December 2016
- Report Date
- November 2016
Section One: Programme Commentary, RAG and Resources Update
Section Two: Projects Not Started
Section Three: Projects In Progress
Section Four: Closed or Withdrawn Projects
Section Five: Programme Risk Register
Section Six: Programme Meeting Minutes
Section One: Programme Commentary, RAG and Resources Update
During December.
Progress continues to be made on all active projects.
- EST080 - HelpDesk Project remains the priority project within the programme.
- EST094 - Struxureware Project has completed User Acceptance Testing including the disaster recovery failover to the secondary site
After reviewing the Estates programme for the remainder of the year, a number of adjustments have been agreed and can be actioned immediately, whilst a few others require further guidance from specific business users. As a result, the current Estates Department budget will be reduced by 218 days from 1384 days to 1166 days. In addition, a decision regarding a further 100 days is still awaited.
Project | Narrative | Current Budget 2016-17 | Adjusted budget 2016-17 | Programme Adjustment 2016-17 |
EST080– Estates HelpDesk | Increase budget to deliver | 159 | 283 | +124 |
EST093 – Strategic Reporting | Reduce budget due to project suspension | 163 | 43 | - 120 |
EST095 – Energy Systems Update | Reduce budget due to scope change | 96 | 45 | - 49 |
AP67-048 – Compliance Management Integration |
To be withdrawn after consultation with Building Services Team Nb. This was a multi-year project with 80 days in 16/17 and 120 days 17/18 |
80 | 0 | - 80 |
AP67-049 – BIM Strategic Review | Decision awaited from Estates | 50 | 50 | 0 |
AP67-50 – BIM Implementation | Project to be deferred into 18/19 | 42 | 0 | - 42 |
AP67-052 – Capital Budgeting | Decision awaited from Estates | 50 | 50 | 0 |
ESTPB1 – Core Funded Balance Row |
Reduce budget by transferring 40 days to AP67-033 Estates Purchase To Pay 20 days to remain in balance row |
62 | 20 | 0 |
ESTPB2 – Sponsor Funded Balance Row | Zeriose budget | 51 | 0 | -51 |
Total Adjustment |
Reduce budget |
- 218 |
During December, a total of 71 days were utilised by IS Applications across the programme, resulting in a monthly burn rate of 73%, with a year to date burn rate of 91%.
Programme RAG Overview
Programme Resource
Section Two: Projects Not Started
The scheduled projects for 2015-16 are
Project Info | Programme Managers Commentary |
AP56-021 Archibus Oracle Database Migration to Oracle 12c Core Funded Planning: July 2017 Delivery: February 2018 |
Plan - project to commence in July 2017 - No change after mid-year review in January 2017 Dependencies - should be run as a stand-alone project whilst no other Archibus related activity is being undertaken. Dependant on planning with regards the various Archibus related projects - will require a large commitment from Estates departments throughout all stages of the project - will require a significant input from IS Applications Development Technology team and the supplier Schneider throughout the project |
AP67-033 Estates Financial Management Purchase to Payment Planning: February 2017 Delivery: July 2018 |
Plan - The project sponsor has directed that the project start should be delayed until the Estates Helpdesk has gone live. As a result this is now rescheduled to commence in January. In the interim, preparatory work is being undertaken to review roles and responsibilities for the project governance board and project team - The project sponsor has confirmed that the project can now commence, but noting some potential resource conflicts due the final stages of the Estates Helpdesk project (EST080) - No change after mid-year review in January 2017 Dependencies - will require a large commitment from multiple departments namely; Estates, Finance and Procurement representatives throughout all stages of the project - will require a significant input from IS Applications Development teams - may require additional external technical support for any Webcentral based developments |
AP67-066 Archibus Upgrade Sponsor Funded Planning: April 2017 Delivery: July 2017 |
Plan - Due to the delay in implementing the Estates helpdesk project, this project has been rescheduled to commence in March 2017 - requirement for the HelpDesk project to be operational - confirmed that Archibus 23.0 will be available according to the scheduled project start date - No change after mid-year review in January 2017 Dependencies - will require a large commitment from Estates departments throughout all stages of the project - will require input from IS Applications Development Technology team and the supplier Mass throughout the project |
AP67-049 BIM Strategic Review Sponsor Funded Planning: t.b.c. Delivery: t.b.c. |
Plan - Discussions with Estates Building Services and Estates Development are on-going to determine if this project should commence. currently being rescheduled to commence in January 2017 - As part of the mid-year review - awaiting decision from Estates to determine if the project will commence in 2016-17 or be deferred to 2017-18 Dependencies - will require a large commitment from Estates Building Services and Estates Development department throughout all stages of the project - will require input from a business analyst |
AP67-050 BIM Implementation Sponsor Funded Planning: September 2018 Delivery: March 2019
|
