Programme Report for August 2012
- Report Date
- August 2012
Report compiled by Maurice Franceschi (IS Apps Programme Co-ordinator) for Jared Taylor (Programme Owner)
Section One: Programme Commentary, RAG and Resources Update
Section Two: Projects Not Started
Section Three: Projects In Progress
Section Four: Closed or Withdrawn Projects
Section One: Programme Commentary, RAG and Resources Update
With a need to move the portal onto supported infrastrcture, the programme budget needs to be applied effectively if it is to deliver (some of) My Group as well as the enhancements that have been listed as changes to portal to faciliate easier exam board experience for students and administrators.
Actions from Programme Meeting
Section Two: Projects Not Started
| Project Info | Programme Manager's Commentary |
AP23-033 ECA Portal My Groups ECA Ring-Fenced Milestones TBC
RAG Status Amber | Plan Other work has risen in priority which probably lead to this proposal beign descoped or even withdrawn. Decision to be made in September.
Dependencies None |
Section Three: Projects in Progress
| Project Info | Project Managers Commentary |
Section Four: Projects Closed / Withdrawn
| Project Info | Project Managers Commentary |
Actions from Programme Meeting (19th Sept)
| ) Craig to pick up Infrastructure project - if not possible Maurice to get another project manager. Right away. | Craig Maurice | Done - Craig is PM |
Jared will work with colleagues on an analysis of the portal content and triage content that is not being updated content that resides on the university website - remove from Portal? Or link from Portal? Content that is best kept in the portal
And where from Website do we link back to portal, and consider a MyED launcher
And ECA to commit to maintianing the
I think that if at the end of the exercise ECA could articulate their vision for the portal in the medium term ... more than an VLE, just a VLE, the main resource from where students start ... it would help | Jared ECA | Pending |
Craig to organise an estimation meeting with John A. so we can get a rough budget for the enhancements for the board : project to eb set up with delivery date April | Craig | Pending |
Need to chunk up the My Groups requirements and focus on the highest priority - List of Groups for example. After 1) and 2) and 3) are done, then whatever budget is left will be prioritised for My Groups. Do we already have this requirements/task breakdown? | Jared | Pending |