Report for Nov 2019

Report Date
November 2019

Programme Commentary

Overall BI/MI Programme is RED.

DTI049 - HR Strategic Reporting - has completed five x 3-week agile sprints and Sprint 6 is now in progress 

DTI049 will require additional budget , as it hasn't yet completed the load of the legacy HR data , and still has to load the new HR data from Core systems (AMBER)

DTI050 - Finance Strategic reporting -   planning stalled while focusing on HR Strategic Reporting (RED)

Both DTI049 and DTI050 have been set to Higher priority on the IS Applications overall priority scale ( up from 'Normal' to 'Higher') . This is a 3 step priority scale from Normal to Higher to Highest.

 

BI / MI Programme - Key Achievements in Last Period

  • DTI049 Sprint 5 completed - Access layer prototype in DEV
  • DTI049 Sprint 6 planning done and new sprint started

 

BI / MI Programme - Top Issues

 

  • Some of the BI team resources had to be assigned to the EST109 Estates Strategic Reporting project - to get that project over the line for start of UAT Phase 2
  • Difficulties agreeing BI/MI scope boundaries with SEP Core Systems, due to their need of a 'Historic Data Store' (HDS) and expectations this would have been delivered by the EDW programme.

...this may utilise the data warehouse, although other options should be investigated and the requirements are not yet understood. Advice from Enterprise Architecture has led to invalid assumptions that this will met through the DT funded BI Team, whereas it will need its own management and resourcing. Had previously agreed this with Core Systems but now needing to clarify that position again.

  • Agreed Business Analyst resource from Core Systems not forthcoming.

...expected a dedicated resource to proactively cover reporting requirements but BAs have had delays in recruitment (expected July) and SEP process is to submit individual work package requests. Current expectation is to not receive much help for the analysis of strategic reporting requirements or data sourcing from existing systems, mitigated as much as possible by an increase in GaSP MI Analyst time seconded to the programme until the end of this year at least. Ideally need to increase Enterprise Architecture (EA) input this year to cover increased data sourcing analysis but EA team has limited spare capacity.

 

BI / MI Programme - Key Next Steps

  • Agree programme brief with stakeholders.
  • Estimate size of each separate datamart project -  HR datamart , Finance and Payroll datamarts and eRecruitment datamart - to feed into overall sprint planning - how many sprints per project
  • Confirm resourcing commitment with IS Production Management ( estimated 0.2 FTE) - who and when and governance for agreeing changes as project goes through the different stages of built & Test
  • Agree scope limitations and expectations with SEP Core Systems programme / REF / Historical data store
  • Programme Risk Review and consolidate related EDW/BI Tools risks.
  • Agree  comms plan with Lynda Hutchison and Programme stakeholders 

--

RAG Forward Look to end of Nov 2019

 

BIMI RAG to end of Nov 19

 

 

 

 

Resources to the end of Nov  2019

 

BIMI Actual spend to end of Nov 19

 

 

 

 

Section Two: Projects Not Started 

 

Project Info Programme Manager's Commentary

Project Code / Project Name

Category: Compliance / Discretionary

New projects in the DTI plan for 19/20

 

 

Section Three: Projects in Progress

 

Project Info Project Managers Commentary

DTI049 HR Strategic Reporting

Category: Discretionary

Milestones

 

Stage Milestone Status
Sprint 1 complete 03-Sep 2019 Done
Sprint 2 complete 24-Sep 2019 Done
Sprint 3 complete 15-Oct 2019 Done
Sprint 4 complete 05-Nov 2019 Done
Sprint 5 complete 26-Nov 2019 Done
Sprint 6 complete 17-Dec 2019 In progress
Alpha release  27-Jan 2020 Provisional estimate

 

RAG Status

AMBER

 

Report by Jamie Thin for Nov 2019

 

Achievements this period

  • Sprint 5 completed - HR - Access layer prototype , Estates UAT re-work
  •  Sprint 6 started - Access layer basic star schema / connection to BI Tools
  • Git / Bamboo - Synch  between DEV and TEST has been done for Foundation layer

Issues

  • Git / Bamboo - Synch to LIVE requires a couple of scripts to be run in LIVE - delayed due to change freeze for the strike
  • Budget will need to be increased - 253 days has been spent from initial allocation of 300 days and this is for the load of historic legacy data before the new core data is loaded 

Next Steps

  • Full backlog to be collected for the HR datamart
  • Complete Sprint 6
  • Plan Sprint 7 
  • Alpha release to LIVE

  

 

DTI050 Finance Strategic Reporting

Category: Discretionary

Milestones

 

Stage Milestone Due Date
Planning End of Planning Feb 2020

 

RAG Status

RED

Report by Jamie Thin for Nov 2019

 

Achievements this period

  • limited activity while focus on HR Strategic reporting
  • BI/MI Road map updated to push start of Finance datamart build later into 2020

Issues

  • Discussion to agree Project Sponsor , and other project roles stalled  - potential capacity issue for key people - as these same people are already fully committed to DTI BIMI HR ,  SEP core systems and Finance Transformation work
  • Planning delayed / End of Planning milestone will move back several months into Q1 2020

Next Steps

  • Start Planning - rough sizing and set outline milestones
  • Start user engagement and start gathering use stories
  • Set up Agile tools - JIRA Board , start creating Backlog of User stories
  • Agree MVP ( Minimum Viable Product) , and agree priority areas within the large scope of Finance Strategic Reporting

Section Four: Closed or Withdrawn Projects

 

Project Info Project Managers Commentary

Project Code / Project Name

Category: Compliance / Discretionary

**Add**

Report by PM

This project was closed on ....

Please see the Completion Report for further information.

 

 
Programme Status
Has formal escalation taken place?
No