- Report Date
- March 2018
Report compiled by Karen Stirling, IS Apps Programme Manager for Lisa Dawson (Programme Owner)
Section One: Programme Commentary, RAG and Resources Update
Section Two: Projects Not Started
Section Three: Projects In Progress
Section Four: Closed or Withdrawn Projects
Section One: Programme Commentary, RAG and Resources Update
Commentary
The UCP & Notifications Programme activity still progressing :
- DTI011 re-plan is now out for senior management review and will be presented to Steering Group on 18th April (delayed due to unavailability of steering group members for meeting planned on 30th March).
- Also SAS002 evaluation of contact details for approval and agreement to close down project.
- Requests for new project for UCP re-plan under DTI044 has been agreed and also SAS012 for Contact Details Rollout
- DTI020 is gathering momentum following discussions with USD and Exam Scheduler project for potential integrations, the project team are preparing activity to deploy the basic notifications backbone targetting an end of May date. An interim Service Owner is in place which is helping towards replanning activities.
- The key risk to the programme is a overspend on forecast to end of financial year, areas have been identified to reduce :
- PRICCL to be raised to reduce Programme Management days allocated as unlikely to be utilised, previously highlighted to Steering Group (66 days reduction)
- Following discussions between DTI011/044 project team and MyED Service team now unlikely to require MyED Small improvements project of 50 days
- Total reduction of 116 days on programme budget
- This has been reviewed with Portfolio Manager and agreed, raised to Programme Owner for approval.
Overall Programme RAG: AMBER
Forward Look and RAG

Resource Position

Section Two: Projects Not Started
| Project Info |
Project Manager's Commentary |
|
AP78-104
MyEd Small Improvements
|
Project to be withdrawn on agreement with Programme Owner. |
Section Three: Projects in Progress
| Project Info |
Project Manager's Commentary |
|
DTI011
User Centred Portal Pilot
Discretionary
Milestones (Current to be reviewed on replan See DTI044 below)
RAG Status :
AMBER
|
Report by Ranald Swanson for March 2018
Achievements in Last Period
-
Technical Architecture design improved
-
UCP Re-scope paper (v0.6) approved by Project Sponsor, Programme Manager and Portfolio Manager.
-
DTI044 approved by WIS 30/3/18 based on UCP Replan v0.6. Agreed, v0.6 form basis of a Project Brief document/project plan for DTI044.
-
Infrastructure lead, production management and graphic design leads engaged in project.
- Risk/PICCL Logs up-to-date
Issues
Next Steps
-
Suspend DTI011 from 6/4/18 (subject to WIS approval). Remove ASTA remaining effort from DTI011 (as soon as all timesheets up-to-date to 6/4/18). Submit PICCL to cover changes in milestones.
-
Close all DTI011 PICCL, Risks and other logs
- Create/update DTI044 project plan, risks, PICCL, benefits and Project Brief/Plan
- DTI011 Project closure actions to begin.
The project status is AMBER as re-scope plan to be approved by Steering Group. Scope reduced by Sponsor to remove new content, but infrastructure, content audit, UI redesign, content migration (refactor and rebuild) all still in scope.
|
|
DTI020
Notifications Service - Rollout, Integrations and Subscribers
Discretionary
Milestones (Under review)
RAG Status :
AMBER
|
Report by Karen Stirling for March 2018
Achievements in last period
- WP1 :
- UAT Review and update of pilot JIRAs
- Service documentation out for review with interim Service Owner
- Discussions with Lisa Dawson and Colan Mehaffey have identified possible triggers from EUCLID to incorporate into the service
- Draft implementation plan produced and distributed for comments
- Review possible dates for pilot rollout where reduced impact o MyEd - possible date 28th May
- WP3 : Walkthrough of Exam Scheduler workflow with BA on SAS005 project and have established options for where notifications could potentially fit into the process. A further session to be arranged with project developer to understand integration links and if any APIs are required
- WP4 : Workflow diagrams distributed for comments by project team, arrange further session to walkthrough and update with team
- Notifications Service Overview paper produced for submission to Jennifer Milne and IS Applications Senior management team
- Meeting held with Gosia Such and Neil Bruce to brainstorm potential options for Notification Service, exploring onboarding to the service, stakeholder mapping, possible integration with IS Alerts, EASE / AD synchronisation
Issues
- Key roles of Service Owner / Business Owner remains to be confirmed, Colan Mehaffey is currently fulfilling interim Service Owner role whilst LTW resource is confirmed via HR process, this has been delayed due to industrial action. Request has been issued to Gosia Such to ask if she would consider taking on Business Service Owner role.
