- Report Date
- December 2018
Report compiled by Tim Gray, IS Apps Programme Manager for Lisa Dawson (Programme Owner)
Section One: Programme Commentary, RAG and Resources Update
Section Two: Projects Not Started
Section Three: Projects In Progress
Section Four: Closed or Withdrawn Projects
Section One: Programme Commentary, RAG and Resources Update
Commentary
The headlines: good progress has been made on both projects this month. In the notifications project, the work package covering the Exam Scheduler was successfully deployed to LIVE. The UCP project has continued with development, student and content owners engagement. A more detailed comms plan has been signed off.
With 3 year planning now underway, two bids will be submitted to this process, one covering continuous improvement will be submitted to LTW and with a second to support process implementation from SEP submitted through Digital Transformation.
Resource Position

Section Two: Projects Not Started
| Project Info |
Project Manager's Commentary |
|
NONE
|
N/A
|
Section Three: Projects in Progress
| Project Info |
Project Manager's Commentary |
|
DTI020 - Notifications Service - Rollout, Integrations and Subscribers
Discretionary
Milestones
RAG Status :
GREEN
|
Report by Karen Stirling for December 2018
Achievements in last period
-
WP0 Apereo Open Source – meeting with Ian Dolphin, Apereo and CCLA signed off by Jennifer Milne
-
WP2 Library & Cards – further session held with Library contacts to review triggers and identify further information for scope.
-
WP3 Exam Scheduler – Pilot (Divinity) group now completed. Feedback due 9th January 2019.
-
On going engagement with UNICON
-
Project activity with Exam Scheduling team
-
Project activity with Library and Helpdesk contacts
-
Service team engagement with Student Surveys
Issues
- Review sustainability of service going forward
-
Review and revise remaining milestones and assess any impact / dependencies form DTI044
-
Review options for further funding to expand notifications for staff (this was part of the original DTI proposal in 2016 for future phases)
Next steps
-
WP0 Apereo Open Source - close off JIRAs and management of community activity to sit with new Service Manager, agree closure of WP
-
WP2 Library – liaising with service for updated triggers/process maps, investigating Alma API
-
WP3 Exam Scheduler – agree (9/1/19) when next scheduled exams to be activated, close WP
-
Ongoing engagement with Exam Scheduling team and Library and Card Services team
-
Ongoing engagement by Service team with Student Surveys to test notifications and perform load testing
The project status is currently GREEN
|
|
DTI044 - UCP uPortal5, Content Migration and UI Redesign
Discretionary
Milestones
RAG Status: GREEN
|
Report by Ranald Swanson for December 2018
Achievements in Last Period
-
Infrastructure and Framework
-
LIVE/Preview server configured (puppet/bamboo deployments configured)
-
Single sign-on verified
-
Load testing requirements identified, tool selected. Execution of load testing to be tied to major releases
-
UI and Student Validation
-
Content Migration – Channel Owner Engagement
-
Migration plan developed for Release 1.x (student opt-in) and Release 2.x (all user opt-in)
-
Path, Event booking, Cashless Catering, Change EASE password, Student Homes, Moodle, Timetabling, campus maps, MyEd Announcements, Parking Permits portlets all migrated for UAT
-
Project being managed with 2-week Agile sprints.
-
Communications plan on schedule
Risks and Issues
Next Steps
|
Section Four: Closed or Withdrawn Projects
| Project Info |
Project Managers Commentary |
| |
|