Report for July 2016
- Report Date
- July 2016
Section One: Programme Commentary, RAG and Resources Update
Section Two: Projects Not Started
Section Three: Projects In Progress
Section Four: Closed or Withdrawn Projects
Section One: Programme Commentary, RAG and Resources Update
Progress continues to be made on all active projects,. However, there is still the project issue regarding sponsorship for the Strategic Reports that has still to be resolved. During the month, the project associated with Capital Budgeting has been closed, whilst the start-up for Struxureware project has been initiated.
With the programme now covering several departmental areas within Estates, there is now the requirement to review future attendees to the programme meeting and the overall budget holder.
During July, a total of 54 days were utilised by IS Applications across the programme, resulting in a monthly burn rate of 79%.
Forward Look and RAG for July 2016
Resource Position to 31st July 2016
Section Two: Projects Not Started
The scheduled projects for 2015-16 are
Project Info | Programme Managers Commentary |
AP56-021 Archibus Oracle Database Migration to Oracle 12c Core Funded Planning: March 2017 Delivery tbc | Plan - project to commence in March 2017 - delivery date to be confirmed Dependencies - should be run as a stand-alone project whilst no other Archibus related activity is being undertaken. Dependant on planning with regards the Archibus Upgrade - will require a large commitment from Estates departments throughout all stages of the project - will require a significant input from IS Applications Development Technology team and the supplier Schneider throughout the project |
AP67-066 Archibus Upgrade Sponsor Funded Planning: December 2016 Delivery: tbc | Plan - project to commence in November 2016 - requirement for the HelpDesk project to be operational - consideration of the release date of the next version of Archibus 23.0 will be required Dependencies - will require a large commitment from Estates departments throughout all stages of the project - will require input from IS Applications Development Technology team and the supplier Mass throughout the project |
AP67-048 Compliance Management Integration Sponsor Funded Planning: March 2017 Delivery: tbc
| Plan - project to commence in march 2017 - a number of considerations will require to be made with regards this project, namely;
Dependencies - will require a large commitment from Estates Techical Services department throughout all stages of the project - will require input from IS Applications Development Technology team and the supplier Mass throughout the project |
AP67-049 BIM Strategic Review Sponsor Funded Planning: October 2016 Delivery: tbc | Plan - project to commence in September 2016 Dependencies - will require a large commitment from Estates Development department throughout all stages of the project - may require input from a business analyst |
AP67-050 BIM Implementation Sponsor Funded Planning: March 2017 Delivery: tbc
| Plan - project to commence in February 2017 Dependencies - will require the BIM Strategic Review project to have been completed - will require a large commitment from Estates Development department throughout all stages of the project - may require external consultancy to assist in implementing - will require input from IS Applications Development Technology team and the supplier Mass throughout the project |
AP67-051 Asset Management Sponsor Funded Planning: December 2016 Delivery tbc | Plan - project to commence in November 2016 - the release date of the next version of Achibus 23.0 will be required to detremine possible additional functionality Dependencies - will require a large commitment from Estates Technical Services department throughout all stages of the project - will require input from IS Applications Development Technology team and the supplier Mass throughout the project |
AP67-052 Capital Budgeting Sponsor Funded Planning: February 2017 Delivery tbc | Plan - project to commence in January 2017 Dependencies - project requirements and schedule will be dictated by the defined requirements regarding the work being undertaken by Faithful and Gould - will require a large commitment from Estates departments throughout all stages of the project - will require input from IS Applications Development teams and the supplier Mass throughout the project |
AP67-069 Perspective Upgrade Sponsor Funded Planning December 2016 Delivery tbc | Plan - project to commence in November 2016 Dependencies - will require a large commitment from Estate Security department throughout all stages of the project - will require input from IS Applications Development Technology and the supplier throughout the project |
Section Three: Projects in Progress
Project Info | Project Managers Commentary | ||||||||||
EST080 (AP45-016) Estates Department Help Desk Funded
Milestones
RAG Status Green | Report by Andrew Stewart for July 2016Achievements
Issues
Next Steps
Having adjusted the project budget the project reverts to a RAG status of Green
| ||||||||||
EST083 (AP45-013) Estates and Buildings Financial Management Process Review - Phase 2 Compliance Milestones
RAG Status Green | Report by Ben Armstrong for July 2016
Achievements in Last Period
Issues
Next Steps
| ||||||||||
EST087 (AP56-062) Energy Systems Consolidation Funded Milestones
RAG status Green | Report by Andrew Stewart for July 2016
Achievement in Last Period
Issues
Next Steps
Having re-adjusted the delivery date last month, the project reverts to a RAG status of Green.
| ||||||||||
Capital Budgeting Funded Milestones
RAG status Blue | Report by Andrew Stewart for July 2016Achievements in Last Period
Issues
Next Steps
| ||||||||||
EST091 (AP56-014) EBIS OnLine ColdFusion Upgrade Compliance Milestones
Rag Status Amber | Report by Chris Lawford for July 2016Achievements in Last Period
Issues
Next Steps None Milestones None
| ||||||||||
EST092 (secured) (AP56-061) Estates Operational Reports Funded Milestones 05-Aug-2016 Business Analysis & Scoping Completed 23-Sep-2016 Reporting Platform Available 21-Oct-2016 Proof-of-concept Sign-off 18-Nov-2016 Tranche 1 Sign-off 16-Dec-2016 Tranche 2 Sign-off 23-Dec-2016 Project Closed Rag Status Green | Report by Chris Lawford for July 2016Achievements in Last Period
Issues
Next Steps
| ||||||||||
EST093 (AP56-060) Estates Strategic Reporting Funded Milestones 26-Aug-2016 Business Analysis & Scoping Complete 30-Sep-2016 Business Gate Review 03-Mar-2017 Delivery Complete 17-Mar-2017 Project Close
Rag Status Amber | Report by Chris Lawford for July 2016Achievements in Last Period
Issues
Next Steps
| ||||||||||
EST094 (secured) (AP45-015) Struxureware Funded Milestones 26-Aug-2016 Planning Rag Status Green | Report by Andy Stewart (on behalf of Anne Mathison) for July 2016 Achievements in Last Period
Issues
Next Steps
| ||||||||||
| Report by Andrew Stewart for July 2016
Achievements in Last Period
Issues
Next Steps
|
Section Four: Closed or Withdrawn Projects
Project Info | Project Managers Commentary |
AP45-017: Building Information Modelling Strategic Review | Withdrawn on 18th September 2015 |
EST089 (AP56-065) Perspective Upgrade | Withdrawn on 22nd April 2016 |
AP56-063 Archibus Upgrade | Withdrawn on 1st April 2016 |
EST084 (AP34-015) Estates Document Management | Completion report on 6-May 2016 |
EST088 Capital Budgeting | Completion Report on 15th July 2016 |
Section Five: Programme Risks
Date | Risk Ref. | Programem Risk | Rag Status | Risk Owner |
16/08/16 | 6 | Schneider Struxureware Solution does not meet business requirements Update: As the decison has been taken to commence the project in August 2016, this risk can now be closed | Closed | Martin Crawford |
Section Six : Programme Meeting Minutes
This section details the minutes from the programme meetings held in 2015-16
Date | Comments |
15/09/15 | Minutes from programme meeting |
23/11/15 | Minutes from programme meeting |
20/04/16 | Minutes from programme meeting |
11/05/16 | Minutes from programme meeting |
17/08/16 | Minutes from programme meeting |