November 2016
- Report Date
- November 2016
Section One: Programme Commentary, RAG and Resources Update
Section Two: Projects Not Started
Section Three: Projects In Progress
Section Four: Closed or Withdrawn Projects
Section Five: Programme Risk Register
Section Six: Programme Meeting Minutes
Section One: Programme Commentary, RAG and Resources Update
During November .
Progress continues to be made on all active projects.
- EST080 - HelpDesk Project remains the priority project within the programme.
The following projects have been completed and have been closed during November
- EST083 - Estates Financial Management
- EST087 - Energy Systems Consolidation
Discussions have been held with starting the following projects
- AP56-062 - Energy Systems Consolidation - The project has now commenced and a project manager assigned
- AP67-049 - BIM Strategic Review - Currently on-going discussions as to how this progress should progress after further discussions with the supplier Balfour Beatty on how they are implementing BIM
- AP67-033 - Estates Financial Management Purchase to Payment - The project is scheduled to commence in January 2017. Preparatory work is being undertaken to review roles and responsibilities for the project governance board and project team.
-
AP67-069 - Perspective Upgrade - The project can now commence after the appointment of a project manger
-
AP67-051 - Asset Management - Initial discussion shave been held to determine if this project, whilst dependant on the Archibus upgrade can be advanced
During October, a total of 121 days were utilised by IS Applications across the programme, resulting in a monthly burn rate of 105%, with a year to date burn rate of 81%.
Programme RAG Overview
Programme Resource
Section Two: Projects Not Started
The scheduled projects for 2015-16 are
Project Info | Programme Managers Commentary |
AP56-021 Archibus Oracle Database Migration to Oracle 12c Core Funded Planning: July 2017 Delivery: February 2018 |
Plan - project to commence in July 2017 Dependencies - should be run as a stand-alone project whilst no other Archibus related activity is being undertaken. Dependant on planning with regards the various Archibus related projects - will require a large commitment from Estates departments throughout all stages of the project - will require a significant input from IS Applications Development Technology team and the supplier Schneider throughout the project |
AP67-033 Estates Financial Management Purchase to Payment Planning: November 2016 Delivery: July 2018 |
Plan - The project sponsor has directed that the project start should be delayed until the Estates Helpdesk has gone live. As a result this is now rescheduled to commence in January. In the interim, preparatory work is being undertaken to review roles and responsibilities for the project governance board and project team - The project sponsor has confirmed that the project can now commence, but noting some potential resource conflicts due the final stages of the Estates Helpdesk project (EST080) Dependencies - will require a large commitment from multiple departments namely; Estates, Finance and Procurement representatives throughout all stages of the project - will require a significant input from IS Applications Development teams - may require additional external technical support for any Webcentral based developments |
AP67-066 Archibus Upgrade Sponsor Funded Planning: January 2017 Delivery: July 2017 |
Plan - Due to the delay in implementing the Estates helpdesk project, this project will be rescheduled to commence in February 2017 - requirement for the HelpDesk project to be operational - confirmed that Archibus 23.0 will be available accrding to the scheduled project start date Dependencies - will require a large commitment from Estates departments throughout all stages of the project - will require input from IS Applications Development Technology team and the supplier Mass throughout the project |
AP67-048 Compliance Management Integration Sponsor Funded Planning: March 2017 Delivery: March 2018
|
Plan - project to commence in March 2017 - a number of considerations will require to be made with regards this project, namely;
Dependencies - will require a large commitment from Estates Techical Services department throughout all stages of the project - will require input from IS Applications Development Technology team and the supplier Mass throughout the project |
AP67-049 BIM Strategic Review Sponsor Funded Planning: October 2016 Delivery: February 2017 |
Plan - Discussions with Estates Building Services and Estates Development are on-going to determine if this project should commence. currently being rescheduled to commence in January 2017 - Further meeting held in relation to BIM with representatives from Estates Development, Estates Technical Services and IS Applications and the construction company Balfour Beatty to get an understanding on how they are implementing BIM - Currently on-going discussions with Estates representatives on how best to take this forward Dependencies - will require a large commitment from Estates Building Services and Estates Development department throughout all stages of the project - will require input from a business analyst |
AP67-050 BIM Implementation Sponsor Funded Planning: February 2017 Delivery: October 2017
|
