Report for July 2019

Report Date
July 2019

Report compiled by Andy Stewart  (IS Apps Programme Manager) for Candice Schmid (Programme Owner)

Section One: Programme Commentary, RAG and Resources Update

During July

  • Project activity continues to be focused on the two active projects and has resulted in 
    • The move towards purchasing a cloud based solution for a new Fire Management System
    • The deployment of the COSHH updates into the live production environment
  • With regards the potential projects for 2019-2o
    • The Cardinus upgrade project is scheduled to commence in August and a project manager has been assigned 
    • Clarification of funding is still awaited with regards to 
      • eOPAS Upgrade 
      • Upgrades to AIR and RETAIN  (although clarification is still being sought regarding ColdFusion strategy)

 

Forward Look

Resource Position 

 

Section Two: Projects Not Started

 

Project Info Programme Manager's Commentary

AP89-006

Health and Safety Minor Enhancements

Funded

Planning: t.b.c.

Delivery: t.b.c.

Plan

 Whilst this project has been declared as part of the annual planning process  for 2018-19, it has been decided to defer this project to 2019-20.

Dependencies:

- will require considerable input from the Health and safety teams

- will require input from IS Applications Development Technology , Development and IS Applications Production Management

 Section Three: Projects in Progress

 

Project Info Project Managers Commentary

HAS005 (AP89-003)

Fire Management System Procurement 

Category: Compliance 

 

Milestone Due Date
Third Party ITT Response to Procurement Window Closed 11-Jul-2019
Third Party Solution Evaluation Completed / Supplier Chosen 19-Jul-2019
Exit Point - No Supplier Chosen 19-Jul-2019
End of Supplier Holding Period 22-Jul-2019
Agree T's & C's / Sign Contract With Chosen Supplier 22-Jul-2019
End of Procurement Phase 26-Jul-2019
Solution Implementation Planning Completed 15-Nov-2019
Solution Configuration / Implementation Completed 10-Jan-2020
Solution Acceptance / Sign Off 07-Feb-2020
Solution Deployment / Go Live 11-Feb-2020
Project Closure 28-Feb-2020

 

RAG Status:  AMBER

Report by Richard Bailey for July 2019

Achievements this Period

  • The Business took an option to complete a Non-Competitive Agreement (NCA) and have identified a Supplier / have agreed to procure a solution.
  • IS / The Project Team continue to work with H&S on a best efforts basis.
  • In conjunction with the NCA, an attempt was made to enable a full evaluation of the proposed solution using a slimmed down question set whereby:

    • A request was made regarding a technical specification to enable the infrastructure components to be reviewed  (not received)
    • A request was made regarding an SLA to enable post implementation support to be reviewed (not received)
    • The Information Security questions were submitted to ensure compliance regarding security and data protection (received 31st July p.m.)

 

Issues

 

Next Steps

  • IS will retrospectively review the slimmed down version of the IS Procurement Question set, focusing on Information Security, in order to highlight any potential risks to the Business.
  • Review Project actions and milestones
  • Agree steps for Project Closure

 

HAS006

COSHH Health Passport System Enhancements

Category: Discretionary

Milestone Due Date
Sprint 4 Completion 31-Jul-2019
Deployment Sign-off Review 07-Aug-2019
Project Closed 09-Aug-2019

Rag Status: GREEN

Report by Kevin Hone for July 2019

Achievements this Period

  • Project delivered. 

Issues

  • None. 

Next Steps

  • Project closure.  

  Section Four: Closed or Withdrawn Projects

 

Project Info Project Managers Commentary
HAS002 (AP67-020)

OPAS Upgrade & Migration

Project Closure Report

Closure Milestone

  • WIS approved 18-Jan-2019

HAS004

COSHH Updates

Project closure report

Project closure approval

AP89-005

Training Records

Project Withdrawn on 24th May 2019