March 2016
- Report Date
- March 2016
Section One: Programme Commentary, RAG and Resources Update
Section Two: Projects Not Started
Section Three: Projects In Progress
Section Four: Closed or Withdrawn Projects
Section One: Programme Commentary, RAG and Resources Update
During March.
In general, progress continues to be made on all active projects, however, a number of resource conflicts within the Estates department are being experienced in a number of the projects. This is being recognised within the Estates department with on-going efforts being made to resolve. In addition, due to the on-going activity associated with the Estates Helpdesk and Estates Financial Management projects it was acknowledged that it would not be possible to undertake the planned Archibus upgrade within the current academic year. As a result the project has been withdrawn, as there is already an Archibus upgrade project scheduled for 16/17.
During the month, a number of project budget changes were initiated, resulting in an overall reduction of the programme budget from 900 days to 881 days. This incorporated;
Project | Detail | Transfer from ESTPB2 - Sponsor Funded Contingency (73 days) | Impact on Budget | Revised Budget |
Current approved programme budget | 900 days | |||
EST080: Estates HelpDesk | Project budget increase of 37 days | 37 days | No impact | |
EST083: Estates Financial Management System | Project Budget increase of 88 days | 36 days | + 52 days | |
EST090: Waste Management System Upgrade | Project Budget decrease of 29 days | N/A | - 21 days | |
AP56-063: Archibus Upgrade | Project Budget decrease of 50 days | N/A | - 50 days | |
Revised programme budget | 881 days |
During March, a toal of 93 days were utilised by IS Applications across the programme, resulting in a monthly burn rate of 126%. The burn rate for the current year to date is 89%
Section Two: Projects Not Started
The scheduled projects for 2015-16 are
Project Info | Programme Managers Commentary |
AP45-015 Struxureware BEMS Server Migration Funded Planning: June 2016 Delivery: t,b.c. | Plan This project has been carried over from 14/15. The decision to delay the project unti May 2016 was taken to enable further time for the Energy department to review the new version of software. - project to commence in May 2016 - initial planning phase scheduled to be completed in June 2016 - By delaying the project to commence in May 2016, the initial project budget of 100 days has been re-adjusted with 35 days activity planned for 15/16 with the remainder in 16/17 - delivery date to be confirmed Dependencies - will require a large commitment from Estates and Buildings Energy department throughout all stages of the project - will require a significant input from IS Applications Development Technology team and the supplier Schneider throughout the project |
AP56-063 Archibus Upgrade Funded Planning: May 2016 Delivery: July 2016 | Plan - project has been rescheduled to commence in May 2016 - due to the ongoing activitry with the HelpDesk and EBIS OnLine Upgrade projects - initial planning phase scheduled to be completed in May 2016 - delivery date scheduled for July 2016 Dependencies - the release of the next major release of Archibus - the involvement of specific Estates and Buildings personnel to assist with user acceptance testing for the Archibus client, WebCentral based applications and EBIS Online - requirement to avoid upgrade during any Archibus related product installation |
Section Three: Projects in Progress
Project Info | Project Managers Commentary | ||||||||||||||||
EST080 (AP45-016) Estates Department Help Desk Funded
Milestones
RAG Status Green
| Report by Anne Mathison for March 2016Achievements
Issues
Next Steps
| ||||||||||||||||
EST083 (AP45-013) Estates and Buildings Financial Management Process Review - Phase 2 Compliance Milestones
RAG Status Red | Report by Ben Armstrong for March 2016Achievements in Last Period
Issues
Next Steps
Due to the budget increase, the project status has been assigned as RED, as the budget increase was more than 20%. | ||||||||||||||||
EST084 (AP34-015) Estates and Buildings Document Management Extranet Discretionary Milestones
RAG Status Green
| Report by Anne Mathison for March 2016Achievements:
Issue
Next Steps:
Due to agreement of the milestones, this project has been assigned a GREEN RAG status | ||||||||||||||||
EST087 (AP56-062) Energy Systems Consolidation Funded Milestones
RAG status Green | Report by Andrew Stewart for March 2016
Achievement in Last Period
Issues
Next Steps
| ||||||||||||||||
Capital Budgeting Funded Milestones
RAG status Amber | Report by Andrew Stewart for March 2016Achievements in Last Period
Issues
Next Steps
The poroject manager has assigned a RAG status of Amber, whilst seeking clarity regarding the direction of the project | ||||||||||||||||
EST089 (AP56-065) Perspective Upgrade Funded Milestones
RAG status Blue | Report by Andrew Stewart for March 2016Achievements in Last Period
Issues
Next Steps
| ||||||||||||||||
EST090 (AP56-065) Waste Management System Upgrade Sponsor Funded Milestones
RAG status Blue | Report by Andrew Stewart (on behalf of Elaine Wighton) for March 2016
Achievements in the last period
Issues
Next steps
| ||||||||||||||||
EST091 (AP56-014) EBIS OnLine ColdFusion Upgrade Compliance Milestones Projected
Rag Status Amber | Report by Chris Lawford for March 2016Achievements in Last Period
Issues
Next Steps
Due to potential slippage regarding the live deployment, the project has been assigned a RAG status of Amber | ||||||||||||||||
EST092 (AP56-061) Estates Operational Reports Funded Milestones
Rag Status Green | Report by Chris Lawford for March 2016Achievements in Last Period
Issues
Next Steps
| ||||||||||||||||
EST093 (AP56-060) Estates Strategic Reporting Funded Milestones
Rag Status Green | Report by Chris Lawford for March 2016Achievements in Last Period
Issues
Next Steps
| ||||||||||||||||
| Report by Andrew Stewart for March 2016
Achievements in Last Period
Issues
Next Steps
|
Section Four: Closed or Withdrawn Projects
Project Info | Project Managers Commentary |
AP45-017: Building Information Modelling Strategic Review | Withdrawn on 18th September 2015 |
Section Five: Programme Risks
Date | Risk Ref. | Programem Risk | Rag Status | Risk Owner |
01/09/15 | 4 | Additional Effort required to complete Estates Financial Management project - Phase 1 | Red | David Brook |
14/09/15 | 5 | Additional Effort Required to undertake Phase 2- Good Receipting | Red | David Brook |
14/09/15 | 6 | Schneider Struxureware Solution does not meet business requirements | Amber | Robert Calder |
Section Six : Programme Meeting Minutes
This section details the minutes from the programme meetings held in 2015-16
Date | Comments |
15/09/15 | Minutes from programme meeting |
23/11/15 | Minutes from programme meeting |
20/04/16 | Minutes from programme meeting |