Report for February 2019

Report Date
February 2019

Report compiled by Andy Stewart  (IS Apps Programme Manager) for Candice Schmid (Programme Owner)

Section One: Programme Commentary, RAG and Resources Update

During February

  • Active Projects
    • The new Fire Management System project continues according to plan 
  • eOPAS Historic Data 
    • Work is now underway 
  • In Year Projects
    • Three in-year projects have been submitted and planning / resourcing review is now underway.  The projects relate to 
      • Cardinus Upgrade
      • eOPAS Upgrade 
      • CHPS Upgrade incorporating an interface with eOPAS 
  • The overall programme budget is currently 304 days, which includes 50 days for the planned eOPAS upgrade which has been delayed until release 6.0 is available 

 

Forward Look

Resource Position 

 

Section Two: Projects Not Started

 

Project Info Programme Manager's Commentary

AP89-005

Training Records

Funded

Planning: t.b.c.

Delivery: t.b.c.

 

Plan

 Whilst this project has been declared as part of the annual planning process  for 2018-19, it has been decided to defer this project to 2019-20.

Dependencies:

will require input from IS Applications Development Technology, Development  and IS Applications Production Management

AP89-006

Health and Safety Minor Enhancements

Funded

Planning: t.b.c.

Delivery: t.b.c.

Plan

 Whilst this project has been declared as part of the annual planning process  for 2018-19, it has been decided to defer this project to 2019-20.

Dependencies:

- will require considerable input from the Health and safety teams

- will require input from IS Applications Development Technology , Development and IS Applications Production Management

 Section Three: Projects in Progress

 

Project Info Project Managers Commentary

HAS005 (AP89-003)

Fire Management System Procurement 

Category: Compliance 

 

Milestone Due Date
Planning 18-Jan-2019
Final Procurement Question Set (Business) Determined 29-Mar-2019
Prior Information Notice (PIN) Completed / Procurement Approach Determined   29-Mar-2019
Business Requirements Defined 29-Mar-2019
Exit Point - No Interest Received From Third Party Suppliers 29-Mar-2019
Final Procurement Question Set (IS) Determined 29-Mar-2019
Third Party ITT Published / Response to Procurement Window Open 01-Apr-2019
Third Party ITT Response to Procurement Window Closed 21-Jun-2019
Third Party Solution Evaluation Completed / Supplier Chosen 23-Aug-2019
Exit Point - No Supplier Chosen 23-Aug-2019
End of Supplier Holding Period 06-Sep-2019
End of Procurement Phase 13-Sep-2019
Agree T's & C's / Sign Contract With Chosen Supplier 04-Oct-2019
Solution Implementation Planning Completed 15-Nov-2019
Solution Configuration / Implementation Completed 10-Jan-2020
Solution Acceptance / Sign Off 07-Feb-2020
Solution Deployment / Go Live 11-Feb-2020
Project Closure 28-Feb-2020

 

RAG Status: Green

Report by Richard Bailey for February 2019

Achievements this Period

  • Public Information Notification (PIN) period completed, with four expressions of interest received
  • Business Requirements / Existing Process Workshops are ongoing, draft Business procurement question sets for the ITT are close to completion
  • The Disability Information Officer has been engaged and the procurement questions for accessibility have been drafted 
  • It was agreed by both the Business Lead and Project Sponsor that the 'could have'Deliverable in the Project Brief "D8 - Personal Emergency Evacuation Plans (PEEP) - solution enables the recording, tracking and sharing of Personal Emergency Evacuation Plans" be removed from the scope of the Project

 

Issues

  • None

 

Next Steps

  • A Project Stakeholder / Business engagement meeting is calendared for: 19-Mar-2019, out of which those involved in the Procurement / question marking will be agreed / identified   
  • Complete the draft procurement question sets for the ITT, combining Business, accessibility and IS question sets
  • Determine procurement strategy

 

 Section Four: Closed or Withdrawn Projects

 

Project Info Project Managers Commentary
HAS002 (AP67-020)

OPAS Upgrade & Migration

Project Closure Report

Closure Milestone

  • WIS approved 18-Jan-2019

HAS004

COSHH Updates

Project closure report

Project closure approval