February 2017
- Report Date
- February 2017
Section One: Programme Commentary, RAG and Resources Update
Section Two: Projects Not Started
Section Three: Projects In Progress
Section Four: Closed or Withdrawn Projects
Section Five: Programme Risk Register
Section Six: Programme Meeting Minutes
Section One: Programme Commentary, RAG and Resources Update
During February.
Progress continues to be made on all active projects.
- EST080 - Work is on-going to bring the project to conclusion
- EST094 - The Struxureware Project has been successfully delivered and closed
There are two specific projects within the programme that require action.
- EST093 - Strategic Reporting: A new project sponsor will be required to direct this project forward
- AP67-051 - Asset Management: A clear strategy requires to be defined to enable the Business Services Team to progress with their asset capture requirements.
As part of the on-going review of the programme, a number of changes, as noted below, has resulted in the programme budget being reduced by 38 days to 1132 days
- EST080 - An additional 62 days is required with regards the additional activity during the go-live phase and the subsequent post go-live activities towards closure
- EST092 - An additional 10 days to complete the testing and implementation of the reports
- EST094 - Project completed 10 days under budget
- AP67-049 - BIM Strategic Review - project deferred to 2017-18, resulting in a reduction of 50 days
- AP67-052 Capital Budgeting - project to be withdrawn, resulting in a reduction of 50 days
There is still a degree of uncertainty with regards to the effort required this year for the following projects, which may result in further adjustments to the overall programme budget
- AP67-066 Archibus Upgrade. Budget is currently 75 days, but still uncertainty when this project can commence
- AP67-051 Asset Management. Budget is currently 50 days, but still uncertainty regarding the project scope
During February, a total of 64 days were utilised by IS Applications across the programme, resulting in a monthly burn rate of 65%, with a year to date burn rate of 89%. The reduction in activity is attributed to the reduction in activity associated with the HelpDesk and the Purchase To Pay just commencing.
There is still a requirement for the business to clarify if the following projects will be undertaken this year namely;
Programme RAG Overview
Programme Resource
Section Two: Projects Not Started
The scheduled projects for 2016-17 are;
Project Info | Programme Managers Commentary |
AP56-021 Archibus Oracle Database Migration to Oracle 12c Core Funded Planning: September 2018 Delivery: April 2019 |
Plan - project now delayed to be undertaken within 2018-19 - After discussions with both Development Technology and Production Management, it has been agreed that the plan to upgrade to Oracle 12 can be delayed until 2018-19, providing a minor patch is applied to upgrade to Oracle 11.0.2.4. It is envisaged that this will be completed as part of the forthcoming Archibus software upgrade project AP67-066. Dependencies - should be run as a stand-alone project whilst no other Archibus related activity is being undertaken. Dependant on planning with regards the various Archibus related projects - will require a large commitment from Estates departments throughout all stages of the project - will require a significant input from IS Applications Development Technology team and the supplier Schneider throughout the project |
AP67-066 Archibus Upgrade Sponsor Funded Planning: April 2017 Delivery: August 2017 |
Plan - Due to the delay in implementing the Estates helpdesk project, this project has been rescheduled to commence in March 2017 - requirement for the HelpDesk project to be operational - confirmed that Archibus 23.0 will be available according to the scheduled project start date - No change after mid-year review in January 2017 Dependencies - will require a large commitment from Estates departments throughout all stages of the project - will require input from IS Applications Development Technology team and the supplier Mass throughout the project |
AP67-049 BIM Strategic Review Sponsor Funded Planning: October 2017 Delivery: April 2017 |
Plan - Discussions with Estates Building Services and Estates Development are on-going to determine if this project should commence. In taking into account the level of project activity currently on-going at this time, it has been agreed with the programme owner that this project should be deferred to 2017-18. Dependencies - will require a large commitment from Estates Building Services and Estates Development department throughout all stages of the project - will require input from a business analyst |
AP67-050 BIM Implementation Sponsor Funded Planning: September 2018 Delivery: April 2019
|
Plan - As this project is dependant on the outcomes of the BIM Strategic Review and given the amount of business activity, this project has now been deferred to 2018-19 Dependencies - will require the BIM Strategic Review project to have been completed - will require a large commitment from Estates Development department throughout all stages of the project - may require external consultancy to assist in implementing - will require input from IS Applications Development Technology team and the supplier Mass throughout the project |
