August 2016
- Report Date
- August 2016
Section One: Programme Commentary, RAG and Resources Update
Section Two: Projects Not Started
Section Three: Projects In Progress
Section Four: Closed or Withdrawn Projects
Section Five: Programme Risk Register
Section Six: Programme Meeting Minutes
Section One: Programme Commentary, RAG and Resources Update
During August
After an initial review of the programme budget, a few adjustments were made and the programme budget for 2016-17 has been set at 1414 days. For information, the budget has subsequently been reduced by a further 30 days to 1384 days after completing the planning phase of the project EST094 - Struxureware.
The initial review took into account complexities and dependencies of the various projects associated with the Archibus Integrated Workplace management System that were required to be lined up after the implementation of the Estates helpdesk project, EST080. In summary, on completion of the HelpDesk Project there is the requirement to line up the following projects;
- Archibus Upgrade to version 23 - which is dependent on the completion of the Estates HelpDesk
- Asset Management - which is dependent on the Archibus Upgrade
- Compliance management Integration - which is dependent on the Archibus Upgrade
- Archibus Oracle Database Upgrade - whilst not dependent will impact on the above. As a result after consultation with both Estates and IS Applications Development and Production Teams if was agreed to delay the start of this project until July 2017
During August, a total of 101 days were utilised by IS Applications across the programme, resulting in a monthly burn rate of 86%..
Programme RAG Overview
Programme Resource
Section Two: Projects Not Started
The scheduled projects for 2015-16 are
Project Info | Programme Managers Commentary |
AP56-021 Archibus Oracle Database Migration to Oracle 12c Core Funded Planning: July 2017 Delivery: February 2018 | Plan - project to commence in July 2017 Dependencies - should be run as a stand-alone project whilst no other Archibus related activity is being undertaken. Dependant on planning with regards the various Archibus related projects - will require a large commitment from Estates departments throughout all stages of the project - will require a significant input from IS Applications Development Technology team and the supplier Schneider throughout the project |
AP56-062 Energy Systems Consolidation - Systems Update Sponsor Funded Planning: October 2016 Delivery: June 2017 | Plan - project to commence in October 2016 Dependencies - The project activity will be directed by the output Strategic Report generated through the project EST087 - Energy Systems Consolidation - will require a large commitment from Estates departments throughout all stages of the project - will require a significant input from IS Applications Development Technology team and the supplier Schneider throughout the project |
AP67-033 Estates Financial Management Purchase to Payment Planning: November 2016 Delivery: July 2018 | Plan - project to commence in November 2016 Dependencies - - will require a large commitment from multiple departments namely; Estates, Finance and Procurement representatives throughout all stages of the project - will require a significant input from IS Applications Development teams - may require additional external technical support for any Webcentral based developments |
AP67-066 Archibus Upgrade Sponsor Funded Planning: January 2017 Delivery: July 2017 | Plan - project to commence in January 2017 - requirement for the HelpDesk project to be operational - confirmed that Archibus 23.0 will be available accrding to the scheduled project start date Dependencies - will require a large commitment from Estates departments throughout all stages of the project - will require input from IS Applications Development Technology team and the supplier Mass throughout the project |
AP67-048 Compliance Management Integration Sponsor Funded Planning: March 2017 Delivery: March 2018
| Plan - project to commence in March 2017 - a number of considerations will require to be made with regards this project, namely;
Dependencies - will require a large commitment from Estates Techical Services department throughout all stages of the project - will require input from IS Applications Development Technology team and the supplier Mass throughout the project |
AP67-049 BIM Strategic Review Sponsor Funded Planning: October 2016 Delivery: February 2017 | Plan - project to commence in October 2016 Dependencies - will require a large commitment from Estates Development department throughout all stages of the project - may require input from a business analyst |
AP67-050 BIM Implementation Sponsor Funded Planning: February 2017 Delivery: October 2017
