Section One: Programme Commentary, RAG and Resources Update
During September.
Progress continues to be made on all active projects.
- EST080 - HelpDesk Project remains the priority project within the programme.
The following projects are now in their final phases and will close within the coming month
- EST083 - Estates Financial Management
- EST087 - Energy Systems Consolidation
Discussions have either started or been arranged with the various business users with regards to commencing
- AP56-062 - Energy Systems Consolidation - Systems Update (28th September)
- AP67-049 - BIM Strategic Review (21st October)
- AP67-033 Estates Financial Management Purchase to Payment (28th October)
-
AP67-069 - Perspective Upgrade (28th October)
During August, a total of 68 days were utilised by IS Applications across the programme, resulting in a monthly burn rate of 60%, with a year to date burn rate of xx% Activity was down as a result of some projects coming to an end and others just commencing
Programme RAG Overview
Programme Resource
Section Two: Projects Not Started
The scheduled projects for 2015-16 are
Project Info | Programme Managers Commentary |
AP56-021 Archibus Oracle Database Migration to Oracle 12c Core Funded Planning: July 2017 Delivery: February 2018 |
Plan - project to commence in July 2017 Dependencies - should be run as a stand-alone project whilst no other Archibus related activity is being undertaken. Dependant on planning with regards the various Archibus related projects - will require a large commitment from Estates departments throughout all stages of the project - will require a significant input from IS Applications Development Technology team and the supplier Schneider throughout the project |
AP56-062 Energy Systems Consolidation - Systems Update Sponsor Funded Planning: October 2016 Delivery: June 2017 |
Plan - project to commence in October 2016 Dependencies - The project activity will be directed by the output Strategic Report generated through the project EST087 - Energy Systems Consolidation - will require a large commitment from Estates departments throughout all stages of the project - will require a significant input from IS Applications Development Technology team and the supplier Schneider throughout the project |
AP67-033 Estates Financial Management Purchase to Payment Planning: November 2016 Delivery: July 2018 |
Plan - project to commence in November 2016 Dependencies - - will require a large commitment from multiple departments namely; Estates, Finance and Procurement representatives throughout all stages of the project - will require a significant input from IS Applications Development teams - may require additional external technical support for any Webcentral based developments |
AP67-066 Archibus Upgrade Sponsor Funded Planning: January 2017 Delivery: July 2017 |
Plan - project to commence in January 2017 - requirement for the HelpDesk project to be operational - confirmed that Archibus 23.0 will be available accrding to the scheduled project start date Dependencies - will require a large commitment from Estates departments throughout all stages of the project - will require input from IS Applications Development Technology team and the supplier Mass throughout the project |
AP67-048 Compliance Management Integration Sponsor Funded Planning: March 2017 Delivery: March 2018
|
Plan - project to commence in March 2017 - a number of considerations will require to be made with regards this project, namely;
Dependencies - will require a large commitment from Estates Techical Services department throughout all stages of the project - will require input from IS Applications Development Technology team and the supplier Mass throughout the project |
AP67-049 BIM Strategic Review Sponsor Funded Planning: October 2016 Delivery: February 2017 |
Plan - project to commence in October 2016 Dependencies - will require a large commitment from Estates Development department throughout all stages of the project - may require input from a business analyst |
AP67-050 BIM Implementation Sponsor Funded Planning: February 2017 Delivery: October 2017
|
Plan - project to commence in February 2017 Dependencies - will require the BIM Strategic Review project to have been completed - will require a large commitment from Estates Development department throughout all stages of the project - may require external consultancy to assist in implementing - will require input from IS Applications Development Technology team and the supplier Mass throughout the project |
AP67-051 Asset Management Sponsor Funded Planning: March 2017 Delivery: August 2017 |
Plan - project to commence in March 2017 - confirmed that Archibus 23.0 will be available accrding to the scheduled project start date Dependencies - will require a large commitment from Estates Technical Services department throughout all stages of the project - will require input from IS Applications Development Technology team and the supplier Mass throughout the project |
AP67-052 Capital Budgeting Sponsor Funded Planning: January 2017 Delivery: August 2017 |
Plan - project to commence in January 2017 Dependencies - project requirements and schedule will be dictated by the defined requirements regarding the work being undertaken by Faithful and Gould - will require a large commitment from Estates departments throughout all stages of the project - will require input from IS Applications Development teams and the supplier Mass throughout the project |
AP67-069 Perspective Upgrade Sponsor Funded Planning November 2016 Delivery: April 2017 |
Plan - project to commence in November 2016 Dependencies - will require a large commitment from Estate Security department throughout all stages of the project - will require input from IS Applications Development Technology and the supplier throughout the project |
Requirement to add details re AP56-062 Energy Phase 2 and AP67-033 Estates Financial Phase 2 |
Section Three: Projects in Progress
Project Info | Project Managers Commentary | ||||||||||||
EST080 (AP45-016) Estates Department Help Desk Funded
Milestones
RAG Status RED |
Report by Chris Lawford for September 2016
Achievements in Last Period
Issues
Next Steps
The project is reporting RED as a result of the new milestones not having yet been pushed through governance.
|
||||||||||||
EST083 (AP45-013) Estates and Buildings Financial Management Process Review - Phase 2 Compliance Milestones
RAG Status Green |
Report by Ben Armstrong for September 2016
Achievements in Last Period
Issues
Next Steps
|
||||||||||||
EST087 (secured) (AP56-062) Energy Systems Consolidation Funded Milestones
RAG status Green |
Report by Andrew Stewart for September 2016 Achievement in Last Period
Issues
Next Steps
|
||||||||||||
EST092 (secured) (AP56-061) Estates Operational Reports Funded Milestones
Rag Status Green |
Report by Nikki Hackett Reed for September 2016 Achievements this period
Issues
Next Steps
|
||||||||||||
EST093 (AP56-060) Estates Strategic Reporting Funded
Rag Status Red |
Report by Chris Lawford for September 2016
Achievements in Last Period
Issues
Next Steps
The project is continue to report RED until such time as a sponsor is officially appointed. |
||||||||||||
EST094 (secured) (AP45-015) Struxureware Funded Milestones
Rag Status Amber |
Report by Anne Mathison for September 2016 Achievements:
Issues
Next Steps
The project is reporting AMBER now that new milestones have been agreed during September and are within one month of the Brief plan regarding overall delivery |
||||||||||||
|
Report by Andrew Stewart for September 2016
Achievements in Last Period
Issues
Next Steps
|
Section Four: Closed or Withdrawn Projects
Project Info | Project Managers Commentary |
Section Five: Programme Risks
Date | Risk Ref. | Programme Risk | Rag Status | Risk Owner |
24/08/16 | 7 | Delay to Scheduled Project Start for AP67-066 Archibus Upgrade | Amber | Andrew Stewart |
24/08/16 | 8 | Delay to Scheduled Project Start for AP67-051 Asset Management | Amber | Andrew Stewart |
09/09/16 | 9 | Completion of 2016-17 Programme | Amber | Andrew Stewart |
Section Six : Programme Meeting Minutes
This section details the minutes from the programme meetings held in 2015-16
Date | Comments |
15/09/15 | Minutes from programme meeting |
23/11/15 | Minutes from programme meeting |
20/04/16 | Minutes from programme meeting |
11/05/16 | Minutes from programme meeting |
17/08/16 | Minutes from programme meeting |