June 2016
- Report Date
- June 2016
Section One: Programme Commentary, RAG and Resources Update
Section Two: Projects Not Started
Section Three: Projects In Progress
Section Four: Closed or Withdrawn Projects
Section One: Programme Commentary, RAG and Resources Update
During June
Progress continues to be made on all active projects,. However, there are a number of project issues regarding sponsorship that have still to be resolved. During the month the level of activity that could be completed with the remainder of the academic year has been assessed resulting in some retained contingency being removed and some tasks continuing into the next academic year. Consequently the overall programme budget has been reduced by 54 days from 881 days to 827 days.
With the programme now covering several departmental areas within Estates, there is now the requirement to review future attendees to the programme meeting and the overall budget holder.
During June, a total of 50 days were utilised by IS Applications across the programme, resulting in a monthly burn rate of 72%.
Section Two: Projects Not Started
The scheduled projects for 2015-16 are
Project Info | Programme Managers Commentary |
AP67-xxx Archibus Oracle Database Migration to Oracle 12c Core Funded Planning: February 2017 Delivery tbc | Plan - project to commence in February 2017 - initial planning phase scheduled to be completed in February 2017 - delivery date to be confirmed Dependencies - should be run as a stand-alone project whilst no other Archibus related activity is being undertaken. Dependant on planning with regards the Archibus Upgrade - will require a large commitment from Estates departments throughout all stages of the project - will require a significant input from IS Applications Development Technology team and the supplier Schneider throughout the project |
AP45-015 Struxureware BEMS Server Migration Sponsor Funded Planning: August 2016 Delivery: tbc | Plan - project to commence in August 2016 - initial planning phase scheduled to be completed in August 2016 - delivery date to be confirmed Dependencies - will require a large commitment from Estates and Buildings Energy department throughout all stages of the project - will require a significant input from IS Applications Development Technology team and the supplier Schneider throughout the project |
AP56-063 Archibus Upgrade Sponsor Funded Planning: October 2016 Delivery: tbc | Plan - project to commence in October 2016 - requirement for the HelpDesk project to be operational - consideration of the release date of the next version of Archibus 23.0 will be required Dependencies - will require a large commitment from Estates departments throughout all stages of the project - will require input from IS Applications Development Technology team and the supplier Mass throughout the project |
AP67-048 Compliance Management Integration Sponsor Funded Planning: tbc Delivery: tbc
| Plan - project to commence in - a number of considerations will require to be made with regards this project, namely;
Dependencies - will require a large commitment from Estates Techical Services department throughout all stages of the project - will require input from IS Applications Development Technology team and the supplier Mass throughout the project |
AP67-049 BIM Strategic Review Sponsor Funded Planning: September 2016 Delivery: tbc | Plan - project to commence in September 2016 Dependencies - will require a large commitment from Estates Development department throughout all stages of the project - may require input from a business analyst |
AP67-050 BIM Implementation Sponsor Funded Planning: February 2017 Delivery: tbc
| Plan - project to commence in February 2017 Dependencies - will require the BIM Strategic Review project to have been completed - will require a large commitment from Estates Development department throughout all stages of the project - may require external consultancy to assist in implementing - will require input from IS Applications Development Technology team and the supplier Mass throughout the project |
AP67-051 Asset Management Sponsor Funded Planning: tbc Delivery tbc | Plan - project to commence in - the release date of the next version of Achibus 23.0 will be required to detremine possible additional functionality Dependencies - will require a large commitment from Estates Technical Services department throughout all stages of the project - will require input from IS Applications Development Technology team and the supplier Mass throughout the project |
AP67-052 Capital Budgeting Sponsor Funded Planning: tbc Delivery tbc | Plan - project to commence in September 2016 Dependencies - will require a large commitment from Estates departments throughout all stages of the project - will require input from IS Applications Development teams and the supplier Mass throughout the project |
AP67-xxx Perspective Upgrade Sponsor Funded Planning tbc Delivery tbc | Plan - project to commence in September 2016 Dependencies - will require a large commitment from Estate Security department throughout all stages of the project - will require input from IS Applications Development Technology and the supplier throughout the project |
Section Three: Projects in Progress
Project Info | Project Managers Commentary | ||||||||||
EST080 (AP45-016) Estates Department Help Desk Funded
Milestones
RAG Status Green | Report by Andrew Stewart for June 2016
Issues
Next Steps
Due to the requirement to re-adjust the current project budget, the project has been assigned an Amber status. | ||||||||||
EST083 (AP45-013) Estates and Buildings Financial Management Process Review - Phase 2 Compliance Milestones
Project to be suspended/put on hold
RAG Status Green | Report by Ben Armstrong for June 2016
Issues
Next Steps
| ||||||||||
EST087 (AP56-062) Energy Systems Consolidation Funded Milestones
RAG status Amber | Report by Andrew Stewart for June 2016
Achievement in Last Period
Issues
Next Steps
Due to the project closure being delayed to August, the project has been assigned a RAG status of Amber.
| ||||||||||
Capital Budgeting Funded Milestones
RAG status Green | Report by Andrew Stewart for June 2016Achievements in Last Period
Issues
Next Steps
| ||||||||||
EST091 (AP56-014) EBIS OnLine ColdFusion Upgrade Compliance Milestones 12-Jul-16 Project Close Rag Status Amber | Report by Chris Lawford for June 2016Achievements in Last Period
Issues
Next Steps
| ||||||||||
EST092 (secured) (AP56-061) Estates Operational Reports Funded Milestones 22-Aug-16 Reporting Platform Available 23-Sep-16 Proof-of-concept Sign-off 04-Nov-16 Tranche 1 Sign-off 09-Dec-16 Tranche 2 Sign-off 23-Dec-16 Project Closed Rag Status Amber | Report by Chris Lawford for June 2016Achievements in Last Period
Issues
Next Steps
The project has been assigned an Amber status as the new Project Sponsor has still to be confirmed. | ||||||||||
EST093 (AP56-060) Estates Strategic Reporting Funded Milestones 15-Jul-16 Business Analysis & Design Complete 31-Jul-16 Business Gate Review 03-Mar-17 Delivery Complete 17-Mar-17 Project Close Rag Status Amber | Report by Chris Lawford for June 2016Achievements in Last Period
Issues
Next Steps
The project has been assigned an Amber status as the new Project Sponsor has still to be confirmed. | ||||||||||
| Report by Andrew Stewart for June 2016
Achievements in Last Period
Issues
Next Steps
|
Section Four: Closed or Withdrawn Projects
Project Info | Project Managers Commentary |
AP45-017: Building Information Modelling Strategic Review | Withdrawn on 18th September 2015 |
EST089 (AP56-065) Perspective Upgrade | Withdrawn on 22nd April 2016 |
AP56-063 Archibus Upgrade | Withdrawn on 1st April 2016 |
EST084 (AP34-015) Estates Document Management | Completion report on 6-May 2016 |
Section Five: Programme Risks
Date | Risk Ref. | Programem Risk | Rag Status | Risk Owner |
06/05/16 | 6 | Schneider Struxureware Solution does not meet business requirements | Green | Martin Crawford |
Section Six : Programme Meeting Minutes
This section details the minutes from the programme meetings held in 2015-16
Date | Comments |
15/09/15 | Minutes from programme meeting |
23/11/15 | Minutes from programme meeting |
20/04/16 | Minutes from programme meeting |
11/05/16 | Minutes from programme meeting |