| Plan - project to commence in February 2017 Dependencies - will require the BIM Strategic Review project to have been completed - will require a large commitment from Estates Development department throughout all stages of the project - may require external consultancy to assist in implementing - will require input from IS Applications Development Technology team and the supplier Mass throughout the project |
AP67-051 Asset Management Sponsor Funded Planning: March 2017 Delivery: August 2017 | Plan - project to commence in March 2017 - confirmed that Archibus 23.0 will be available accrding to the scheduled project start date Dependencies - will require a large commitment from Estates Technical Services department throughout all stages of the project - will require input from IS Applications Development Technology team and the supplier Mass throughout the project |
AP67-052 Capital Budgeting Sponsor Funded Planning: January 2017 Delivery: August 2017 | Plan - project to commence in January 2017 Dependencies - project requirements and schedule will be dictated by the defined requirements regarding the work being undertaken by Faithful and Gould - will require a large commitment from Estates departments throughout all stages of the project - will require input from IS Applications Development teams and the supplier Mass throughout the project |
AP67-069 Perspective Upgrade Sponsor Funded Planning November 2016 Delivery: April 2017 | Plan - project to commence in November 2016 Dependencies - will require a large commitment from Estate Security department throughout all stages of the project - will require input from IS Applications Development Technology and the supplier throughout the project |
Requirement to add details re AP56-062 Energy Phase 2 and AP67-033 Estates Financial Phase 2 |
Section Three: Projects in Progress
Project Info | Project Managers Commentary | ||||||||||||||
EST080 (AP45-016) Estates Department Help Desk Funded
Milestones30-Sep-2016 Full Acceptance & User Acceptance Testing 21-Oct-2016 User Training Completed 11-Nov-2016 Deploy to Live 25-Nov-2016 Deployment Signoff Review and Closure RAG Status RED | Report by Chris Lawford for August 2016Achievements in Last Period
Issues
Next Steps
The project is reporting RED as a result of the budgetary increase agreed over the last month and the new project go-live date has yet to be agreed.
| ||||||||||||||
EST083 (AP45-013) Estates and Buildings Financial Management Process Review - Phase 2 Compliance Milestones
RAG Status Green | Report by Ben Armstrong for August 2016
Achievements in Last Period
Issues
Next Steps
| ||||||||||||||
EST087 (AP56-062) Energy Systems Consolidation Funded Milestones
RAG status Green | Report by Andrew Stewart for August 2016
Achievement in Last Period
Issues
Next Steps
| ||||||||||||||
EST092 (AP56-061) Estates Operational Reports Funded Milestones 05-Aug-2016 Business Analysis & Scoping Completed 23-Sep-2016 Reporting Platform Available 21-Oct-2016 Proof-of-concept Sign-off 18-Nov-2016 Tranche 1 Sign-off 16-Dec-2016 Tranche 2 Sign-off 23-Dec-2016 Project Closed Rag Status Green | Report by Chris Lawford for August 2016Achievements in Last Period
Issues
Next Steps
| ||||||||||||||
EST093 (AP56-060) Estates Strategic Reporting Funded Milestones 26-Aug-2016 Business Analysis & Scoping Complete 30-Sep-2016 Business Gate Review 03-Mar-2017 Delivery Complete 17-Mar-2017 Project Close
Rag Status Red | Report by Chris Lawford for August 2016
Achievements in Last Period
Issues
Next Steps
The project is reporting RED as no sponsor is currently assigned, and the project lacks impetus within Estates compared to other, higher priority initiatives. | ||||||||||||||
EST094 (AP45-015) Struxureware Funded Milestones
Rag Status Green | Report by Anne Mathison for August 2016 Achievements:
Issues
Next Steps
| ||||||||||||||
| Report by Andrew Stewart for August 2016
Achievements in Last Period
Issues
Next Steps
|
Section Four: Closed or Withdrawn Projects
Project Info | Project Managers Commentary |
Date | Risk Ref. | Programme Risk | Rag Status | Risk Owner |
24/08/16 | 7 | Delay to Scheduled Project Start for AP67-066 Archibus Upgrade | Amber | Andrew Stewart |
24/08/16 | 8 | Delay to Scheduled Project Start for AP67-051 Asset Management | Amber | Andrew Stewart |
09/09/16 | 9 | Completion of 2016-17 Programme | Amber | Andrew Stewart |
Section Six : Programme Meeting Minutes
This section details the minutes from the programme meetings held in 2015-16
Date | Comments |
15/09/15 | Minutes from programme meeting |
23/11/15 | Minutes from programme meeting |
20/04/16 | Minutes from programme meeting |
11/05/16 | Minutes from programme meeting |
17/08/16 | Minutes from programme meeting |