January 2017
- Report Date
- January 2017
Section One: Programme Commentary, RAG and Resources Update
Section Two: Projects Not Started
Section Three: Projects In Progress
Section Four: Closed or Withdrawn Projects
Section Five: Programme Risk Register
Section Six: Programme Meeting Minutes
Section One: Programme Commentary, RAG and Resources Update
During January.
Progress continues to be made on all active projects.
- EST080 - HelpDesk Project went live during the month
- EST094 - Struxureware Project has successfully completed disaster recovery on the live environment
- EST097 - Estates Purchase to Payment has commenced
A few project budget changes as noted below, has resulted the programme budget being increased by 4 days to 1170
- EST092 - Operational Reports has been increased by 20 days to complete the rollout of the defined projects
- EST096 - Perspective Upgrade has been reduced by 16 days after completing the planning phase of the project
- AP56-021 - Archibus Oracle Database Migration has been reduced by 8 days by agreeing to defer this project to 2018-19. As this is a core funded project there will be no impact to the overall budget as the days will be transferred back to the balance row.
During January, a total of 97 days were utilised by IS Applications across the programme, resulting in a monthly burn rate of 100%, with a year to date burn rate of 93%.
There is still a requirement for the business to clarify if the following projects will be undertaken this year namely;
- AP67-049 - BIM Strategic Review
- AP67-052 - Capital Budgeting
Programme RAG Overview
Programme Resource
Section Two: Projects Not Started
The scheduled projects for 2016-17 are;
Project Info | Programme Managers Commentary |
AP56-021 Archibus Oracle Database Migration to Oracle 12c Core Funded Planning: t.b.c. Delivery: t.b.c. |
Plan - project now delayed to be undertaken within 2018-19 - After discussions with both Development Technology and Production Management, it has been agreed that the plan to upgrade to Oracle 12 can be delayed until 2018-19, providing a minor patch is applied to upgrade to Oracle 11.0.2.4. It is envisaged that this will be completed as part of the forthcoming Archibus software upgrade project AP67-066. Dependencies - should be run as a stand-alone project whilst no other Archibus related activity is being undertaken. Dependant on planning with regards the various Archibus related projects - will require a large commitment from Estates departments throughout all stages of the project - will require a significant input from IS Applications Development Technology team and the supplier Schneider throughout the project |
AP67-066 Archibus Upgrade Sponsor Funded Planning: April 2017 Delivery: July 2017 |
Plan - Due to the delay in implementing the Estates helpdesk project, this project has been rescheduled to commence in March 2017 - requirement for the HelpDesk project to be operational - confirmed that Archibus 23.0 will be available according to the scheduled project start date - No change after mid-year review in January 2017 Dependencies - will require a large commitment from Estates departments throughout all stages of the project - will require input from IS Applications Development Technology team and the supplier Mass throughout the project |
AP67-049 BIM Strategic Review Sponsor Funded Planning: t.b.c. Delivery: t.b.c. |
Plan - Discussions with Estates Building Services and Estates Development are on-going to determine if this project should commence. currently being rescheduled to commence in March 2017 - As part of the mid-year review - awaiting decision from Estates to determine if the project will commence in 2016-17 or be deferred to 2017-18 Dependencies - will require a large commitment from Estates Building Services and Estates Development department throughout all stages of the project - will require input from a business analyst |
AP67-050 BIM Implementation Sponsor Funded Planning: t.b.c. Delivery: t.b.c.
