Pure API made available to 3 test individuals in WSO2 for test and sign off.
Unidesk API
Testing of internal API carried out and issues raised with TOPdesk for clarification.
Initial non IS testers identified to test API and access process including user documentation
Test user access requested from Dev Tech
Person ID resolver API for EDW
Resolution work reviewed and carried out.
Resolver API made available to user for test and sign off
Issues
With UniDesk upgrade on the horizon should we continue to develop the present API. It was confirmed that the API being developed at present would remain in use during the staggered upgrade and was therefore worth continuing with.
Next Steps
PURE API
Completion of testing within WSO2 and signed off.
Unidesk API
Test firewall opened for external access.
Liaise with Service Team regarding progression through internal Test and prep prior to external testing.
Promotion of API from Test to Live.
Reschedule project timescales to allow for internal and external testing and sign off.
WP 8 API Standards - reviewed and accepted into the Software Development team standards.
WP 7.1 and 7.2 Centralised Logging - review meeting held. Summary written up and being reviewed prior to sign off.
Issues
Final deliverables for WP 6.1 & 6.2 require review workshops and raised at the OGG. These are scheduled for Jan 2020. For the purpose of this project they can be taken as signed off after the workshops have been completed.
Next Steps
Summary statement on WP 7.1 and 7.2 Centralised Logging to be signed off following review.
Complete security document workshops.
Project closure.
DTI029 Maturing the API Service
Revised Milestones To Be Confirmed
RAG: AMBER
Report for December 2019
Achievements in Last Period
Review outstanding tasks with Service Management to ensure all tasks covered. If still relevant must be addressed prior to closure or raised as an outstanding task.
Commence closure Report.
Issues
Existing milestones need updated in response to project review. Present plan is to review deliverables and their relevance in light of the evolution of the project. Project will be undertake a controlled closure with outstanding tasks being picked up by the next tranche of the programme.