Plan - Whilst the project is scheduled to commence in February 2017, it is unlikely due to the delay in commencing the initial BIM Strategic Review. In the interim, preparatory work is being undertaken to review roles and responsibilities for the project team along with an overview of business analysis requirements Dependencies - will require the BIM Strategic Review project to have been completed - will require a large commitment from Estates Development department throughout all stages of the project - may require external consultancy to assist in implementing - will require input from IS Applications Development Technology team and the supplier Mass throughout the project |
AP67-051 Asset Management Sponsor Funded Planning: March 2017 Delivery: August 2017 |
Plan - project to commence in March 2017 - confirmed that Archibus 23.0 will be available accrding to the scheduled project start date - discussions are on-going to determine if the timeline of this project can be advanced without compromising the Estates Helpdesk project Dependencies - will require a large commitment from Estates Technical Services department throughout all stages of the project - will require input from IS Applications Development Technology team and the supplier Mass throughout the project |
AP67-052 Capital Budgeting Sponsor Funded Planning: January 2017 Delivery: August 2017 |
Plan - project to commence in January 2017 Dependencies - project requirements and schedule will be dictated by the defined requirements regarding the work being undertaken by Faithful and Gould - will require a large commitment from Estates departments throughout all stages of the project - will require input from IS Applications Development teams and the supplier Mass throughout the project |
AP67-069 Perspective Upgrade Sponsor Funded Planning November 2016 Delivery: April 2017 |
Plan - project will commence in December 2016 after the appointment of a project manager - project sponsor has confirmed the project can now commence in November, planning will be scheduled to be completed with December, with the actual upgrade then commencing in January 2017 - Initial project review meeting on 28/10/16 - Dependencies - will require a large commitment from Estate Security department throughout all stages of the project - will require input from IS Applications Development Technology and the supplier throughout the project |
Section Three: Projects in Progress
Project Info | Project Managers Commentary | ||||||||
EST080 (AP45-016) Estates Department Help Desk Funded
Milestones22-Dec-2016 Full Acceptance & User Acceptance Testing 02-Dec-2016 User Training Completed 25-Jan-2017 Deploy to Live 23-Feb-2016 Deployment Signoff Review and Closure
RAG Status Amber |
Report by Chris Lawford for November 2016 Achievements in Last Period
Issues
Next Steps
The project is reporting AMBER, subject to new timescale / budget / scope PICCL 40 approval being submitted and approved by WIS.
|
||||||||
EST092 (secured) (AP56-061) Estates Operational Reports Funded Milestones
Rag Status Green |
Report by Nikki Hackett Reed for November 2016 Achievements this period OP02: Search Work Requests Build continues internally
Infrastructure
Showcase undertaken to the Business for initial feedback OP03/OP33 The development of these reports have been commissioned to Mass to develop and have been delivered OP03 - Reactive and Planned Maintenance Response Times OP33 - eIT Costs by Team Issues During the month there has been the requirement to;
Next Steps OP02 Integration and UAT OP03/OP33 Integration and UAT Acceptance sign off |
||||||||
EST093 (AP56-060) Estates Strategic Reporting Funded
Rag Status Suspended |
Report by Chris Lawford for October 2016 Achievements in Last Period
Issues
Next Steps
The project will now be suspended |
||||||||
EST094 (secured) (AP45-015) Struxureware Funded Milestones to be approved
Rag Status Green |
Report by Anne Mathison for November 2016 Achievements:
Issues
Next Steps
The project is reporting Green as it is anticipated that the current delivery date can still be achieved |
||||||||
EST095 (AP56-062) Energy Systems Update Funded Milestones
Rag Status Green |
Report by Andrew Stewart for November 2016 Achievements:
Issues
Next Steps
|
||||||||
|
Report by Andrew Stewart for October 2016
Achievements in Last Period
Issues
Next Steps
|
Section Four: Closed or Withdrawn Projects
Project Information | Project managers commentary |
EST083 (AP-45-013) Estates and Buildings Financial Management Process Review - Phase 2 |
Project closed on 4th November 2016 |
EST087 (AP56-062) Energy Systems Consolidation |
Project closed on 11th November 2016 |
Project Info | Project Managers Commentary |
Section Five: Programme Risks
Date | Risk Ref. | Programme Risk | Rag Status | Risk Owner |
24/08/16 | 7 | Delay to Scheduled Project Start for AP67-066 Archibus Upgrade | Amber | Andrew Stewart |
24/08/16 | 8 | Delay to Scheduled Project Start for AP67-051 Asset Management | Amber | Andrew Stewart |
09/09/16 | 9 | Completion of 2016-17 Programme | Amber | Andrew Stewart |
Section Six : Programme Meeting Minutes
This section details the minutes from the programme meetings held in 2015-16
Date | Comments |
15/09/15 | Minutes from programme meeting |
23/11/15 | Minutes from programme meeting |
20/04/16 | Minutes from programme meeting |
11/05/16 | Minutes from programme meeting |
17/08/16 | Minutes from programme meeting |
Attachment | Size |
---|---|
![]() | 42.49 KB |
![]() | 67.78 KB |
![]() | 60.35 KB |
![]() | 67.68 KB |
![]() | 78.58 KB |
![]() | 65.96 KB |