Report for June 2019

Report Date
June 2019

Report compiled by Andy Stewart  (IS Apps Programme Manager) for Candice Schmid (Programme Owner)

Section One: Programme Commentary, RAG and Resources Update

During June

  • Project activity continues to be focused on the two active projects 
  • the following projects have been added into the 2019-20 plan.   Whilst all projects will require to be funded, clarification of funding has still to be determined with the exception of the Cardinus update project 
    • Fire Management System (continued from 2018-19)
    • Cardinus upgrade 
    • eOPAS Upgrade 
    • Upgrades to AIR and RETAIN  (although clarification is still being sought regarding ColdFusion strategy)

 

Forward Look

Resource Position 

 

Section Two: Projects Not Started

 

Project Info Programme Manager's Commentary

AP89-006

Health and Safety Minor Enhancements

Funded

Planning: t.b.c.

Delivery: t.b.c.

Plan

 Whilst this project has been declared as part of the annual planning process  for 2018-19, it has been decided to defer this project to 2019-20.

Dependencies:

- will require considerable input from the Health and safety teams

- will require input from IS Applications Development Technology , Development and IS Applications Production Management

 Section Three: Projects in Progress

 

Project Info Project Managers Commentary

HAS005 (AP89-003)

Fire Management System Procurement 

Category: Compliance 

 

Milestone Due Date
Third Party ITT Response to Procurement Window Closed 11-Jul-2019
Third Party Solution Evaluation Completed / Supplier Chosen 19-Jul-2019
Exit Point - No Supplier Chosen 19-Jul-2019
End of Supplier Holding Period 22-Jul-2019
Agree T's & C's / Sign Contract With Chosen Supplier 22-Jul-2019
End of Procurement Phase 26-Jul-2019
Solution Implementation Planning Completed 15-Nov-2019
Solution Configuration / Implementation Completed 10-Jan-2020
Solution Acceptance / Sign Off 07-Feb-2020
Solution Deployment / Go Live 11-Feb-2020
Project Closure 28-Feb-2020

 

RAG Status:  AMBER

Report by Richard Bailey for June 2019

Achievements this Period

  • ITT / Procurement is now closed with one response received that it is likely will be considered as not compliant
  • Evaluation at this stage has been suspended
  • The Project is considering options to move forward / make a decision

 

Issues

 

Next Steps

  • Make decision reference options to take Project forward and re-plan / action as required
  • Milestones and most likely budget will need to be re-planned / addressed

 

HAS006

COSHH Health Passport System Enhancements

Category: Discretionary

Milestone Due Date
Project Planned 10-May-2019
Sprint 1 Complete 16-May-2019
Sprint 2 Complete 06-Jun-2019
Sprint 3 Complete 27-Jun-2019
Project Executed 31-Jul-2019
Project Delivered 02-Aug-2019
Sprint 4 Completion 02-Aug-2019
Project Closed 09-Aug-2019

Rag Status: GREEN

Report by Kevin Hone for June 2019

Achievements this Period

  • Steady progress has been made on the project with development effort presently underway for a third and final agile sprint associated with development. 
  • The benefit of the agile approach to the project has been the ability to adapt to the raising of change requests and to support the revision of business priorities.  
  • All sprint releases have been deferred in order to allow more immediate focus on clearing and testing the backlog of work. There will now be a single release for the entire project.

Issues

  • As much as 25% of development resource time has been lost to competing and unplanned, higher prioritised project demands. In addition, time was also sacrificed to enable interview attendance at short notice over a number of days.  This resulted in a revised delivery focus on the 'Must Have' Jira issues with lower prioritised requirements dropped from a fourth sprint. 
  • Non-availability of production resource and further development resource conflict means that the earliest opportunity to deliver the project will now be the last week in July. A change request and additional risks have been raised for this date movement.

Next Steps

  • To complete development and testing  (sprint 3). 
  • To prepare for project implementation (sprint 4).

  Section Four: Closed or Withdrawn Projects

 

Project Info Project Managers Commentary
HAS002 (AP67-020)

OPAS Upgrade & Migration

Project Closure Report

Closure Milestone

  • WIS approved 18-Jan-2019

HAS004

COSHH Updates

Project closure report

Project closure approval

AP89-005

Training Records

Project Withdrawn on 24th May 2019