October 2017
- Report Date
- October 2017
Key activities:
Business:
EST109: Strategic Reporting. Risk: additional cost- 112 days. Project brief under review & funding agreed for additional 112 days. DM to seek further details on additional costs. Estates Maintenance and Space reporting will be early adopter of Enterprise Data Warehouse.
EST097: Purchase to Pay. Agreed on hold until Jan '18
EST100: BIM Strategic review: Agreed on hold until 2018/19
Estates Capital System
EST102: Estates Capital System Procurement. Responses and presentations scored. Request to make supplier visits (to be scheduled). Signoff of vendor expected by end '17
EST103: Estates Capital System Implementation. Technical Design held until application identified. Transition and Operating model plan underway to deliver 'must-haves'
EST104: Estates Capital System Embed & Optimise. On hold - expect to kick off at DP1 GoLive. Capture and agree priority for delivery of 'should/could haves'
Hard Services (Helpdesk and Maintenance):
EST098: Archibus upgrade. Risk: Test defect with Mass for resolution - plans unclear. Impact on GoLive TBC - we expect a move to early 20187 due to Christmas period.
EST099: Mobile Asset data capture. Risk: Data ageing in offsite environment. Requested clarity on ageing issues. Agreed on hold until post EST098. AP78-005: 'Archibus opportunities': Project to be initiated after EST099 to improve use of Archibus v23.1. Immediate priority is Asset management
Helpdesk - Group ticket access: Request from Helpdesk to support multi-ticket management. Seeking additional Business Analyst support from ISG
Hard Services (Energy)
EST095: Energy Systems Upgrade. Project requested closed. Energy team to pick up remaining issues. Closure report being prepared
Consolidated Energy Systems: Immediate need is to pick up outstanding issues from EST095 to ensure stability of current systems. Performing review of Energy systems with GF/DJ/MC/SS
Meterology: Meter-reading speed improved (25 minutes to 3) by improving database performance (new processors, memory). Meterology looking at database optimisation
Hard Services (Asbestos):
EST107: Asbestos Systems review: Asbestos systems review underway to create a future-proof Asbestos system and dataset. Handover completed to new Project Manager
Soft Services Consolidated Systems review:
Waste: Risk: Spreadsheet to be used for capture of waste tracking across several hundred waste generators - potential loss of data. Picking up with DB/GF
Security: Working with ISG and Security team on consolidated system (Door access, Alerting)
Consilidated Soft Services Systems: Meeting arranged with GF/DB to agree priorities for Soft Services
Mass 3rd party:
Customisations audit: Risk: High levels of customisations affecting system stability - impact on upgrade/BAU activities and Intellectual property stranglehold. Requested customisations audit from Mass Systems - delayed due to Single Points of Failure in Mass team. Chasing Mass for progress post EST098.
Mass - resolution planning: Risk: Lack of maturity in Mass technical team. Little clarity/visibility on plans for technical resolution (recent mobile issue in EST098). Request to Mass regarding improved methodology - on hold pending immediate EST098 issue
Account Management actions: Risk: Strategic risk to Estates Operations. Action plan agreed with Mass post June support renewal. Little response from Mass to date. Concerns to be raised in account management meeting
Technical Systems:
ESTP02: Archibus technical upgrade underway as part of EST098. Server technology, database, web server and Java upgrades underway. Within EST098 timelines.
ESTP03/ESTP04: Annual upgrade strategy to be agreed for Archibus and Perspective
SQL upgrade: Database version running out of support. Requiements to be confirmed
Programme areas:
Business-as-Usual Operating Model: TOM defined - will be rolled out as part of EPPM and included in future medium/large scale projects.
Data and Documentation: Immediate actions discussed as part of EPPM - this project will close and be incorporated into EPPM and subsequent medium/large projects
Programme/Portfolio Strategy: IS Strategy documentation being extended to support communication of immediate Estates IS direction and actions as part of Estates projects. clarify IS direction and 'whole-life' view, allowing Total Cost of Ownership planning.
Breakfast briefings: Team breakfast briefings to be recorded and linked online. Planned for November
External Activities:
Digital transformation. Monitor
Core Systems. Monitor and confirm immediate impact on Estates
EST108: CSG Fire Safety Systems: Project moved to CSG portfolio - closed here
Summary and latest Roadmap contained in Monthly report: estates_mis_programme_update_oct_17_v1_1.xlsx