Report for Aug 2019

Report Date
August 2019

 

Programme Commentary

Overall BI/MI Programme is AMBER.

DTI049 is AMBER until the sprint velocity is understood and a better overall estimate of cost to complete the HR datamart is known

- starting assumption is 6 dev sprints + 2 maintenance sprints and budget of 350 + ISG days effort

 

BI / MI Programme - Key Achievements in Last Period

  • DTI049 Sprint 1 started

 

BI / MI Programme - Top Issues

 

  • Difficulties agreeing BI/MI scope boundaries with SEP Core Systems, due to their need of a 'Historic Data Store' (HDS) and expectations this would have been delivered by the EDW programme.
  • Agreed Business Analyst resource from Core Systems not forthcoming.

 

 

BI / MI Programme - Key Next Steps

  • Agree programme brief with stakeholders.
  • Estimate size of the HR datamart , Finance datamart and eRecruitment datamart - to find into overall sprint planning - how many sprints per project
  • Initiate Discovery/Analysis project for  Finance strategic reporting requirements and data sourcing
  • Confirm resourcing commitment with Service Management.
  • Agree scope limitations and expectations with SEP Core Systems programme
  • Programme Risk Review and consolidate related EDW/BI Tools risks.
  • Arrange comms plan with Shaun and BI Team.

--

RAG Forward Look to end of Aug 2019

 

DTI BI Tools RAG at end of July 2019

 

 

Resources to the end of Aug 2019

 

BI/MI Programme - actual spend to end of July 2019

 

 

 

Section Two: Projects Not Started 

 

Project Info Programme Manager's Commentary

Project Code / Project Name

Category: Compliance / Discretionary

New projects in the DTI plan for 19/20

 

 

Section Three: Projects in Progress

 

Project Info Project Managers Commentary

DTI049 BI Reports Discovery

Category: Discretionary

Milestones

 

Stage Milestone Due Date
Build    

 

RAG Status

AMBER

 

Report by Jamie Thin for July 2019

 

Achievements this period

  • Design and Build of the HR datamart has started
  • Project team attended 2 days agile training 
  • Project team are starting working to a scrum agile methodology
  • Initial backlog has been added to Jira 
  • Project Manager handover completed from Geoff Cropely to Jamie Thin

Issues

  • Long term solution for managing connections to EDW from BI tools to be resolved
  • Potential resource conflict with EST109 - Estates Strategic reporting - depending what new work arises out of the Estates UAT
  • Dependency on EST109 is preventing changes to EDW Access layer from being promoted to TEST
  • Waiting confirmation that the eRecruitment datamart has been formally brought into scope of the BI/MI programme

Next Steps

  • End of Planning to be completed
  • Full backlog to be collected for the HR datamart
  • Decision on whether the HR , eRecruitment and FInance datamarts should be separate projects within the BI/MI programme , or separate work packages in the DTI049 project

  

 

Section Four: Closed or Withdrawn Projects

 

Project Info Project Managers Commentary

Project Code / Project Name

Category: Compliance / Discretionary

Report by PM

This project was closed on ....

Please see the Completion Report for further information.