Section One: Programme Commentary, RAG and Resources Update
During July .
Whilst the main focus throughout the month has been on the new Archibus upgrade project (EST098), progress continues to be made on all active projects.
In addition,
- the new Asset Management project (EST099) has commenced
- planning for 2017-18 is now underway with discussions being held with the business areas
During July, a total of 66 days were utilised by IS Applications across the programme, resulting in a revised monthly burn rate of 89 with a year to date burn rate of 99%.
Programme RAG Overview
Programme Resource
Section Two: Projects Not Started
The scheduled projects for 2016-17 are;
Project Info | Programme Managers Commentary |
AP56-021 Archibus Oracle Database Migration to Oracle 12c Core Funded Planning: September 2018 Delivery: April 2019 |
Plan - project now delayed to be undertaken within 2018-19 - After discussions with both Development Technology and Production Management, it has been agreed that the plan to upgrade to Oracle 12 can be delayed until 2018-19, providing a minor patch is applied to upgrade to Oracle 11.0.2.4. It is envisaged that this will be completed as part of the forthcoming Archibus software upgrade project AP67-066. Dependencies - should be run as a stand-alone project whilst no other Archibus related activity is being undertaken. Dependant on planning with regards the various Archibus related projects - will require a large commitment from Estates departments throughout all stages of the project - will require a significant input from IS Applications Development Technology team and the supplier Schneider throughout the project |
AP67-049 BIM Strategic Review Sponsor Funded Planning: October 2017 Delivery: April 2017 |
Plan - Discussions with Estates Building Services and Estates Development are on-going to determine if this project should commence. In taking into account the level of project activity currently on-going at this time, it has been agreed with the programme owner that this project should be deferred to 2017-18. Dependencies - will require a large commitment from Estates Building Services and Estates Development department throughout all stages of the project - will require input from a business analyst |
AP67-050 BIM Implementation Sponsor Funded Planning: September 2018 Delivery: April 2019
|
Plan - As this project is dependant on the outcomes of the BIM Strategic Review and given the amount of business activity, this project has now been deferred to 2018-19 Dependencies - will require the BIM Strategic Review project to have been completed - will require a large commitment from Estates Development department throughout all stages of the project - may require external consultancy to assist in implementing - will require input from IS Applications Development Technology team and the supplier Mass throughout the project |
AP67-052 Capital Budgeting Sponsor Funded Planning: n/a Delivery: n/a |
Plan - After discussions with the programme owner, this project has been withdrawn as all activity associated with this activity will be managed through the Estates Capital Systems programme
|
Section Three: Projects in Progress
Project Info | Project Managers Commentary | ||||||||||||||||||||||||
EST080 (AP45-016) Estates Department Help Desk Funded Milestones
RAG Status Blue
|
Report by Andrew Stewart for July 2017 Achievements
Issues
Next Steps
|
||||||||||||||||||||||||
EST092 (secured) (AP56-061) Estates Operational Reports Funded Milestones
RAG Status Amber |
Report by Andrew Stewart for July 2017
Issues
Next Steps
Whilst the project has delivered, the project has been assigned a RAG status of Amber due to the delay in closing the project |
||||||||||||||||||||||||
EST093 (AP56-060) Estates Strategic Reporting Funded Milestones 05-AUG-17 End of Re-planning 25-AUG-17 End of Analysis Review 29-MAR-18 Delivery Complete 19-APR-18 Project Close RAG Status Green |
Report by Chris Lawford for July 2017
Achievements in Last Period
Issues
Next Steps
The project is reporting GREEN.
|
||||||||||||||||||||||||
EST095 (AP56-062) Energy Systems Update Funded Milestones Rag Status Amber |
Report by Kevin Brennan for July 2017 Achievements in Last Period
Issues
Next Steps
Implement test environment The project has been assigned a RAG status of Amber due to the need to re-plan due to holidays and supplier availability |
||||||||||||||||||||||||
EST097 (AP67-033) Estates Financial Management Purchase to Payment Core Funded (initially) Milestones
RAG Status Red
|
Report by Andrew Stewart for July 2017 Achievements in Last Period
Issues
Next Steps
The project has been assigned a Red RAG status due to lack of progress in the completion of the planning and analysis as the formation of the business representatives of the project team has still to be confirmed
|
||||||||||||||||||||||||
EST098 Archibus 23.1 Upgrade Funded Milestones
RAG Status Amber |
Report by Chris Orrell for July 2017 Achievements in Last Period
Issues
Next Steps
RAG Commentary Timing is amber to highlight risks as the proposed go-live date has removed all contingency from the schedule and a detailed plan is required confirming, particularly Mass and Estates can perform required tasks within the allotted time. Cost is amber to reflect there has been an increase in project budget from the original proposal, this has been approved by Estates. Scope is green because a clear statement of scope now exists between IS, Estates and Mass. |
||||||||||||||||||||||||
Asset Management Funded Milestones
RAG Status Amber |
Report by Andrew Stewart for July 2017 Achievements in Last Period
Issues
Next Steps
The project has been assigned a RAG status of Amber due to unexpected issues being encountered and schedule to commence data capture next month
|
||||||||||||||||||||||||
|
Report by Andrew Stewart for June 2017
Achievements in Last Period
Issues
Next Steps
|
Section Four: Closed or Withdrawn Projects
Project Information | Project managers commentary |
EST083 (AP-45-013) Estates and Buildings Financial Management Process Review - Phase 2 |
Project closed on 4th November 2016 |
EST087 (AP56-062) Energy Systems Consolidation |
Project closed on 11th November 2016 |
AP67-048 Compliance Management Integration |
Project submitted for withdrawal to WIS on 20/01/17 |
EST094 (AP45-015) Struxureware |
Project closed on 20th February 2017 |
EST080 (AP45-016) Estates HelpDesk |
Project Info | Project Managers Commentary |
Section Five: Programme Risks
Date | Risk Ref. | Programme Risk | Rag Status | Risk Owner |
07/07/17 | 7 | Delay to Scheduled Project Start for AP67-066 Archibus Upgrade | Closed | |
07/07/17 | 8 | Delay to Scheduled Project Start for AP67-051 Asset Management | Closed | |
07/07/17 | 9 | Completion of 2016-17 Programme | Closed |
Section Six : Programme Meeting Minutes
This section details the minutes from the programme meetings held in 2015-16
Date | Comments |
15/09/15 | Minutes from programme meeting |
23/11/15 | Minutes from programme meeting |
20/04/16 | Minutes from programme meeting |
11/05/16 | Minutes from programme meeting |
17/08/16 | Minutes from programme meeting |
Attachment | Size |
---|---|
![]() | 42.49 KB |
![]() | 67.78 KB |
![]() | 60.35 KB |
![]() | 67.68 KB |
![]() | 78.58 KB |
![]() | 65.96 KB |
![]() | 78.87 KB |
![]() | 58.99 KB |
![]() | 67.94 KB |
![]() | 61.9 KB |
![]() | 37.36 KB |
![]() | 33.1 KB |
![]() | 82.75 KB |
![]() | 61.17 KB |
![]() | 39.63 KB |
![]() | 27.81 KB |
![]() | 51.15 KB |
![]() | 51.15 KB |
![]() | 51.39 KB |
![]() | 60.49 KB |
![]() | 51.19 KB |
![]() | 61.18 KB |
![]() | 61.32 KB |
![]() | 55.03 KB |