We have had resource challenges this month due to long term absence. These are currently being addressed within project services.
Work on the individual projects is progressing with much of the work coming towards conclusion.
DTI018 (Continuous Service Improvement APIs) - Pure API and EDW Person API delivered to WS02. Need to confirm if UniDesk API still worthwhile with UniDesk upgrade on horizon.
DTI026 (API Gateway and API Management Tool) - Documentation review ongoing.
DTI028 (Infrastructure) - deliverables regarding security are progressing
DTI029 (Maturing the service) - tasks rescheduled for project closure.
Programme status is Amber as there have been delivery challenges in September and we have resource challenges as explained above.
Implications of WSO2 moving to the cloud have yet to be fully incorporated into the project.
Next Steps
Work on WP 7.1 and 7.2 Centralised Logging to be completed. Higher priority work delaying completion of this task at present
D6 deliverables to be logged prior to sign off.
WP 6.1 and 6.2 to be raised at Operational Guidance Group for review.
Work continuing on WP 8 API Standards.
DTI029 Maturing the API Service
Revised Milestones To Be Confirmed
RAG: AMBER
Report for October 2019
Achievements in Last Period
Events Attendance system promoted from Test to Live. Used at ISG All Staff event on 3/10/2019.
Raise PICCL to schedule tasks for project closure on 25/10/2019.
Review of outstanding tasks to identify those being picked up by Service Delivery and those outstanding.
Work commenced to close project in November.
Issues
Existing milestones need updated in response to project review. Present plan is to review deliverables and their relevance in light of the evolution of the project. Project will be undertake a controlled closure with outstanding tasks being picked up by the next tranche of the programme.
Next Steps
Review outstanding tasks. If still relevant must be addressed prior to closure.