Report for July 2018
- Report Date
- July 2018
Report compiled by Programme Manager for Programme Owner
Section One: Programme Commentary, RAG and Resources Update
Programme Commentary
Progress has been made across all projects in the Programme this month:
- DTI018 (Continuous Service Improvement APIs) - the business analysis and development work for the prioritised APIs is progressing ; Card API - development complete, Pure API & HR API - commencing UAT. We have been unable to complete all the implementations within this academic year and as such we are in the process of re-planning and will then raise a PICCL to change the milestones.
- DTI026 (API Gateway and API Management Tool) - The issues raised in PICCL 12 have now been mitigated and work is progressing on D2 (Delivery and setup of infrastructure to support API Gateway and API Management Tool) and D3 (Installation and configuration of WSO2 into the dev, test and live environments). The Build Review has been re-scheduled for 21 August 2018 and the project is scheduled to complete in 2018/19.
- DTI028 (Maturing the API Infrastructure) - A number of work packages scheduled for 2017/18 did not complete and these have been rolled into 2018/19. Also the ENT020 Centralised Logging Project has not delivered required functionality and this will have an impact on the scope of delivery for WP 7.1 - utilise centralised logging - writing to logs and WP 7.2 - utilise centralised logging - reporting from logs. The project is scheduled to complete in 2018/19.
- DTI029 (Maturing the API Service) - A number of work packages scheduled for 2017/18 did not complete due to resource constraints these have been rolled into 2018/19. There was also a dependency on the successful completion of the evaluation of WSO2 (part of deliverable 4.2 in project DTI026 API Gateway and API Management Tool), which has been significantly delayed. The project is still scheduled to complete in 2018/19.
- The new Programme Manager (Tola Odedina) started on 9th July 2018
The high level scope of work for 2018/19 has been agreed. Further work is required on the estimation and planning for 2018/19.
Overall, the programme is AMBER at this time.
RAG Status and Forward Look
Resource Summary
Section Two: Projects Not Started
There are no projects not started.
Section Three: Projects in Progress
Project Info | Project Manager's Commentary | ||||||||||||||
DTI026 API Gateway and API Management Tool Discretionary Milestones
RAG AMBER |
Report for July 2018 Achievements in Last Period
Issues
Next Steps
|
||||||||||||||
DTI028 Maturing the API Infrastructure Discretionary Milestones
RAG AMBER |
Report for July 2018 Achievements in Last Period
IssuesENT020 Centralised Logging Project has not delivered required functionality and this will impact the delivery of WP7.1 and WP7.2 below Next Steps
Notes
|
||||||||||||||
DTI029 Maturing the API Service Discretionary Milestones RAG AMBER |
Report for July 2018 Achievements in Last Period
The following deliverable are categorised as should-have:
Issues
Next Steps
|
||||||||||||||
DTI018 Continuous Service Improvement APIs Discretionary Milestones
RAG AMBER |
Report for July 2018 Achievements in Last PeriodThe Steering Group on 8th May approved the following list of APIs for development, the status of each is shown below:
The Head of Service Management has approved the implementation of three additional APIs. This has been done on the basis of a tactical need to move quickly in order to realise the benefits
Three JIRA boards have been created - one for managing all requests, one for managing withdrawals and one for managing those taken forward for development. Issues
Next Steps
|
Section Four: Closed, Suspended or Withdrawn Projects
Project Info | Project Manager's Commentary |
---|---|
DTI013 Analysis and Specification of Requirements | Project closure approved by WIS 2/2/18 |
DTI014 Enterprise API Technology | Project closure approved by WIS 17/11/17 |
DTI015 Student Record APIs | Project closure approved by WIS 1/9/17 |
DTI016 UCP Pilot API |
22/12/17 - Project withdrawal approved by WIS 22/12/17 - PICCL Change 6 6/12/17 - Recommendation is to withdraw and review requirements again in 18/19 due to PICCL Issue 5, project risk 5 13/10/17 - Project suspension approved by WIS 13/10/17 - PICCL Change 4 |
DTI017 VLE API |
Project closure approved by WIS 23/3/18 5/2/18 - Recommendation is to close project early - PICCL Decision 8 6/12/17 - Recommendation is to review conditions for removing project from suspension in 18/19, PICCL Change 7, project risk 10, project risk 11 17/11/17 - Project suspension approved by WIS 17/11/17 - PICCL Change 7 |
DTI023 Analysis and Requirements | Project withdrawal approved by WIS 15/12/17 - PICCL Change 1 |
DTI024 Maturing Student Record APIs | Project closure submitted to WIS 29/6/18 |
DTI025 Approved Small APIs | Project withdrawal approved by WIS 13/10/17 - PICCL Change 1 |
COM027 Enterprise API Foundation | Project closure approved by WIS 9/6/17 |
Section Five: Actions/Notes from monthly meeting held on 12 Jun 2018:
The purpose of the meeting was to review the May 2018 Enterprise APIs Programme report, issues and risks.
Chris reviewed progress during May and the budget summary and analysis:
- May Programme Report
- Budget Summary and Analysis (circulated by email)
The following summary was noted:
- Good progress has been made across the four live projects in the Programme:
- DTI018 (Continuous Service Improvement APIs) - the Steering Group approved five APIs for development - the design and build of these is underway. The project is scheduled to complete in 2017/18.
- DTI026 (API Gateway and API Management Tool) - the three outstanding issues (issues 7, 10 and 11) are resolved and work on D2 (delivery and setup of infrastructure to support API Gateway and API Management Tool) and D3 (installation and configuration of WSO2 into the dev, test and live environments) has now started. The project is scheduled to complete in 2018/19.
- DTI028 (Maturing the API Infrastructure) - work packages scheduled for 2017/18 are in progress or complete. The project is scheduled to complete in 2018/19.
- DTI029 (Maturing the API Service) - deliverables scheduled for 2017/18 are in progress or complete. The project is scheduled to complete in 2018/19.
- A review of the suspended status of DTI024 (Maturing Student Record APIs) took place in early June and recommended the early closure of this project (PICCL Decision 14)
- The proposed scope of work for 2018/19 was agreed:
-
4 scopes of work:
-
API Gateway – Embed and Optimise (150d)
-
API Infrastructure – Embed and Optimise (100d)
-
API Service – Embed and Optimise (100d)
-
API Developments (319d)
-
Core Systems APIs
-
Continuous Service Improvement APIs
-
Support for other projects to develop new ways of working
-
-
-
-
A new project manager requires to be assigned to the projects from July
-
A new programme manager requires to be assigned to the Programme from July
The following actions were agreed:
[no outstanding actions]
The next programme meeting will be scheduled by the new programme manager in August 2018
Attachment | Size |
---|---|
![]() | 43.09 KB |
![]() | 186.02 KB |