Report for September 2012

Report Date
September 2012

Report compiled by Jamie Thin (IS Apps Programme Manager) for Alex Hyde-Parker (Programme Owner)

 

Section One: Programme Commentary, RAG and Resources Update

 

Work on DAS008 was carried over from 11-12 , due to resource conflicts with higher priority projects in the period May to July 2012.

Progress has now been made, as some dev team resource was made available in August to complete the Technical spec.

 

The agreed DAS programme baseline budget for 2012-13 is 24 days.

 

 

 Section Two: Projects Not Started

 

None

 

Section Three: Projects in Progress

 

 

Project InfoProject Managers Commentary

DAS008

Decommission Alumni Live Database

 

Category: Discretionary

Milestones

End of re-plan - 02-Nov-12

RAG Status

GREEN

 

Report by Stevie Conlon for  Sept 2012 

Achievements Last Period

The  technical spec has been sent to ThankQ (via Dev & Alumni) to allow ThankQ to build the new direct feed from ThankQ to IDM.

(the delivery of this new feed will allow the legacy  ALUMLIVE database to be decommisioned )

Dev & Alumni will discuss priorities with ThankQ , and schedule this work into the forward plan for ThankQ.

Next steps

Once ThankQ have committed to a delivery date, the PM can then book the IS resources  and re-plan project milestones.

Planning meeting with Dev & Alumni by Fri 2nd Nov

 

 

Section Four: Closed or Withdrawn Projects

 

None

 

Documentation

Not available.