Report for February 2018
- Report Date
- February 2018
Report compiled by Karen Stirling, IS Apps Programme Manager for Lisa Dawson (Programme Owner)
Section One: Programme Commentary, RAG and Resources Update
Section Two: Projects Not Started
Section Three: Projects In Progress
Section Four: Closed or Withdrawn Projects
Section One: Programme Commentary, RAG and Resources Update
Commentary
Both UCP & Notifications projects require to be re-planned:
- DTI011 is in the process of re-planning, project resource will have to be confirmed and any additional funding be agreed within DTI portfolio and with Programme Owner this may be dependant on the scope of the re-planned deliverables
- DTI020 put forward an options paper to Steering Group in February however there has been no resolution to the ownership of the Notifications Service, this has been escalated within LTW and IS Applications Directorates. Re-planning exercise will be required on a reduced scope when ownership has been agreed.
- The overall programme is AMBER, project activities remain in progress, concerns remains regarding programme budget which have been raised at Steering Group level
- Programme Risk Review meeting held on 6th February.
Overall Programme RAG: AMBER
Forward Look and RAG

Resource Position

Section Two: Projects Not Started
| Project Info | Project Manager's Commentary |
|
AP78-104 MyEd Small Improvements |
Project start to be agreed with Project Sponsor. |
Section Three: Projects in Progress
| Project Info | Project Manager's Commentary |
|
Discretionary Milestones (Current to be reviewed on replan)
RAG Status : AMBER
|
Report by Ranald Swanson for February 2018Achievements in Last Period
Issues 1. PICCL24 (https://www.projects.ed.ac.uk/unpublished/project/dti011/issues/24) for Milestones updated with rescoped plan. 2. PICLL25 (https://www.projects.ed.ac.uk/unpublished/project/dti011/issues/25) for database upgrad. Managed within project. Next Steps
The project status is AMBER - At Amber as rescope plan to be approved by Steering Group. Scope reduced by Sponsor to remove new content, but infrastructure, content audit, UI redesign, content migration (refactor and rebuild) all still in scope..
|
|
DTI020 Notifications Service - Rollout, Integrations and Subscribers Discretionary Milestones (Under review) RAG Status : RED |
Report by Karen Stirling for February 2018Achievements in last period
Issues
Next steps
The project status is currently RED : Project remains impacted by no resolution to agreement of role of Service and Business Service Owner and has been escalated within IS Apps. Until this is resolved the project team are unable to produce a revised plan in alignment with the options paper submitted to UCP Steering Group in February.
|
Section Four: Closed or Withdrawn Projects
| Project Info | Project Managers Commentary |
| WEB009 |
Report by Karen Stirling This project was closed 24th October 2017 |
| DTI012 |
Raised by Karen Stirling This project was withdrawn 13th October 2017 |
Notes from Programme Meeting
| Note | Action | Status |
|---|---|---|
| Attachment | Size |
|---|---|
| 125.2 KB | |
| 90.16 KB |

