- Report Date
- February 2019
Report compiled by Tim Gray, IS Apps Programme Manager for Lisa Dawson (Programme Owner)
Section One: Programme Commentary, RAG and Resources Update
Section Two: Projects Not Started
Section Three: Projects In Progress
Section Four: Closed or Withdrawn Projects
Section One: Programme Commentary, RAG and Resources Update
Commentary
Good progress has been made in the reporting period, especially on the UCP project. The project resolved challenging resource issues and remains on track to deliver the preview to Students in the next reporting period.
Resource Position

Section Two: Projects Not Started
| Project Info |
Project Manager's Commentary |
|
NONE
|
N/A
|
Section Three: Projects in Progress
| Project Info |
Project Manager's Commentary |
|
DTI020 - Notifications Service - Rollout, Integrations and Subscribers
Discretionary
Milestones
RAG Status :
AMBER
|
Report by Karen Stirling for February 2019
Achievements in last period
-
WP0 Apereo Open Source - MyEd and Notifications information presented at ESUP:Portail Days/Apereo by Anne Marie Scott on 5th February 2019
-
WP1 - Estimation of key outstanding JIRAs, 6 days effort to be planned in post April
-
WP3 Exam Scheduler – some minor changes have been fixed and tested ready for deployment to Live
-
Service team with Student Surveys testing notifications and perform load testing
Issues
- Review and revise remaining milestones and assess any impact / dependencies form DTI044
- Main developer resource conflicts with DTI044 and annual leave planned from mid March to mid April therefore WP2 developments may not be able to commence until mid April
- Main developer resource conflicts with other projects to allow investigation into Alma webhooks
- Key helpdesk contact is leaving university at beginning of April
Next steps
-
WP2 Library – estimate effort for 2 triggers for Library
-
On-going engagement Library and Helpdesk team
-
On-going engagement by Service team with Finance to test notifications
-
Service notifications for Student Systems to be issued out in March
-
Engagement with ACE
The project status is currently AMBER
|
|
DTI044 - UCP uPortal5, Content Migration and UI Redesign
Discretionary
Milestones
RAG Status: GREEN
|
Report by Chris Copner for February 2019
Achievements in Last Period
Infrastructure, Framework, UI
-
Some work required on scripts to sync MyEd from IDM data (this is on critical path)
-
Accessibility testing completed – no issues preventing deployment of release 1.0; accessibility testing will continue in preparation for releases 2.x and 3.x
-
EqIA completed and approved
-
Load testing suggests that there are no issues at this point which would prevent us going live with the Preview release. Load testing will, however, continue during the rest of the project up to the final release in May
Content Migration
-
20 portlets in MVP release 1.0 migrated and signed-off (by service or channel-owner)
-
Some outstanding sign-offs
-
One portlet on critical path (Library Account / Library Search)
-
A small number of portlets won’t be available in the initial release
Communications Plan
-
6/3/19 – Go / No Go decision for release of MVP release 1.0 from Board
-
7/3/19 - email to DOPs (issued by Internal Comms)
-
w/c 11/3/19 – email to staff and students (issued by Internal Comms)
-
w/c 11/3/19 – posts on staff and student news channels and student eNewsletter (issued by Internal Comms)
-
12/3/19 - demos for Service Desk (two demos back-to-back)
-
13/3/19 - filming for creation of video communications promoting the forthcoming improvements and benefits to MyEd
-
w/c 18/3/19 - screen savers on open access lab screens and Student Association screens, promoting the changes to MyEd
-
w/c 15/4/19 – release of video communications promoting the forthcoming improvements and benefits to MyEd
Issues
Next steps
- Go / No Go decision for release of MVP release 1.0 from Board
- Communications as per summary above
- Work for Release 2.x
|
Section Four: Closed or Withdrawn Projects
| Project Info |
Project Managers Commentary |
| |
|