May 2017
- Report Date
- May 2017
Section One: Programme Commentary, RAG and Resources Update
Section Two: Projects Not Started
Section Three: Projects In Progress
Section Four: Closed or Withdrawn Projects
Section Five: Programme Risk Register
Section Six: Programme Meeting Minutes
Section One: Programme Commentary, RAG and Resources Update
During May.
Progress continues to be made on all active projects.
- EST080 - Estates Helpdesk: Work has continued with a view to bringing this project to conclusion
- EST092 - Operational Report: Reports have been deployed to live and project closure process has commenced
- EST093 - Strategic Reports: Project has now re-commenced after project sponsor assigned and approval given to proceed
- EST096 - Perspective Upgrade: The upgrade to the Security Incident Tracking system has been closed
- EST098 - Archibus Upgrade: Planning for the project is now underway
- AP67-051 - Asset Management: Initial project requirements have been clarified
In reviewing the potential activity that could achieved in the remaining months of the year, a review of all active projects resulted in the projected budget for 2016-17 being reduced from 1132 days to 972 days. A summary of the budget changes can be viewed on the programme issue log
During May, a total of 39 days were utilised by IS Applications across the programme, resulting in a revised monthly burn rate of 48%, with a year to date burn rate of 104%. The reduction in activity is attributed to the focus on closing down the HelpDesk project. The programme budget has been adjusted after an analysis of what can be feasibly achieved with the remainder of the academic year, resulting in a reduction of days
Programme RAG Overview
Programme Resource
Section Two: Projects Not Started
The scheduled projects for 2016-17 are;
Project Info | Programme Managers Commentary |
AP56-021 Archibus Oracle Database Migration to Oracle 12c Core Funded Planning: September 2018 Delivery: April 2019 |
Plan - project now delayed to be undertaken within 2018-19 - After discussions with both Development Technology and Production Management, it has been agreed that the plan to upgrade to Oracle 12 can be delayed until 2018-19, providing a minor patch is applied to upgrade to Oracle 11.0.2.4. It is envisaged that this will be completed as part of the forthcoming Archibus software upgrade project AP67-066. Dependencies - should be run as a stand-alone project whilst no other Archibus related activity is being undertaken. Dependant on planning with regards the various Archibus related projects - will require a large commitment from Estates departments throughout all stages of the project - will require a significant input from IS Applications Development Technology team and the supplier Schneider throughout the project |
AP67-049 BIM Strategic Review Sponsor Funded Planning: October 2017 Delivery: April 2017 |
Plan - Discussions with Estates Building Services and Estates Development are on-going to determine if this project should commence. In taking into account the level of project activity currently on-going at this time, it has been agreed with the programme owner that this project should be deferred to 2017-18. Dependencies - will require a large commitment from Estates Building Services and Estates Development department throughout all stages of the project - will require input from a business analyst |
AP67-050 BIM Implementation Sponsor Funded Planning: September 2018 Delivery: April 2019
|
Plan - As this project is dependant on the outcomes of the BIM Strategic Review and given the amount of business activity, this project has now been deferred to 2018-19 Dependencies - will require the BIM Strategic Review project to have been completed - will require a large commitment from Estates Development department throughout all stages of the project - may require external consultancy to assist in implementing - will require input from IS Applications Development Technology team and the supplier Mass throughout the project |
AP67-051 Asset Management Sponsor Funded Planning: March 2017 Delivery: August 2017 |
