Report for June 2019
- Report Date
- June 2019
Report compiled by Tim Gray, IS Apps Programme Manager for Lisa Dawson (Programme Owner)
Section One: Programme Commentary, RAG and Resources Update
Section Two: Projects Not Started
Section Three: Projects In Progress
Section Four: Closed or Withdrawn Projects
Section One: Programme Commentary, RAG and Resources Update
Commentary
In this reporting period, work has continued on both projects. The UCP project will switch over the new MyEd as planned on 11th July.
Resource Position

Section Two: Projects Not Started
| Project Info | Project Manager's Commentary |
|
NONE |
N/A |
Section Three: Projects in Progress
| Project Info | Project Manager's Commentary | ||||||||||
|
DTI020 - Notifications Service - Rollout, Integrations and Subscribers Discretionary Milestones
RAG Status : GREEN
|
Report by Karen Stirling for June 2019 Achievements in last period
Issues
Next steps
The project status is currently GREEN
|
||||||||||
|
DTI044 - UCP uPortal5, Content Migration and UI Redesign Discretionary Milestones
RAG Status: GREEN |
Report by Chris Copner for June 2019 Achievements in Last Period
Communications Plan
Issues
Next steps
|
Section Four: Closed or Withdrawn Projects
| Project Info | Project Managers Commentary |