Report for Feb 2019
- Report Date
- February 2019
Report compiled by Hilary Shand for Programme Owner
Section One: Programme Commentary, RAG and Resources Update
Programme Commentary
Majority of the programme progress has been on project DTI026.
- DTI018 (Continuous Service Improvement APIs) - Reprioritisation in progress AMBER
- DTI026 (API Gateway and API Management Tool) - progressing with installation/configuration of WS02 AMBER
- DTI028 (Infrastructure) - rescheduling of work packages RED
- DTI029 (Maturing the Service) - TOM work being considered AMBER
Programme Status is currently RED. DTI026 has changed from GREEN to AMBER due to a technical issue, resolution of which has delayed a milestone delivery . Project DTI026 has had a significant shift in milestone dates and there has been an increase in estimation of effort for a deliverable.
Section Two: Projects Not Started
There are no projects not started.
Section Three: Projects in Progress
Project Info | Project Manager's Commentary | ||||||||||||||||
DTI026 API Gateway and API Management Tool
Milestones
RAG AMBER |
Report for February 2019
Achievements in Last Period
Issues
Next Steps
|
||||||||||||||||
DTI028 Maturing the API Infrastructure Milestones
RAG RED |
Report for February 2019
Achievements in Last Period
Issues
Next Steps
|
||||||||||||||||
DTI029 Maturing the API Service New Proposed Milestones To Be Confirmed RAG AMBER |
Report for February 2019 Achievements in Last Period
IssuesNo new issues Next Steps
|
||||||||||||||||
DTI018 Continuous Service Improvement APIs New Proposed Milestones To Be Confirmed RAG AMBER
|
Report for February 2019 Achievements in Last Period
Further progress on this project has been difficult to achieve this month due to other demands on Service Leads time. As a result the new project milestones have not been determined. PM secured for the project Issues
Next Steps
|
Section Four: Closed, Suspended or Withdrawn Projects
Project Info | Project Manager's Commentary |
---|---|
DTI013 Analysis and Specification of Requirements | Project closure approved by WIS 2/2/18 |
DTI014 Enterprise API Technology | Project closure approved by WIS 17/11/17 |
DTI015 Student Record APIs | Project closure approved by WIS 1/9/17 |
DTI016 UCP Pilot API |
22/12/17 - Project withdrawal approved by WIS 22/12/17 - PICCL Change 6 6/12/17 - Recommendation is to withdraw and review requirements again in 18/19 due to PICCL Issue 5, project risk 5 13/10/17 - Project suspension approved by WIS 13/10/17 - PICCL Change 4 |
DTI017 VLE API |
Project closure approved by WIS 23/3/18 5/2/18 - Recommendation is to close project early - PICCL Decision 8 6/12/17 - Recommendation is to review conditions for removing project from suspension in 18/19, PICCL Change 7, project risk 10, project risk 11 17/11/17 - Project suspension approved by WIS 17/11/17 - PICCL Change 7 |
DTI023 Analysis and Requirements | Project withdrawal approved by WIS 15/12/17 - PICCL Change 1 |
DTI024 Maturing Student Record APIs | Project closure submitted to WIS 29/6/18 |
DTI025 Approved Small APIs | Project withdrawal approved by WIS 13/10/17 - PICCL Change 1 |
COM027 Enterprise API Foundation | Project closure approved by WIS 9/6/17 |
Section Five: Actions/Notes from monthly meeting :