Section One: Programme Commentary, RAG and Resources Update
Section Two: Projects Not Started
Section Three: Projects In Progress
Section Four: Closed or Withdrawn Projects
Section Five: Programme Risk Register
Section Six: Programme Meeting Minutes
Section One: Programme Commentary, RAG and Resources Update
During June.
The main focus throughout the month has been on the Archibus facilities management environment, resulting in the closure of the helpdesk project (EST080) and the planning for the Archibus upgrade project (EST098).
The programme budget has been adjusted after an analysis of what can be feasibly achieved with the remainder of the academic year. This has resulted in a further reduction in the overall budget for 2016-17 from 972 days to 888 days. A summary of the budget changes can be viewed on the programme issue log
During June, a total of 42 days were utilised by IS Applications across the programme, resulting in a revised monthly burn rate (based on the revised budget) of 57%, with a year to date burn rate of 91%. The reduction in activity is attributed to the focus on closing down the HelpDesk project and lack of resource within both Estates and IS Applications.
Programme RAG Overview
Programme Resource
Section Two: Projects Not Started
The scheduled projects for 2016-17 are;
Project Info | Programme Managers Commentary |
AP56-021 Archibus Oracle Database Migration to Oracle 12c Core Funded Planning: September 2018 Delivery: April 2019 |
Plan - project now delayed to be undertaken within 2018-19 - After discussions with both Development Technology and Production Management, it has been agreed that the plan to upgrade to Oracle 12 can be delayed until 2018-19, providing a minor patch is applied to upgrade to Oracle 11.0.2.4. It is envisaged that this will be completed as part of the forthcoming Archibus software upgrade project AP67-066. Dependencies - should be run as a stand-alone project whilst no other Archibus related activity is being undertaken. Dependant on planning with regards the various Archibus related projects - will require a large commitment from Estates departments throughout all stages of the project - will require a significant input from IS Applications Development Technology team and the supplier Schneider throughout the project |
AP67-049 BIM Strategic Review Sponsor Funded Planning: October 2017 Delivery: April 2017 |
Plan - Discussions with Estates Building Services and Estates Development are on-going to determine if this project should commence. In taking into account the level of project activity currently on-going at this time, it has been agreed with the programme owner that this project should be deferred to 2017-18. Dependencies - will require a large commitment from Estates Building Services and Estates Development department throughout all stages of the project - will require input from a business analyst |
AP67-050 BIM Implementation Sponsor Funded Planning: September 2018 Delivery: April 2019
|
Plan - As this project is dependant on the outcomes of the BIM Strategic Review and given the amount of business activity, this project has now been deferred to 2018-19 Dependencies - will require the BIM Strategic Review project to have been completed - will require a large commitment from Estates Development department throughout all stages of the project - may require external consultancy to assist in implementing - will require input from IS Applications Development Technology team and the supplier Mass throughout the project |
AP67-052 Capital Budgeting Sponsor Funded Planning: n/a Delivery: n/a |
Plan - After discussions with the programme owner, this project has been withdrawn as all activity associated with this activity will be managed through the Estates Capital Systems programme
|
Section Three: Projects in Progress
Project Info | Project Managers Commentary | ||||
EST080 (AP45-016) Estates Department Help Desk Funded Milestones
RAG Status Blue
|
Report by Andrew Stewart for June 2017 Achievements
Issues
Next Steps
|
||||
EST092 (secured) (AP56-061) Estates Operational Reports Funded Milestones
RAG Status Blue |
Report by Andrew Stewart for June 2017 Achievements OP03 -Reactive and Planned Maintenance Response Times
OP33-eIT Costs by Team
Issues
Next Steps
|
||||
EST093 (AP56-060) Estates Strategic Reporting Funded Milestones 05-AUG-17 End of Re-planning 25-AUG-17 End of Analysis Review 29-MAR-18 Delivery Complete 19-APR-18 Project Close RAG Status Green |
Report by Chris Lawford for June 2017
Achievements
Issues
Next Steps
|
||||
EST095 (AP56-062) Energy Systems Update Funded Milestones Rag Status Amber |
Report by Kevin Brennan for June 2017 Achievements in Last Period
Issues
Next Steps
The project has been assigned a RAG status of Amber due to the need to re-plan due to holidays and supplier availability |
||||
|
|
||||
EST097 (AP67-033) Estates Financial Management Purchase to Payment Core Funded (initially) Milestones
RAG Status Red
|
Report by Andrew Stewart for June 2017 Achievements in Last Period
Issues
Next Steps
The project has been assigned a Red rag status due to the Project brief being delayed as a result of project manager resource conflict and delay in formulating the project team whilst noting concerns regarding Estates resourcing
|
||||
EST098 Archibus 23.1 Upgrade Funded Milestones
RAG Status Red |
Report by Chris Orrell for June 2017 Achievements in Last Period
Issues
Next Steps
RAG Commentary Neither timing, scope or budget have been fully agreed with Estates. A Project Brief was drafted with initial timing showing go-live 4 December for review at the 21st June Project Board. This meeting was cancelled and Estates have strongly requested an improvement to the go-live date. Tasks to improve the timing but to also progress key project tasks are ongoing. |
||||
Asset Management Funded Milestones
RAG Status Amber |
Report by Andrew Stewart for June 2017 Achievements in Last Period
Issues
Next Steps
The project has been assigned a RAG status of Amber due to unexpected issues being encountered and schedule to commence data capture next month
|
||||
|
Report by Andrew Stewart for June 2017
Achievements in Last Period
Issues
Next Steps
|
Section Four: Closed or Withdrawn Projects
Project Information | Project managers commentary |
EST083 (AP-45-013) Estates and Buildings Financial Management Process Review - Phase 2 |
Project closed on 4th November 2016 |
EST087 (AP56-062) Energy Systems Consolidation |
Project closed on 11th November 2016 |
AP67-048 Compliance Management Integration |
Project submitted for withdrawal to WIS on 20/01/17 |
EST094 (AP45-015) Struxureware |
Project closed on 20th February 2017 |
EST080 (AP45-016) Estates HelpDesk |
Project Info | Project Managers Commentary |
Section Five: Programme Risks
Date | Risk Ref. | Programme Risk | Rag Status | Risk Owner |
07/07/17 | 7 | Delay to Scheduled Project Start for AP67-066 Archibus Upgrade | Closed | |
07/07/17 | 8 | Delay to Scheduled Project Start for AP67-051 Asset Management | Closed | |
07/07/17 | 9 | Completion of 2016-17 Programme | Closed |
Section Six : Programme Meeting Minutes
This section details the minutes from the programme meetings held in 2015-16
Date | Comments |
15/09/15 | Minutes from programme meeting |
23/11/15 | Minutes from programme meeting |
20/04/16 | Minutes from programme meeting |
11/05/16 | Minutes from programme meeting |
17/08/16 | Minutes from programme meeting |
Attachment | Size |
---|---|
![]() | 42.49 KB |
![]() | 67.78 KB |
![]() | 60.35 KB |
![]() | 67.68 KB |
![]() | 78.58 KB |
![]() | 65.96 KB |
![]() | 78.87 KB |
![]() | 58.99 KB |
![]() | 67.94 KB |
![]() | 61.9 KB |
![]() | 37.36 KB |
![]() | 33.1 KB |
![]() | 82.75 KB |
![]() | 61.17 KB |
![]() | 39.63 KB |
![]() | 27.81 KB |
![]() | 51.15 KB |
![]() | 51.15 KB |
![]() | 51.39 KB |
![]() | 60.49 KB |
![]() | 51.19 KB |
![]() | 61.18 KB |