Report for July 2018

Report Date
July 2018

Report compiled by Andy Stewart  (IS Apps Programme Manager) for Candice Schmid (Programme Owner)

Section One: Programme Commentary, RAG and Resources Update

During July

Investigations regarding possible projects for 18/19 have continued with regards to;

  • Cardinus Health and Safety application
  • Integration betwen eOPAS and COSHH

Outline project planning schedule has been completed for 2018-19

Project Scheduled to Commence Comments
Migrate H&S ColdFusion Applications September 2018 Compliance Funding still to be confirmed
eOPAS Upgrade October 2018 New in-year sponsor funded project
Fire Management System September  / October 2018 Compliance Funding still to be confirmed
Training Records October 2018  
Cardinus Upgrade October / November 2018 New in-year sponsor funded project
Integrate Health Passport with Occupational Health January 2019 New in-year sponsor funded project
Health and Safety Minor Enhancements April / May 2019 Dependency on the completion of  the project - Migrate H&S ColdFusion Applications

Forward Look

Resource Position 

 

Section Two: Projects Not Started

 

Project Info Programme Manager's Commentary

 

 

Title

Content

 Section Three: Projects in Progress

 

Project Info Project Managers Commentary

HAS002 (AP67-020)

OPAS Upgrade & Migration

Category: Compliance  

Provisional Milestones to be agreed

Date Milestone
10-Aug-2018 Roll out Portal for first nominated area
24-Aug-2018 Deployment Signoff
31-Aug-2018 Close

 RAG Status :AMBER

 

Report by Anne Mathison for July 2018

Achievements

  • Reviewed milestones and budget to accommodate unexpected delays in Portal testing and the resolution of the remaining outstanding issues
    • Approval to extend project budget by 20 days into 2018-19
  • Portal testing progress
    • OH have completed portal testing in Test
    • HAS have completed portal testing in Test
    • Other users starting to look at the Portal
    • Portal user guides have been used, but still to be fully reviewed
  • Spirometry connectivity issue has been resolved  
  • Amplivov audio issue has been resolved
  • Termination date errors have been resolved
  • Integration with Mjog text messaging service remains unresolved
  • HR, OH and IS meeting held to discuss the nightly data transfer of personnel data into eOPAS.
    • HR agreed OH can continue to use the data until a decision has been agreed.

Issues

  • Personnel data transfer from HR to be resolved
  • Spirometry
    • It has been discovered that the additional requirements to import graphs of readings along with the generation of PDF's require an upgrade to the next version of eOPAS 

Next Steps

  • Resolve integration issues relating to Mjog light
  • Formal agreement to be  decided between HR and OH regarding the nightly data transfer of personnel data into eOPAS
  • Resolve remaining outstanding issues with Warwick
  • Termination date population to be queried with Warwick
  • Portal
    • complete testing within the Test environment
    • commence arrangements to site Portal on the live OH Website
    • portal user guides to be finalised
    • roll out portal to first nominated area
  • Plan on-site training day with the supplier to be arranged with regards to advanced searches
  • Decommission TEST and LIVE OPAS  during last week in August
  • Complete closure report

RAG Commentary

Personnel data transfer from HR to be resolved

HAS004 

COSHH Updates

Category: Discretionary 

 

Milestones:

Target Date Title
07-Aug-2018   Deploy Bug Fixes 
10-Aug-2018 Closure

 

 

 

RAG Status : GREEN

 

Report by Richard Bailey for July  2018

 

Achievements in Last Period

  • Two more production issues were identified since deployment to live, neither of these were as a result of the additional works requested by the Business, but were thought to be further items that were now noticeable as a result of fixing the time boxed support based issues on behalf of Application Management.  The Developer has a booking to complete these works w/c 30/07/2018.  These are being tracked in risk #5:  Pre-Existing LDAPIssue  

Issues

  • None

Next Steps

  • Sign off / deployment of fixes to the additional two production issues
  • Close Project

 Section Four: Closed or Withdrawn Projects

 

Project Info Project Managers Commentary

AP78-018

Health and Safety Minor Enhancements 

This is a holding project for minor enhancements that the H&S directorate would like to progress through 17/18. It is currently assumed that the work will be undertaken by the HAS001 and HAS003 projects. Once the budgeting is confirmed then this project is likely to be withdrawn.

Withdrawal approved by WIS on 06/10/17

 

HAS001 - COSHH Health Records

Project was closed on 8th December 2017

Closure approved by WIS

Closure Report

HAS003 - Retain - Monthly Reporting Enhancements

Project was closed on 11th May 2018

Closure approved by WIS

Closure Report