Report for July 2018

Report Date
July 2018

Report compiled by Tim Gray, IS Apps Programme Manager for Lisa Dawson (Programme Owner)

 

Section One: Programme Commentary, RAG and Resources Update

Section Two: Projects Not Started

Section Three: Projects In Progress

Section Four: Closed or Withdrawn Projects 

Section One: Programme Commentary, RAG and Resources Update

Commentary

TG add commentary

Overall Programme RAG: AMBER

Forward Look and RAG

Resource Position

 

Section Two: Projects Not Started

Project Info Project Manager's Commentary

 

NONE

 

N/A

 

Section Three: Projects in Progress

Project Info Project Manager's Commentary

DTI011

User Centred Portal Pilot

Discretionary

Milestones

27/07/2018 Closure

 

RAG Status :

BLUE

 

Report by Ranald Swanson for July 2018

DTI020

Notifications Service - Rollout, Integrations and Subscribers

Discretionary

Milestones (Under review)

13-Jul-2018

     Work Package 1 - Pilot Rollout Evaluation complete

20-Jul-2018

     Work Package 1 – Pilot Deployment Review Sign Off

Under review

     Work Package 0 - Apereo Source Code Complete

Under review

     Work Package 4 - New Subscriber Notifications commence

Under review

     Work Package 2 - Notifications for Alma and Card Services complete

Under review

     Work Package 3 - Notifications for Timetable Changes

Under review

     WP1 Full Rollout of Service completed

Under review

     Closure

 

RAG Status :

AMBER

 

 

Report by Karen Stirling for July 2018

 

DTI044 - UCP uPortal5, Content Migration and UI Redesign

Discretionary

Milestones

27-Jul-2018 Production uPortal5 Installed (D5.03)
03-Aug-2018 MyEd Progressive Framework Design (MyEd Deployed to Dev) Created (D3.01) (Review Date)
03-Aug-2018 Content Migration Strategy (Process and Technical) Documented (D6.05)
03-Aug-2018 Initial User Access UI Agreed (D7.05)
03-Aug-2018 Iteration 1 August 2018 Checkpoint (D9.01)
07-Sep-2018 MyEd v4.3 New Content Freeze (D8.04) (Review Date)
07-Sep-2018 Iteration 2 September 2018 Checkpoint (D9.02)
05-Oct-2018 Iteration 3 October 2018 Checkpoint (D9.03)
02-Nov-2018 Iteration 4 November 2018 Checkpoint (D9.04)
09-Nov-2018 MyEd Progressive Framework Design (Final) Created (D3.04) (Review Date)
09-Nov-2018 All MyEd 4.3 Content Actioned (D8.7) (Review Date)
07-Dec-2018 All UoE Users Transferred to MyEd Progressive (D10.04) (Release to Live)
07-Dec-2018 MyEd v4.3 Decommission (D10.05) (Review Date)
07-Dec-2018 Iteration 5 December 2018 Checkpoint (D9.05)
18-Jan-2019 Iteration 6 January 2019 Checkpoint (Deployment Review)
22-Feb-2019 Project Closure (D11.01)

RAG Status: AMBER

 

 

 
Report by Ranald Swanson for July 2018

 

 

 

 

 

 

 

Section Four: Closed or Withdrawn Projects

Project Info Project Managers Commentary
WEB009 MyEd Upgrade

Report by Karen Stirling

This project was closed 24th October 2017

Completion report

DTI012

 Raised by Karen Stirling

This project was withdrawn 13th October 2017

PICCL 1

AP78-104 MyEd Small Improvements  

Raised by Karen Stirling

This proposal was withdrawn 20th April 2018

PRICCL

 

Notes from Programme Meeting

Note Action Status