May 2016
- Report Date
- May 2016
Section One: Programme Commentary, RAG and Resources Update
Section Two: Projects Not Started
Section Three: Projects In Progress
Section Four: Closed or Withdrawn Projects
Section One: Programme Commentary, RAG and Resources Update
During May
Two projects were completed and closed.
Progress continues to be made on all active projects, however, there are still a number of resource conflicts within the Estates department are being experienced in a number of the projects. This is being recognised within the Estates department with on-going efforts being made to resolve.
During May, a toal of 112 days were utilised by IS Applications across the programme, resulting in a monthly burn rate of 151%. The burn rate for the current year to date is 96%
Section Two: Projects Not Started
The scheduled projects for 2015-16 are
Project Info | Programme Managers Commentary |
AP45-015 Struxureware BEMS Server Migration Funded Planning: June 2016 Delivery: t,b.c. | Plan This project has been carried over from 14/15. The decision to delay the project unti May 2016 was taken to enable further time for the Energy department to review the new version of software. - project to commence in June 2016 - Development Technology resource has been confirmed to assit with the Planning activities in June, and the Design phase within July - initial planning phase scheduled to be completed in June 2016 - By delaying the project to commence in June 2016, the initial project budget of 100 days has been re-adjusted with 15 days activity planned for 15/16 with the remainder in 16/17 - delivery date to be confirmed Dependencies - will require a large commitment from Estates and Buildings Energy department throughout all stages of the project - will require a significant input from IS Applications Development Technology team and the supplier Schneider throughout the project |
Section Three: Projects in Progress
Project Info | Project Managers Commentary | ||||||||||||||||||
EST080 (AP45-016) Estates Department Help Desk Funded
Milestones
RAG Status Red | Report by Andrew Stewart for May 2016Achievements
Issues
Next Steps
The RAG status has been set to Red given the change of delivery date and required budget increase | ||||||||||||||||||
EST083 (AP45-013) Estates and Buildings Financial Management Process Review - Phase 2 Compliance Milestones
Project to be suspended - put on hold
RAG Status Green | Report by Ben Armstrong for May 2016
Achievements in Last Period
Issues
Next Steps
The Project has reverted to Green as the Project Board have agreed a revised provisional implementation plan which includes putting the project on hold for up to 4 months. | ||||||||||||||||||
EST084 (AP34-015) Estates and Buildings Document Management Extranet Discretionary Milestones RAG Status BLUE
| Report by Anne Mathison for May 2016Achievements:
Issue
Next Steps:
Project Cosed and so the project has been assigned a BLUE RAG status | ||||||||||||||||||
EST087 (AP56-062) Energy Systems Consolidation Funded Milestones
RAG status Green | Report by Andrew Stewart for May 2016
Achievement in Last Period
Issues
Next Steps
| ||||||||||||||||||
Capital Budgeting Funded Milestones
RAG status Green | Report by Andrew Stewart for May 2016Achievements in Last Period
Issues
Next Steps
| ||||||||||||||||||
EST089 (AP56-065) Perspective Upgrade Funded Milestones RAG status Blue | Report by Andrew Stewart for May 2016
Achievements in Last Period
Issues
Next Steps
| ||||||||||||||||||
EST091 (AP56-014) EBIS OnLine ColdFusion Upgrade Compliance Milestones Projected
Rag Status Amber | Report by Chris Lawford for May 2016Achievements in Last Period
Issues
Next Steps
Due to continuing environment issues, the project status remains at a RAG status of Amber | ||||||||||||||||||
EST092 (AP56-061) Estates Operational Reports Funded Milestones
Rag Status Green | Report by Chris Lawford for May 2016
Achievements in Last Period
Issues
Next Steps
| ||||||||||||||||||
EST093 (AP56-060) Estates Strategic Reporting Funded Milestones
Rag Status Green | Report by Chris Lawford for May 2016Achievements in Last Period
Issues
Next Steps
| ||||||||||||||||||
| Report by Andrew Stewart for May 2016
Achievements in Last Period
Issues
Next Steps
|
Section Four: Closed or Withdrawn Projects
Project Info | Project Managers Commentary |
AP45-017: Building Information Modelling Strategic Review | Withdrawn on 18th September 2015 |
EST089 (AP56-065) Perspective Upgrade | Withdrawn on 22nd April 2016 |
AP56-063 Archibus Upgrade | Withdrawn on 1st April 2016 |
EST084 (AP34-015) Estates Document Management | Completion report on 6-May 2016 |
Section Five: Programme Risks
Date | Risk Ref. | Programem Risk | Rag Status | Risk Owner |
06/05/16 | 6 | Schneider Struxureware Solution does not meet business requirements | Green | Martin Crawford |
Section Six : Programme Meeting Minutes
This section details the minutes from the programme meetings held in 2015-16
Date | Comments |
15/09/15 | Minutes from programme meeting |
23/11/15 | Minutes from programme meeting |
20/04/16 | Minutes from programme meeting |
11/05/16 | Minutes from programme meeting |