- Project team are re-planning work packages with a view to deploy pilot in May, on proviso the project is given approval by MyED Service Owner
- Key project resource, Service Manager and Developer, have been on leave from mid March, both being available early to mid April therefore limited resource to progress project activity over this period.
Next steps
- WP0:
- Investigate Contributor agreement
- Assess progress
- WP1 : Pilot
- Preparation to rollout basic Backbone to small pilot group
- Deployment Checklist, Implementation plan, PAGS group
- Acceptance sign off
- WP1 : Investigate EUCLID triggers and meeting to discuss options for EASE/AD synchronisation process to aid on-boarding of students
- WP3: Arrange further meeting to discuss potential exam scheduler notifications
- WP4: Review and sign off workflow for SMS POC
- Project planning session to be arranged w/c 23rd April and review stakeholder mappings and communication plans
The project status is currently AMBER :
An interim Service Owner has been agreed until permanent position has been approved. Project team planning out pilot deployment and investigating other potential notifications options to take the service forward. Revised milestones to be agreed.
|
|
DTI044 - UCP uPortal5, Content Migration and UI Redesign
Discretionary
Milestones (subject to Project Brief approval)
| Baseline Target Date |
Deliverable Description
|
| 30/03/2018 |
Planning Completed
|
| 30/03/2018 |
H-L Benefits Baselined and Success Criteria Created
|
| TBC |
MyEd Progressive Framework Design (MyEd Deployed to Dev) Created
|
| TBC |
MyEd Progressive Framework Design (Final) Created
|
| 27/04/2018 |
Infrastructure Design Documented
|
| 30/06/2018 |
Live Infrastructure Built
|
| 27/07/2018 |
Production uPortal5 Installed
|
| 03/08/2018 |
Content Migration Strategy (Process and Technical) Documented (incl Migration timescales). Critical input for Iteration 1 Checkpoint D9.01.
|
| 03/08/2018 |
Initial User Access UI Agreed
|
| 02/04/2018 |
MyEd v4.3 New Content Gatekeeper Decision Point
|
| TBC |
MyEd v4.3 New Content Freeze
|
| TBC |
All MyEd 4.3 Content Actioned (Migrated, Ditched or Replaced)
|
| 01/08/2018 |
Iteration 1 August 2018 Checkpoint
|
| 03/09/2018 |
Iteration 2 September 2018 Checkpoint
|
| 01/10/2018 |
Iteration 3 October 2018 Checkpoint
|
| 01/11/2018 |
Iteration 4 November 2018 Checkpoint
|
| 03/12/2018 |
Iteration 5 December 2018 Checkpoint
|
| TBC |
All UoE Users Transferred to MyEd Progressive
|
| TBC |
MyEd v4.3 Decommission
|
| TBC |
Closure Tasks
|
RAG Status:
AMBER
|
- Report Date
- March 2018
Achievements in Last Period
-
Technical Architecture design improved
-
UCP Re-scope paper (v0.6) approved by Project Sponsor, Programme Manager and Portfolio Manager.
-
DTI044 approved by WIS 30/3/18 based on UCP Replan v0.6. Agreed, v0.6 to form basis of a Project Brief document/project plan for DTI044.
-
Infrastructure lead, production management and graphic design leads engaged in project.
- Risk/PICCL Logs up-to-date
- ASTA resources booked for PM, Programme Manager, Devtech, uPortal5 Developer, Technical Lead
Issues
Next Steps
-
Milestones and Benefits logs to be created
-
Project Brief to be drafted and circulated for approval
-
Unicon SoW to be drafted and approved
The project status is AMBER overall as Project Brief still to be approved.
|
Section Four: Closed or Withdrawn Projects
| Project Info |
Project Managers Commentary |
| WEB009 |
Report by Karen Stirling
This project was closed 24th October 2017
Completion report
|
| DTI012 |
Raised by Karen Stirling
This project was withdrawn 13th October 2017
PICCL 1
|
Notes from Programme Meeting