Section One: Programme Commentary, RAG and Resources Update
Section Two: Projects Not Started
Section Three: Projects In Progress
Section Four: Closed or Withdrawn Projects
Section One: Programme Commentary, RAG and Resources Update
During April,
In general, progress continues to be made on all active projects, however, there are still a number of resource conflicts within the Estates department are being experienced in a number of the projects. This is being recognised within the Estates department with on-going efforts being made to resolve.
During April, a toal of 74 days were utilised by IS Applications across the programme, resulting in a monthly burn rate of 100%. The burn rate for the current year to date is 90%
Section Two: Projects Not Started
The scheduled projects for 2015-16 are
Project Info | Programme Managers Commentary |
AP45-015 Struxureware BEMS Server Migration Funded Planning: June 2016 Delivery: t,b.c. | Plan This project has been carried over from 14/15. The decision to delay the project unti May 2016 was taken to enable further time for the Energy department to review the new version of software. - project to commence in May 2016 - initial planning phase scheduled to be completed in June 2016 - By delaying the project to commence in May 2016, the initial project budget of 100 days has been re-adjusted with 35 days activity planned for 15/16 with the remainder in 16/17 - delivery date to be confirmed Dependencies - will require a large commitment from Estates and Buildings Energy department throughout all stages of the project - will require a significant input from IS Applications Development Technology team and the supplier Schneider throughout the project |
Section Three: Projects in Progress
Project Info | Project Managers Commentary | ||||||||||||||||
EST080 (AP45-016) Estates Department Help Desk Funded
Milestones
RAG Status Amber
| Report by Anne Mathison for April 2016Achievements
The RAG status has been set to Amber given the change of delivery date | ||||||||||||||||
EST083 (AP45-013) Estates and Buildings Financial Management Process Review - Phase 2 Compliance Milestones
RAG Status Red | Report by Ben Armstrong for April 2016Achievements in Last Period
Issues
Next Steps
Whilst teh project has been assigned a RAG status of Red due to the documented business related issues, it is anticiapted that the project board will approve the revised strategy at the next project board meeting. | ||||||||||||||||
EST084 (AP34-015) Estates and Buildings Document Management Extranet Discretionary Milestones
RAG Status Green
| Report by Anne Mathison for April 2016Achievements:
Issue
Next Steps:
Due to agreement of the milestones, this project has been assigned a GREEN RAG status | ||||||||||||||||
EST087 (AP56-062) Energy Systems Consolidation Funded Milestones
RAG status Green | Report by Andrew Stewart for April 2016
Achievement in Last Period
Issues
Next Steps
| ||||||||||||||||
Capital Budgeting Funded Milestones
RAG status Amber | Report by Andrew Stewart for April 2016Achievements in Last Period
The status of teh project remains wit ha RAG status of Amber, until further clarity of requirements is established
Next Steps Confirm time recording functional requirements with PWC and Estates Determine set-up requirements
Issues Awaiting response from PWC contact regarding requirements | ||||||||||||||||
EST089 (AP56-065) Perspective Upgrade Funded Milestones
RAG status Blue | Report by Andrew Stewart for April 2016Achievements in Last Period
Issues
Next Steps
| ||||||||||||||||
EST091 (AP56-014) EBIS OnLine ColdFusion Upgrade Compliance Milestones Projected
Rag Status Amber | Report by Chris Lawford for April 2016
Achievements in Last Period
Issues
Next Steps
Due to potential slippage regarding the live deployment, the project has been assigned a RAG status of Amber | ||||||||||||||||
EST092 (AP56-061) Estates Operational Reports Funded Milestones
Rag Status Green | Report by Chris Lawford for April 2016
Achievements in Last Period
Issues
Next Steps
| ||||||||||||||||
EST093 (AP56-060) Estates Strategic Reporting Funded Milestones
Rag Status Green | Report by Chris Lawford for April 2016
Achievements in Last Period
Issues
Next Steps
| ||||||||||||||||
| Report by Andrew Stewart for April 2016
Achievements in Last Period
Issues
Next Steps
|
Section Four: Closed or Withdrawn Projects
Project Info | Project Managers Commentary |
AP45-017: Building Information Modelling Strategic Review | Withdrawn on 18th September 2015 |
EST089 (AP56-065) Perspective Upgrade | Withdrawn on 22nd April 2016 |
AP56-063 Archibus Upgrade | Withdrawn on 1st April 2016 |
Section Five: Programme Risks
Date | Risk Ref. | Programem Risk | Rag Status | Risk Owner |
06/05/16 | 6 | Schneider Struxureware Solution does not meet business requirements | Green | Martin Crawford |
Section Six : Programme Meeting Minutes
This section details the minutes from the programme meetings held in 2015-16
Date | Comments |
15/09/15 | Minutes from programme meeting |
23/11/15 | Minutes from programme meeting |
20/04/16 | Minutes from programme meeting |
11/05/16 | Minutes from programme meeting |