|
Plan - As this project is dependant on the outcomes of the BIM Strategic Review and given the amount of business activity, this project has now been deferred to 2018-19 Dependencies - will require the BIM Strategic Review project to have been completed - will require a large commitment from Estates Development department throughout all stages of the project - may require external consultancy to assist in implementing - will require input from IS Applications Development Technology team and the supplier Mass throughout the project |
AP67-051 Asset Management Sponsor Funded Planning: March 2017 Delivery: August 2017 |
Plan - project to commence in March 2017 - confirmed that Archibus 23.0 will be available according to the scheduled project start date - As a result of discussions with the business, the scope of this project will be mainly focused around the development of a solution to capture asset data and subsequently upload into Archibus - No change after mid-year review in January 2017 Dependencies - will require a large commitment from Estates Technical Services department throughout all stages of the project - will require input from IS Applications Development Technology team and the supplier Mass throughout the project |
AP67-052 Capital Budgeting Sponsor Funded Planning: t.b.c. Delivery: t.b.c. |
Plan - - As part of the mid-year review - awaiting decision from Estates to determine if the project will commence in 2016-17. Dependencies - project requirements and schedule will be dictated by the defined requirements regarding the work being undertaken by Faithful and Gould - will require a large commitment from Estates departments throughout all stages of the project - will require input from IS Applications Development teams and the supplier Mass throughout the project |
Section Three: Projects in Progress
Project Info | Project Managers Commentary | ||||||||||||||||||||||
EST080 (AP45-016) Estates Department Help Desk Funded
Milestones
RAG Status GREEN
|
Report by Chris Lawford for January 2016 Achievements in Last Period
Issues
Next Steps
The project is reporting GREEN. |
||||||||||||||||||||||
EST092 (secured) (AP56-061) Estates Operational Reports Funded Milestones
RAG Status Amber |
Report by Nikki Hackett Reed for January 2017 Achievements this period
Issues
Next Steps
|
||||||||||||||||||||||
EST093 (AP56-060) Estates Strategic Reporting 10-Mar-2017 Project Resumption Review RAG Status Suspended |
Report by Chris Lawford for December 2016 Achievements in Last Period
Issues
Next Steps
The project will report GREEN until such time as a project re-boot is initiated.
|
||||||||||||||||||||||
EST094 (secured) (AP45-015) Struxureware Funded Milestones to be approved
RAG Status Green |
Report by Anne Mathison for January 2017 Achievements:
Issues
Next Steps
The project is reporting Green as project is still on schedule to close in February |
||||||||||||||||||||||
EST095 (AP56-062) Energy Systems Update Funded Milestones
Rag Status Green |
Report by Andrew Stewart for January 2017 Achievements in Last Period
Issues
Next Steps
|
||||||||||||||||||||||
EST096 (AP67-069) Perspective Upgrade Funded Milestones
RAG Status Green |
Report by Chris Orrell for January 2016 Achievements in Last Period
Issues
Next Steps
|
||||||||||||||||||||||
EST097 (AP67-033) Estates Financial Management Purchase to Payment Core Funded (initially) Milestones
RAG Status Green |
Report by Andrew Stewart for January 2017 Achievements in Last Period
Issues
Next Steps
|
||||||||||||||||||||||
|
Report by Andrew Stewart for January 2017
Achievements in Last Period
Issues
Next Steps
|
Section Four: Closed or Withdrawn Projects
Project Information | Project managers commentary |
EST083 (AP-45-013) Estates and Buildings Financial Management Process Review - Phase 2 |
Project closed on 4th November 2016 |
EST087 (AP56-062) Energy Systems Consolidation |
Project closed on 11th November 2016 |
AP67-048 Compliance Management Integration |
Project submitted for withdrawal to WIS on 20/01/17 |
Project Info | Project Managers Commentary |
Section Five: Programme Risks
Date | Risk Ref. | Programme Risk | Rag Status | Risk Owner |
10/02/17 | 7 | Delay to Scheduled Project Start for AP67-066 Archibus Upgrade | Amber | Andrew Stewart |
10/02/17 | 8 | Delay to Scheduled Project Start for AP67-051 Asset Management | Amber | Andrew Stewart |
10/02/17 | 9 | Completion of 2016-17 Programme | Amber | Andrew Stewart |
Section Six : Programme Meeting Minutes
This section details the minutes from the programme meetings held in 2015-16
Date | Comments |
15/09/15 | Minutes from programme meeting |
23/11/15 | Minutes from programme meeting |
20/04/16 | Minutes from programme meeting |
11/05/16 | Minutes from programme meeting |
17/08/16 | Minutes from programme meeting |
Attachment | Size |
---|---|
![]() | 42.49 KB |
![]() | 67.78 KB |
![]() | 60.35 KB |
![]() | 67.68 KB |
![]() | 78.58 KB |
![]() | 65.96 KB |
![]() | 78.87 KB |
![]() | 58.99 KB |
![]() | 67.94 KB |
![]() | 61.9 KB |