Commentary

The outstanding work on both projects has progressed, with some work to complete it is expected that the programme will now close in October 2019. 

Resource Position

 

 

Section Two: Projects Not Started

Project Info Project Manager's Commentary

NONE

N/A

 

Section Three: Projects in Progress

Project Info Project Manager's Commentary

DTI020 - Notifications Service - Rollout, Integrations and Subscribers

Discretionary

Milestones

Closure

 04/10/2019

 

RAG Status :

GREEN

 

 

Report by Karen Stirling for September 2019

Achievements in last period

  • Completion Report reviewed by project team, project sponsor and programme manager

  • Closure review meeting held and gained agreement for project to close

Issues

  • None

Next steps

  • Submit project closure to final Programme Board and WIS

 

The project status is currently GREEN

 

 

DTI044 - UCP uPortal5, Content Migration and UI Redesign

Discretionary

Milestones

Deployment Review 25-Jul-2019
Project Closure 31-Jul-2019

 

RAG Status: GREEN

Report by Tim Gray for September2019

 

 

 

 

 

 

Section Four: Closed or Withdrawn Projects

Project Info Project Managers Commentary
   

 

Programme Status
RAG Status
Overall
GREEN
Has formal escalation taken place?