System Enhancements - project has been closed 
  • Cardinus Upgrade - project has now commenced 
  • eOPAS Upgrade - the business has advised that funding is available for this project and would like to commence 

The programme budget at the start of the year was set at 231 days.  However, after adjustments for HAS005 and HAS006, the revised budget is 151 days 

 

Start of Year 

After Adjustments 

Programme Management 

12 days 

12 days (no change) 

HAS005: Fire Safety management System Procurement 

140 days 

  • 60 days core funded  

  • 80 days sponsored funded 

11 days (estimated to complete closure). Balance of 49 days transferred to H&S Core Funded contingency 

HAS006: COSHH Updates 

0 days 

3 days (funded from H&S Core Funded contingency) 

AP90-007; Cardinus Update  

50 days 

50 days (no change) 

H&S Core Funded contingency  

3 days 

49 days (balance from HAS005 Core Funded days)  

H&S Sponsor Funded contingency 

26 days  

26 days (no change)  

Total 

231 days 

151 days  

Forward Look

Resource Position 

 

Section Two: Projects Not Started

 

Project Info Programme Manager's Commentary

 

 

 Section Three: Projects in Progress

 

Project Info Project Managers Commentary

HAS005 (AP89-003)

Fire Management System Procurement 

Category: Compliance 

 

Milestone Due Date
Exit Point - No Supplier Chosen 19-Jul-2019
Solution Deployment / Go Live Withdrawn
Project Closure 20-Sep-2019

 

RAG Status:  AMBER

Report by Richard Bailey for August 2019

Achievements this Period

  • The Project has reduced scope after the Business took an option to complete a Non-Competitive Agreement (NCA) and have identified a Supplier / have agreed to procure a solution.

 

Issues

 

Next Steps

  • Agree steps for Project Closure, WIS have requested as part of this that evidence be sought of:
    • A contract
    • An implementation plan
    • A completed Procurement checklist 
  • Draft Project Closure Report
  • Complete / agree Project Closure

 

HAS007

Cardinus Upgrade

Category: Discretionary

Milestone

Milestone Due Date
Planning 04-Oct-2019

RAG Status: Green

 

Report by Andy Stewart (on behalf of Sophie Milner) for August 2019

Achievements this Period

  • Conference call with supplier to determine technical aspects of 
    • integrating with central authentication system to enable all UoE employees to have access
    • single sign-on
  • Project estimations completed for 
    • integrating with central authentication system to enable all UoE employees to have access
    • single sign-on

Issues 

  • The project planning phase has been delayed due to the unavailability of the project manager 

Next Steps

  • Complete project planning phase 
  • Commence build phase of the project 

  Section Four: Closed or Withdrawn Projects

 

Project Info Project Managers Commentary

HAS006 COSHH Health Passport System (CHPS) Enhancements 

 The project started in April 2019 and closed on August 2019. The Closure Report is available to view.

AttachmentSize
Image icon 201907_resources.png28.3 KB
Image icon 201907_rag.png31.69 KB