Report for June 2018

Report Date
June 2018

Report compiled by Andy Stewart  (IS Apps Programme Manager) for Candice Schmid (Programme Owner)

Section One: Programme Commentary, RAG and Resources Update

During June, 

The defined functional changes to COSHH have been successfully implemented on the Live environment. 

Investigations regarding possible projects for 18/19 have commenced with regards to;

  • Cardinus Health and Safety application
  • Integration betwen eOPAS and COSHH

Outline project planning schedule has been completed for 2018-19

Project Scheduled to Commence Comments
Health and Safety Minor Enhancements August 2018  
Fire Management System September 2018 Compliance Funding still to be confirmed
Training Records October 2018  
Migrate H&S ColdFusion Applications January 2019 Compliance Funding still to be confirmed

Forward Look

Resource Position 

 

Section Two: Projects Not Started

 

Project Info Programme Manager's Commentary

 

 

Title

Content

 Section Three: Projects in Progress

 

Project Info Project Managers Commentary

HAS002 (AP67-020)

OPAS Upgrade & Migration

Category: Compliance  

Provisional Milestones to be agreed

Date Milestone
10-Aug-2018 Roll out Portal for first nominated area
24-Aug-2018 Deployment Signoff
31-Aug-2018 Close

 RAG Status : RED

 

Report by Anne Mathison for June 2018

Achievements

  • Reviewed Milestones and budget
  • Completed DR testing
  • Updated TAD and handed over to production
  • Supplier resolved initial initial issue reported through Portal testing
  • Continued to investigate Spirometry issues with further input from IS Consultancy team
  • Service Level Agreement being updated

Issues

  • Unexpected issues encountered during initial Portal testing and forwarded to the supplier

  • Currently 6 outstanding issues including

    • Integration with Spirometry remains unresolved - although a manual workaround is in place

    • Integration with Amplivox Audio remains unresolved

    • Integration with Mjog text messaging service remains unresolved

Next Steps

  • Review Milestones and budget to accommodate unexpected delays in Portal testing and the resolution of the remaining outstanding issues
  • Update TAD and circulate to production
  • Resolve integration issues relating to Spirometry, Amplivox and Mjog light
  • Portal
    • to be tested within the Test environment
    • commence arrangements to site Portal on the live OH Website
    • portal user guides to be finalised
  • Planned on-site training day with the supplier to be arranged with regards to advanced searches
  • Plan date to  decommission TEST and LIVE OPAS  during last week in August

RAG Commentary

Change: Project to be extended by a further 6 weeks to resolve post go-live integration issues and Portal testing and deployment

HAS004 

COSHH Updates

Category: Discretionary 

 

Milestones:

Target Date Title
23-Jul-2018 Deployment of Changes
30-Jul-2018 Closure

 

 

 

RAG Status : GREEN

 

Report by Richard Bailey for June  2018

 

Achievements in Last Period

  • Work packages completed
  • Application deployed to live Wednesday 27/06/2018
  • Agreement with Production (application management) to pick up a number of current support based issues, time boxed to 3 days 

Issues

  • None

Next Steps

  • Two more production issues have been noted since deployment to live, neither of these were as a result of the additional works requested by the Business, but are thought to be further items that are now noticeable as a result of fixing the time boxed support based issues on behalf of Application Management.  Project to analyse these to see if time remains in the time boxed support budget to address these items.  The Developer has a placeholder booking to complete these works w/c 16/07/2018.  These are being tracked in risk #5:  Pre-Existing LDAP Issue 
  • Close Project

 Section Four: Closed or Withdrawn Projects

 

Project Info Project Managers Commentary

AP78-018

Health and Safety Minor Enhancements 

This is a holding project for minor enhancements that the H&S directorate would like to progress through 17/18. It is currently assumed that the work will be undertaken by the HAS001 and HAS003 projects. Once the budgeting is confirmed then this project is likely to be withdrawn.

Withdrawal approved by WIS on 06/10/17

 

HAS001 - COSHH Health Records

Project was closed on 8th December 2017

Closure approved by WIS

Closure Report

HAS003 - Retain - Monthly Reporting Enhancements

Project was closed on 11th May 2018

Closure approved by WIS

Closure Report