Report for Oct 2018

Report Date
October 2018

Report compiled by Programme Manager for Programme Owner

Section One: Programme Commentary, RAG and Resources Update

Programme Commentary

Progress across projects is summarised below:

  • DTI018 (Continuous Service Improvement APIs) -  focus has been on determining the appropriate UAT approach for API’s. This proposal is close to being ready for consultation and approval.  This will help progress AUT stage for several API’s
  • DTI026 (API Gateway and API Management Tool) - Activities are progressing in order to make WS02 Production ready and handover to BAU. A new technical issue has been raised and is being explored further in conjunction with ITI.
  • DTI028 (Maturing the API Infrastructure) – Several work packages has been considered in more detail so adequate time can be booked for resources. These work packages are due to commence this month (Python templates and security)
  • DTI029 (Maturing the API Service) - Discussions are ongoing regarding a Target Operating Model, its scope and if it should be included in next tranche of programme. API backlog is now being managed through Jira.
  • A Project Manager has been secured to assist with Management and Control of individual projects, in particular DTI026 & DTI028
  • Programme review meeting took place on 31.10.18.  Programme Owner (Alex Carter) and Project Delivery Team Leads (Susan Cooke and Peter Pratt). Next steps identified listed below
    • Follow up meeting to specifically discuss resource and capacity of DTI018 (w/c 12th due to A/L). Debrief of HR API will be complete by then also - HS to organise
    • Ensure sufficient finance available to complete remaining deliverables - HS to perform deep dive of finances, budget spent to date and resource profile for remainder of this phase of Programme
    • Re baseline Programme plan
    • Programme Board Meeting 
    • Commence programme team meeting every 2 weeks
    • Progress work packages currently in flight
    • Update WIS December

 

Overall, the programme is AMBER at this time as the Programme milestone and budget are being reconsidered.

 

RAG Status and Forward Look

AMBER - a programme replan is in progress

Resource Summary

Section Two: Projects Not Started

There are no projects not started.

Section Three: Projects in Progress

Project Info Project Manager's Commentary

DTI026 API Gateway and API Management Tool

 

New Proposed Milestones To Be Confirmed

RAG

AMBER

Report for Sept 2018

Achievements in Last Period

Activities in this current phase are aligned with getting WS02 ready to transition Service Management/Production Services.

  • Work has continued with DEV build for WS02, involving activities to ensure network connectivity, configuration of WS02 and load balancing configuration
  • Work has commenced on Security Use Cases

Issues

  • New issue – Network configuration issue currently being investigated
  • Currently reviewing delivery timescale and budget across whole programme

Next Steps

  • Continuing with the technical tasks associated with making WS02 "production" ready.
  • Commence work packages to Develop Service Model
  • Gain agreement regarding Security Use Cases
  • Agree new milestones for project
  • Secure Rikys time in line with proposed new timeline for delivery
  • Agree plan with production (meeting 7.11.18)

 

DTI028 Maturing the API Infrastructure

New Proposed Milestones To Be Confirmed

RAG

AMBER

Report for Sept 2018

Achievements in Last Period

Deliverables regarding Centralised Logging have been more clearly defined and resource booked to complete this deliverable in November.

Several work packages are due to commence in November. (python templates, security scanning).

Issues

  • Resource - potential conflict with John Alison, impact to be assessed

Next Steps

  • There are several deliverables planned in November

    • WP 4.1 - templates for new APIs - Python
    • WP 7.1 - utilise centralised logging - writing to logs
    • WP 7.2 -  utilise centralised logging - reporting from logs
    • Agree new milestones for project

DTI029 Maturing the API Service

New Proposed Milestones To Be Confirmed

RAG

AMBER

Report for August 2018

Achievements in Last Period

  • D5 Sustainability Plan -  Some meetings/discussions have taken place to discuss this deliverable against the backdrop of the need to develop a target operating model , for the implementation and management of the APIs. It is likely we will propose removal of this deliverable to be replaces with Target Operating Model and propose for delivery in next Tranche. This needs further consideration and discussion with the programme sponsor.
  • Events Uitility Booking - The event booking attendance recording tool is currently in development.  A system has been designed which will allow independent tutors to take attendance via a mobile device focusing on direct interactions with an API without the need for complex logins or authorisation.  The infrastructure has been developed and Adrian is currently focusing on providing the components of the API and then developing the mobile first application.

Issues

  • No new issues

Next Steps

  • Secure Software Standard Development is scheduled for Nov (Resource Restrictions)
  • Further discussion regarding Target Operating Model
  • Agree new milestones for project

DTI018 Continuous Service Improvement APIs

Discretionary

Milestones

RAG

AMBER

Report for August  2018

Achievements in Last Period

There has been minimal progress with this project this month, as the Business Analyst assigned to managing the progress of the API’s has come to the end of their contract.

An overall programme review meeting took place on 31.10.18. A follow up meeting specifically regarding this project is planned for 15.11.18. to consider resource and skills requirement for the project going forward.

There are currently 7 proposed API’s in the project. A full review of the API’s is required and these then need to be reprioritised based on resource available and a realistic delivery timeline agreed. This can be reviewed again at end of January, when recruitment on the Service Management Team has taken place.

Last month we identified a need to define the testing & training approach for testers so that UAT can be progress on 4 API’s which are currently awaiting testing. We have made significant progress in developing a testing approach for API’s and this approach will be circulated for approval by the Sponsoring Group within the next week. Separately we will need to agree support and training required  for Application Developer Community to allow use of API's.

Issues

  • New issue - lack of  resource to manage API pipeline
  • Currently reviewing delivery timescale and budget across whole programme

Next Steps

  • Agreement of proposed UAT approach for API's
  • Define support, guidance and training for Software Developers
  • Raise PICCL to change delivery timelines once agreed
  • Analysis of current pipeline
  • Agree new milestones for project
  • Meeting on 18.11.19 to prioritise API's in line with capacity

 

Section Four: Closed, Suspended or Withdrawn Projects

Project Info Project Manager's Commentary
DTI013 Analysis and Specification of Requirements Project closure approved by WIS 2/2/18
DTI014 Enterprise API Technology Project closure approved by WIS 17/11/17
DTI015 Student Record APIs Project closure approved by WIS 1/9/17
DTI016 UCP Pilot API

22/12/17 - Project withdrawal approved by WIS 22/12/17 - PICCL Change 6

6/12/17 - Recommendation is to withdraw and review requirements again in 18/19 due to PICCL Issue 5, project risk 5

13/10/17 - Project suspension approved by WIS 13/10/17 - PICCL Change 4

DTI017 VLE API

Project closure approved by WIS 23/3/18

5/2/18 - Recommendation is to close project early - PICCL Decision 8

6/12/17 - Recommendation is to review conditions for removing project from suspension in 18/19, PICCL Change 7, project risk 10, project risk 11

17/11/17 - Project suspension approved by WIS 17/11/17 - PICCL Change 7

DTI023 Analysis and Requirements Project withdrawal approved by WIS 15/12/17 - PICCL Change 1
DTI024 Maturing Student Record APIs Project closure submitted to WIS 29/6/18
DTI025 Approved Small APIs Project withdrawal approved by WIS 13/10/17 - PICCL Change 1
COM027 Enterprise API Foundation Project closure approved by WIS  9/6/17

Section Five: Actions/Notes from monthly meeting :

 

The next Programme Board meeting is scheduled for 15.11.18

 