Plan - project was scheduled to commence in April 2017 - As a result of discussions with the business, the scope of this project will be mainly focused around the development of a solution to capture asset data and subsequently upload into Archibus. As a result of discussions with Building Services and Mass, it has been agreed that the asset data capture function will be undertaken using an amended version of the mobile application and a stand-alone externally hosted version of WebCentral 23.1. The data captured will be eventually imported into the UoE environment as part of the version 23.1 upgrade. Dependencies - will require a large commitment from Estates Technical Services department throughout all stages of the project - will require input mainly from IS Applications Project Services and the supplier Mass throughout the project |
AP67-052 Capital Budgeting Sponsor Funded Planning: n/a Delivery: n/a |
Plan - After discussions with the programme owner, this project has been withdrawn as all activity associated with this activity will be managed through the Estates Capital Systems programme
|
Section Three: Projects in Progress
Project Info | Project Managers Commentary | ||||||||||||
EST080 (AP45-016) Estates Department Help Desk Funded
Milestones
RAG Status Blue
|
Report by Andrew Stewart for May 2017 Achievements in Last Period
Issues
Next Steps
|
||||||||||||
EST092 (secured) (AP56-061) Estates Operational Reports Funded Milestones
RAG Status Blue |
Report by Andrew Stewart for May 2017 Achievements in Last Period During the month all the required report were deployed to the Live environment thus enabling
Issues
Next Steps
|
||||||||||||
EST093 (AP56-060) Estates Strategic Reporting Funded Milestones
RAG Status Green |
Report by Chris Lawford for May 2017 Achievements in Last Period
Issues
Next Steps
|
||||||||||||
EST095 (AP56-062) Energy Systems Update Funded Milestones Rag Status Green |
Report by Andrew Stewart for May 2017 Achievements in Last Period
Issues
Next Steps
|
||||||||||||
EST096 (AP67-069) Perspective Upgrade Funded Milestones
RAG Status Blue |
Report by Chris Orrell for May 2017 Achievements in Last Period
Issues
Next Steps
|
||||||||||||
EST097 (AP67-033) Estates Financial Management Purchase to Payment Core Funded (initially) Milestones
RAG Status Red
|
Report by Andrew Stewart for May 2017 Achievements in Last Period
Issues
Next Steps
The project has been assigned a Red rag status due to lack of progress.
|
||||||||||||
EST098 Archibus 23.1 Upgrade Funded Milestones
RAG Status Amber |
Report by Chris Orrell for May 2017 Achievements in Last Period
Issues
Next Steps
A project brief or agreed timescale have yet to be prepared. There is currently a concern regarding the required delivery date of September, as initially stated by the Estates department. . |
||||||||||||
|
Report by Andrew Stewart for May 2017
Achievements in Last Period
Issues
Next Steps
|
Section Four: Closed or Withdrawn Projects
Project Information | Project managers commentary |
EST083 (AP-45-013) Estates and Buildings Financial Management Process Review - Phase 2 |
Project closed on 4th November 2016 |
EST087 (AP56-062) Energy Systems Consolidation |
Project closed on 11th November 2016 |
AP67-048 Compliance Management Integration |
Project submitted for withdrawal to WIS on 20/01/17 |
EST094 (AP45-015) Struxureware |
Project closed on 20th February 2017 |
Project Info | Project Managers Commentary |
Section Five: Programme Risks
Date | Risk Ref. | Programme Risk | Rag Status | Risk Owner |
10/02/17 | 7 | Delay to Scheduled Project Start for AP67-066 Archibus Upgrade | Amber | Andrew Stewart |
10/02/17 | 8 | Delay to Scheduled Project Start for AP67-051 Asset Management | Amber | Andrew Stewart |
10/02/17 | 9 | Completion of 2016-17 Programme | Amber | Andrew Stewart |
Section Six : Programme Meeting Minutes
This section details the minutes from the programme meetings held in 2015-16
Date | Comments |
15/09/15 | Minutes from programme meeting |
23/11/15 | Minutes from programme meeting |
20/04/16 | Minutes from programme meeting |
11/05/16 | Minutes from programme meeting |
17/08/16 | Minutes from programme meeting |
Attachment | Size |
---|---|
![]() | 42.49 KB |
![]() | 67.78 KB |
![]() | 60.35 KB |
![]() | 67.68 KB |
![]() | 78.58 KB |
![]() | 65.96 KB |
![]() | 78.87 KB |
![]() | 58.99 KB |
![]() | 67.94 KB |
![]() | 61.9 KB |
![]() | 37.36 KB |
![]() | 33.1 KB |
![]() | 82.75 KB |
![]() | 61.17 KB |
![]() | 39.63 KB |
![]() | 27.81 KB |
![]() | 51.15 KB |
![]() | 51.15 KB |
![]() | 51.39 KB |
![]() | 60.49 KB |