Report for October 2018

Report Date
October 2018

Report compiled by Andy Stewart  (IS Apps Programme Manager) for Candice Schmid (Programme Owner)

Section One: Programme Commentary, RAG and Resources Update

During October 

  • Current project activity during the month has focussed on re-planning the eOPAS upgrade after clarification received regarding the HR data feed 
  • Clarification on the planned projects for the current academic year have been clarified 
Project Scheduled to Commence   Comments
Fire Management System Yes  This project will proceed and will commence in November 
Training records No Project will be deferred to 2019-20 
Health and safety Minor Enhancements No Project will be deferred to 2019-20 
eOPS Upgrade Yes This  in-year project will be funded by Health and Safety and will commence on the completion of the current HAS002 eOPAS Upgrade project 
Cardinus  Upgrade No No plans to progress this progress this project at this time 
COSHH - eOPAS Interface Yes This in-year project will be funded by Health and Safety and will commence on the completion of the new OPAS Upgrade project 

 

Forward Look

Resource Position 

 

Section Two: Projects Not Started

 

Project Info Programme Manager's Commentary

AP89-003

Fire Management System

Core Funded

Planning: t.b.c.

Delivery: t.b.c.

 

Plan

This project has been declared as part of the annual planning process  for 2018-19 and is now scheduled to commence in November 2018

Dependencies:

- will require considerable input from the Fire Safety team in defining requirements and required business processes prior to entering any procurement process

- will require input from the Estates department and business partners throughout the  University

- will require input from the Procurement department

- will require input from IS Applications Development Technology , Development and IS Applications Production Management

AP89-005

Training Records

Funded

Planning: t.b.c.

Delivery: t.b.c.

 

Plan

 Whilst this project has been declared as part of the annual planning process  for 2018-19, it has been decided to defer this project to 2019-20.

Dependencies:

will require input from IS Applications Development Technology, Development  and IS Applications Production Management

AP89-006

Health and Safety Minor Enhancements

Funded

Planning: t.b.c.

Delivery: t.b.c.

Plan

 Whilst this project has been declared as part of the annual planning process  for 2018-19, it has been decided to defer this project to 2019-20.

Dependencies:

- will require considerable input from the Health and safety teams

- will require input from IS Applications Development Technology , Development and IS Applications Production Management

 Section Three: Projects in Progress

 

Project Info Project Managers Commentary

HAS002 (AP67-020)

OPAS Upgrade & Migration

Category: Compliance  

 

Date Milestone
26-Nov-2018 Deployment Signoff
30-Nov-2018 Close

 RAG Status :Green 

 

Report by Anne Mathison for October 2018

Achievements

  • Successfully decommissioned LIVE OPAS on October 1st
  • Having received clarification regarding the decision on the HR data transfer for specific fields it has been decided to 
    • update the current HR data feed to exclude the specified data fields.  User Acceptance Testing is currently being undertaken 
    • correction of the historic data transferred will be completed outwith this project and supplier will be contracted to complete this work after approval of the quote 
    • The implementation of the Portal and the sms text messaging facility will be de-scoped and completed as part of the next planned eOPAS upgrade 
    • the project will now close on the completion of the updated HT data feed

Issues

  • None

Next Steps

  • User Acceptance Testing of the HR data feed to be completed towards mid November 
  • Implementation of new HR data feed later in November 
  • Complete the project deployment signoff process
  • Complete closure report
  • Close project

 Section Four: Closed or Withdrawn Projects

 

Project Info Project Managers Commentary

HAS004

COSHH Updates

Project closure report

Project closure approval

AttachmentSize
Image icon hasoct.png40.64 KB
Image icon hasoct2.png38.53 KB
Image icon 201810b_rag.png33.93 KB

Programme Info