Report for Sept 2018
- Report Date
- September 2018
Report compiled by Programme Manager for Programme Owner
Section One: Programme Commentary, RAG and Resources Update
Programme Commentary
Progress has been made across all projects in the Programme this month:
- DTI018 (Continuous Service Improvement APIs) - the business analysis and development work for the prioritised APIs is progressing ; several API's are ready for UAT however approach/guidance for UAT to be determined.
- DTI026 (API Gateway and API Management Tool) - Activities are progressing in order to make WS02 Production ready and handover to BAU.
- DTI028 (Maturing the API Infrastructure) - Work has progressed on delivering a containerised microservice. A containerised API has been delivered into the infrastructure via a java microservice. The outcome brings us closer to a Microservices infrastructure and has also allowed us to understand how to better move into production.
- DTI029 (Maturing the API Service) - Discussions are ongoing regarding a Target Operating Model, its scope and if it should be included in next tranche of programme. API backlog is now being managed through Jira.
- Handover to new Programme Manger Hilary Shand now complete.
- Review of proposed delivery timescales and budget required, in the first instance with Programme Owner (Alex Carter) and Project Delivery Team Leads (Susan Cooke and Peter Pratt). Planned for w/c 12th October.
Overall, the programme is AMBER at this time as the Programme milestone and budget need to be reconsidered.
RAG Status and Forward Look
AMBER - a programme replan is required
Resource Summary
Section Two: Projects Not Started
There are no projects not started.
Section Three: Projects in Progress
Project Info | Project Manager's Commentary |
DTI026 API Gateway and API Management Tool
New Proposed Milestones To Be Confirmed RAG AMBER |
Report for Sept 2018 Achievements in Last PeriodActivities in this current phase are aligned with getting WS02 ready to transition Service Management/Production Services.
Issues
Next Steps
|
DTI028 Maturing the API Infrastructure New Proposed Milestones To Be Confirmed RAG AMBER |
Report for Sept 2018 Achievements in Last PeriodTechnical activities in this period have focused on delivering a containerised API into the infrastructure. This work is significant as through this exploration we can better understand the move to production.
Issues
Next Steps
|
DTI029 Maturing the API Service New Proposed Milestones To Be Confirmed RAG AMBER |
Report for August 2018 Achievements in Last Period
Issues
Next Steps
|
DTI018 Continuous Service Improvement APIs Discretionary Milestones RAG AMBER |
Report for August 2018 Achievements in Last PeriodProgress has continued on managing the API’s approved by the Steering Group. There are currently have 7 proposed API’s in the project. 3are awaiting UAT (Card API, Pure API and HR) one has been deployed to Live (Org Hierarchy). 2 are being triaged (AD and Learn Gradebook Access) and Eugex Schools Feed has been approved to start capturing the requirements in a more detailed form. One API approved for Triage has been withdrawn – Computer Lab Occupancy. This is because an API already exists which can be utilised. We have identified a need to define the training approach for testers so that UAT can progress on 4 API’s which are currently awaiting testing. The backlog is now being pro-actively managed through JIRA. Issues
Next StepsDefine UAT approach, guidance and training
|
Section Four: Closed, Suspended or Withdrawn Projects
Project Info | Project Manager's Commentary |
---|---|
DTI013 Analysis and Specification of Requirements | Project closure approved by WIS 2/2/18 |
DTI014 Enterprise API Technology | Project closure approved by WIS 17/11/17 |
DTI015 Student Record APIs | Project closure approved by WIS 1/9/17 |
DTI016 UCP Pilot API |
22/12/17 - Project withdrawal approved by WIS 22/12/17 - PICCL Change 6 6/12/17 - Recommendation is to withdraw and review requirements again in 18/19 due to PICCL Issue 5, project risk 5 13/10/17 - Project suspension approved by WIS 13/10/17 - PICCL Change 4 |
DTI017 VLE API |
Project closure approved by WIS 23/3/18 5/2/18 - Recommendation is to close project early - PICCL Decision 8 6/12/17 - Recommendation is to review conditions for removing project from suspension in 18/19, PICCL Change 7, project risk 10, project risk 11 17/11/17 - Project suspension approved by WIS 17/11/17 - PICCL Change 7 |
DTI023 Analysis and Requirements | Project withdrawal approved by WIS 15/12/17 - PICCL Change 1 |
DTI024 Maturing Student Record APIs | Project closure submitted to WIS 29/6/18 |
DTI025 Approved Small APIs | Project withdrawal approved by WIS 13/10/17 - PICCL Change 1 |
COM027 Enterprise API Foundation | Project closure approved by WIS 9/6/17 |
Section Five: Actions/Notes from monthly meeting :
The next programme meeting will be scheduled for early November 2018.