Report for July 2019
- Report Date
- July 2019
Section One: Programme Commentary, RAG and Resources Update
Programme Commentary
The final month of 2018-19, and we have a mixed bag of statuses to report, with a Red project, one Green and two blues.
The Red project is the well-known SOA Upgrade (COM043). The deployment to Live in early July threw up some errors which meant rolling back the implementation, and starting the process of investigating where the problems lie. This is still being carried out, with a call into Oracle that will hopefully shed some light on things. The remaining milestones have been redrafted, with the caveat that they are subject to change.
This situation has meant that the IDM Database Upgrade (COM045) has been suspended until October as it has a dependency on the successful completion of COM043. The other Blue project this month is the Wiki Upgrade which was closed at the end of July.
Finally, the JIRA Upgrade (COM047) is reported as Green - it is ticking along, more or less to schedule and we hope to have the Live upgrade in place by late August.
The three open projects will carry over into 19-20, and we will report on the new projects in next month's update.
RAG Status and Forward Look

Resources

Section Two: Projects Not Started
| Project Info | Project Manager's Commentary | ||
|---|---|---|---|
|
|
Section Three: Projects in Progress
| Project Info | Project Manager's Commentary | ||||||||||||||||||
| COM043 SOA Upgrade to v12
Compliance Milestones
RAG Status RED |
Report by Adam Wadee for July 2019 Achievements in Last Period
Issues
Next Steps
RAG Commentary The live deployment of SOA 12 went ahead on Tuesday 9th July, however it was not successful and had to be rolled back. We have not been able to resolve the issues encountered during the deployment, so have raised a support call with the SOA vendor Oracle. Our next opportunity for deploying to live will be in October after the start of term change freeze. The delay is not directly impacting on services for students, but is delaying other projects which are dependent on the SOA upgrade. The delay also means that our IDM service continues to run on a version of SOA which is out of support (11G). The issue has been escalated to the Project Sponsor and senior managers in Applications Directorate. We have also raised the issue with Oracle. We expect to have a fix from Oracle by the end of August which will allow us to prepare for a live deployment in October. |
||||||||||||||||||
|
Compliance Milestones Suspended
RAG Status AMBER. Project delayed due to COM043 SOA upgrade. |
Report by Chris Konczak for July 2019 Achievements in Last Period
Issues
Next Steps
|
||||||||||||||||||
|
COM047 Milestones
RAG Status GREEN
|
Report by Yiwei Jing for July 2019 Achievements
Issues
Next steps
|
Section Four: Closed or Withdrawn Projects
| Project Info | Project Managers Commentary |
|
Project closed - Closure Report
|
|
| COM042 - GDPR Preparation for Applications | Project closed - Closure Report |
| COM044 - Serengeti Annual Upgrade | Project closed - Closure Report |
| COM048 Bi-Annual CalSync Upgrade | Project withdrawn - Decision |
| COM036 - BI Business Objects Upgrade | Project closed - Closure Report |
| COM041 Decommission legacy Windows hosting | Project closed - Closure Report |
| COM046 Annual Wiki Upgrade | Project closed - Closure Report |