Plan - Whilst the project is scheduled to commence in February 2017, it is unlikely due to the delay in commencing the initial BIM Strategic Review. In the interim, preparatory work is being undertaken to review roles and responsibilities for the project team along with an overview of business analysis requirements - As part of the mid-year review -this project has been deferred to 2018-19 on the basis that the BIM Strategic Review is unlikely to proceed in 2016-17 Dependencies - will require the BIM Strategic Review project to have been completed - will require a large commitment from Estates Development department throughout all stages of the project - may require external consultancy to assist in implementing - will require input from IS Applications Development Technology team and the supplier Mass throughout the project |
AP67-051 Asset Management Sponsor Funded Planning: March 2017 Delivery: August 2017 |
Plan - project to commence in March 2017 - confirmed that Archibus 23.0 will be available according to the scheduled project start date - discussions are on-going to determine if the timeline of this project can be advanced without compromising the Estates Helpdesk project - No change after mid-year review in January 2017 Dependencies - will require a large commitment from Estates Technical Services department throughout all stages of the project - will require input from IS Applications Development Technology team and the supplier Mass throughout the project |
AP67-052 Capital Budgeting Sponsor Funded Planning: t.b.c. Delivery: t.b.c. |
Plan - - As part of the mid-year review - awaiting decision from Estates to determine if the project will commence in 2016-17 Dependencies - project requirements and schedule will be dictated by the defined requirements regarding the work being undertaken by Faithful and Gould - will require a large commitment from Estates departments throughout all stages of the project - will require input from IS Applications Development teams and the supplier Mass throughout the project |
AP67-069 Perspective Upgrade Sponsor Funded Planning November 2016 Delivery: April 2017 |
Plan - project will commence in December 2016 after the appointment of a project manager - project sponsor has confirmed the project can now commence in November, planning will be scheduled to be completed with December, with the actual upgrade then commencing in January 2017 - Initial project review meeting on 28/10/16 - Dependencies - will require a large commitment from Estate Security department throughout all stages of the project - will require input from IS Applications Development Technology and the supplier throughout the project |
Section Three: Projects in Progress
Project Info | Project Managers Commentary | ||||||||
EST080 (AP45-016) Estates Department Help Desk Funded
Milestones
RAG Status Amber |
Report by Chris Lawford for December 2016 Achievements in Last Period
Issues
Next Steps
The project is reporting AMBER, subject to Background / Legacy UAT sign-off.
|
||||||||
EST092 (secured) (AP56-061) Estates Operational Reports Funded Milestones
RAG Status Amber |
Report by Nikki Hackett Reed for December 2016 Achievements in Last Period OP02 - Serach Work Requests
OP03 - Reactive and Planned Maintenance Response Times
OP33 - eIT Costs by Team
Risks/Issues
Next Steps
The project has been assigned a RAG status of Amber due to the delays in completing user acceptance testing |
||||||||
EST093 (AP56-060) Estates Strategic Reporting 10-Mar-2017 Project Resumption Review RAG Status Suspended |
Report by Chris Lawford for December 2016 Achievements in Last Period
Issues
Next Steps
The project will report GREEN until such time as a project re-boot is initiated.
|
||||||||
EST094 (secured) (AP45-015) Struxureware Funded Milestones to be approved
RAG Status Amber |
Report by Anne Mathison for December 2016 Achievements in Last Period
Issues
Next Steps
The project is reporting Amber as the revised delivery date has moved into February |
||||||||
EST095 (AP56-062) Energy Systems Update Funded Milestones
Rag Status Green |
Report by Andrew Stewart for December 2016 Achievements in Last Period
Issues
Next Steps
|
||||||||
EST096 (AP67-069) Perspective Upgrade Funded Milestones
RAG Status Green
|
Report by Andrew Stewart (on behalf of Chris Orrell) for December 2016 Achievements in Last Period
Issues
Next Steps
|
||||||||
|
Report by Andrew Stewart for December 2016
Achievements in Last Period
Issues
Next Steps
|
Section Four: Closed or Withdrawn Projects
Project Information | Project managers commentary |
EST083 (AP-45-013) Estates and Buildings Financial Management Process Review - Phase 2 |
Project closed on 4th November 2016 |
EST087 (AP56-062) Energy Systems Consolidation |
Project closed on 11th November 2016 |
AP67-048 Compliance Management Integration |
Project submitted for withdrawal to WIS on 20/01/17 |
Project Info | Project Managers Commentary |
Section Five: Programme Risks
Date | Risk Ref. | Programme Risk | Rag Status | Risk Owner |
24/08/16 | 7 | Delay to Scheduled Project Start for AP67-066 Archibus Upgrade | Amber | Andrew Stewart |
24/08/16 | 8 | Delay to Scheduled Project Start for AP67-051 Asset Management | Amber | Andrew Stewart |
09/09/16 | 9 | Completion of 2016-17 Programme | Amber | Andrew Stewart |
Section Six : Programme Meeting Minutes
This section details the minutes from the programme meetings held in 2015-16
Date | Comments |
15/09/15 | Minutes from programme meeting |
23/11/15 | Minutes from programme meeting |
20/04/16 | Minutes from programme meeting |
11/05/16 | Minutes from programme meeting |
17/08/16 | Minutes from programme meeting |