Report for Dec 2019
- Report Date
- December 2019
Programme Commentary
Overall BI/MI Programme is RED.
DTI049 - HR Strategic Reporting - has completed 7 x 3-week agile sprints and Sprint 8 is now in progress, Alpha release to Live has been delayed from Jan 2020 to March 2020
DTI049 - RED - will require additional budget allocation from DTI fixed budget , as it hasn't yet completed the load of the legacy HR data , and still has to load the new HR data from Core systems
DTI050 - RED - Finance Strategic reporting - planning stalled while focusing on HR Strategic Reporting
Both DTI049 and DTI050 have been set to Higher priority on the IS Applications overall priority scale ( up from 'Normal' to 'Higher') . This is a 3 step priority scale from Normal to Higher to Highest.
BI / MI Programme - Key Achievements in Last Period
- DTI049 Sprint 7 completed - Prep for Alpha release
- DTI049 Sprint 8 - in progress - run History jobs in DEV and promote Alpha release to TEST
BI / MI Programme - Top Issues
- Design review required to re-work history load jobs and snapshots to get balance between build cost and user benefits
- Difficulties agreeing BI/MI scope boundaries with SEP People and Money, around 'Historic Data Store' (HDS) and how the business requirements will be met
- Agreed Business Analyst resource from SEP People and Money not available yet
BI / MI Programme - Key Next Steps
- Agree programme brief with stakeholders.
- Estimate size of each separate datamart project - HR datamart , Finance and Payroll datamarts and eRecruitment datamart - to feed into overall sprint planning - how many sprints per project
- Confirm resourcing commitment with IS Production Management ( estimated 0.2 FTE) - who and when and governance for agreeing changes as project goes through the different stages of built & Test
- Agree scope limitations and expectations with SEP Core Systems programme / REF / Historical data store
- Programme Risk Review and consolidate related EDW/BI Tools risks.
- Agree comms plan with Lynda Hutchison and Programme stakeholders
--
RAG Forward Look to end of Dec 2019

Resources to the end of Dec 2019

Section Two: Projects Not Started
| Project Info | Programme Manager's Commentary |
|
Project Code / Project Name Category: Compliance / Discretionary |
New projects in the DTI plan for 19/20
|
Section Three: Projects in Progress
| Project Info | Project Managers Commentary |
DTI049 HR Strategic ReportingCategory: Discretionary Milestones
RAG StatusRED |
Report by Jamie Thin for Dec 2019
Achievements this period
Issues
Next Steps
RAG Commentary *RED Issue* - Time - can't deliver full HR datamart for legacy and new HR data by June 2020. Project requires more time and budget. Resource conflict with Finance Datamart queued behind HR. If Finance work is more important than HR, then some HR work might need to be put on hold to focus on Finance. There are also resource conflicts across the business leads , HR SME's across the university who are also working on the ERP implementation at the same time , and the People and Money ERP implementation takes priority over the DTI Strategic reporting work. *Business Impact* - First alpha release of the HR datamart with legacy data may not be available until Feb 2020 , Work hasn't yet started on the new People & Money HR data which will be consumed via APIs from the cloud ERP. The Beat release joining up data from legacy data source and new data source may be not be ready for the June 2020 SEP People and Money HR Go-Live. Actual impact on business activities is unknown at this point in time. Some business planning activities may not have access to best longitudinal data to pick out trends - or this data may still be available, but might have to be cobbled together by MI analysts from multiple separate sources taking more effort and time. *Action to get project back to AMBER or GREEN* - By end of Feb, the impact of the SEP core systems re-plan should be known. If some of the SEP core system delivery milestones move - then it is likely the project RAG can move to AMBER as there will be more time to complete work on the HR datamart. If the SEP People and Money HR go-Live stays as a hard deadline in June 2020 - then as a contingency, discussions have started with budget holders to request additional funding to scale up the BI team - so that work on the HR and Finance datamarts can be done in parallel. Note there is currently no DTI funding for the BI project team beyond July 2021. This funding cap will curtail the scope of datamart development work. Once the HR and FInance datamarts have been delivered, there will need to be funding for some BI resources in IS Apps beyond July 2021 to maintain the datamarts and EDW to ensure a sustainable transition to business-as-usual. |
||||||||||||||||||||||||||||||
DTI050 Finance Strategic ReportingCategory: Discretionary Milestones
RAG StatusRED |
Report by Jamie Thin for Dec 2019
Achievements this period
Issues
Next Steps
|
Section Four: Closed or Withdrawn Projects
| Project Info | Project Managers Commentary |
|
Project Code / Project Name Category: Compliance / Discretionary |
**Add** Report by PM This project was closed on .... Please see the Completion Report for further information. |
|
|
| Attachment | Size |
|---|---|
| 19.86 KB | |
| 35.24 KB |