AP67-051 Asset Management Sponsor Funded Planning: March 2017 Delivery: August 2017 |
Plan - project was scheduled to commence in March 2017 - As a result of discussions with the business, the scope of this project will be mainly focused around the development of a solution to capture asset data and subsequently upload into Archibus. However, clarity is required as to the source of the solution, and these delays may now impact into the timescales required by the Business Services team. - No change after mid-year review in January 2017 Dependencies - will require a large commitment from Estates Technical Services department throughout all stages of the project - will require input from IS Applications Development Technology team and the supplier Mass throughout the project |
AP67-052 Capital Budgeting Sponsor Funded Planning: n/a Delivery: n/a |
Plan - After discussions with the programme owner, it has been agreed that this project should be withdrawn as all activity associated with this activity will be managed through the Estates Capital Systems programme Dependencies - project requirements and schedule will be dictated by the defined requirements regarding the work being undertaken by Faithful and Gould - will require a large commitment from Estates departments throughout all stages of the project - will require input from IS Applications Development teams and the supplier Mass throughout the project |
Section Three: Projects in Progress
Project Info | Project Managers Commentary | ||||||||||||||||||||||||||||
EST080 (AP45-016) Estates Department Help Desk Funded
Milestones
RAG Status Blue
|
Report by Andrew Stewart for February 2017 Achievements in Last Period
Issues
Next Steps
|
||||||||||||||||||||||||||||
EST092 (secured) (AP56-061) Estates Operational Reports Funded Milestones
RAG Status Amber |
Report by Nikki Hackett Reed for February 2017 Achievements this period OP02:
OP03:
OP33:
Issues
Next Steps Review and revise milestone to reflect delivery delays Delivery 30/03 Closure 13/04 OP02:
OP03:
OP033:
Deployment Sign-off and closure The project has been highlighted as UAT issues has resulted in the project delivery milestone being extended by a further month |
||||||||||||||||||||||||||||
EST093 (AP56-060) Estates Strategic Reporting 10-Mar-2017 Project Resumption Review RAG Status Suspended |
Report by Andrew Stewart for February 2017 Achievements in Last Period
Issues
Next Steps
The project is currently suspended
|
||||||||||||||||||||||||||||
EST094 (secured) (AP45-015) Struxureware Funded Milestones No milestones RAG Status Blue |
Report by Anne Mathison for February 2017 Achievements:
Issues
Next Steps
|
||||||||||||||||||||||||||||
EST095 (AP56-062) Energy Systems Update Funded Milestones
Rag Status Green |
Report by Andrew Stewart for February 2017 Achievements in Last Period
Issues
Next Steps
|
||||||||||||||||||||||||||||
EST096 (AP67-069) Perspective Upgrade Funded Milestones
RAG Status Green |
Report by Chris Orrell for February 2017 Achievements in Last Period
Issues
Next Steps
|
||||||||||||||||||||||||||||
EST097 (AP67-033) Estates Financial Management Purchase to Payment Core Funded (initially) Milestones
RAG Status Green |
Report by Andrew Stewart for February 2017 Achievements in Last Period
Issues
Next Steps
|
||||||||||||||||||||||||||||
|
Report by Andrew Stewart for February 2017
Achievements in Last Period
Issues
Next Steps
|
Section Four: Closed or Withdrawn Projects
Project Information | Project managers commentary |
EST083 (AP-45-013) Estates and Buildings Financial Management Process Review - Phase 2 |
Project closed on 4th November 2016 |
EST087 (AP56-062) Energy Systems Consolidation |
Project closed on 11th November 2016 |
AP67-048 Compliance Management Integration |
Project submitted for withdrawal to WIS on 20/01/17 |
EST094 (AP45-015) Struxureware |
Project closed on 20th February 2017 |
Project Info | Project Managers Commentary |
Section Five: Programme Risks
Date | Risk Ref. | Programme Risk | Rag Status | Risk Owner |
10/02/17 | 7 | Delay to Scheduled Project Start for AP67-066 Archibus Upgrade | Amber | Andrew Stewart |
10/02/17 | 8 | Delay to Scheduled Project Start for AP67-051 Asset Management | Amber | Andrew Stewart |
10/02/17 | 9 | Completion of 2016-17 Programme | Amber | Andrew Stewart |
Section Six : Programme Meeting Minutes
This section details the minutes from the programme meetings held in 2015-16
Date | Comments |
15/09/15 | Minutes from programme meeting |
23/11/15 | Minutes from programme meeting |
20/04/16 | Minutes from programme meeting |
11/05/16 | Minutes from programme meeting |
17/08/16 | Minutes from programme meeting |
Attachment | Size |
---|---|
![]() | 42.49 KB |
![]() | 67.78 KB |
![]() | 60.35 KB |
![]() | 67.68 KB |
![]() | 78.58 KB |
![]() | 65.96 KB |
![]() | 78.87 KB |
![]() | 58.99 KB |
![]() | 67.94 KB |
![]() | 61.9 KB |
![]() | 37.36 KB |
![]() | 33.1 KB |